About this file

This document is a Request for Proposals (RFP) for an Indefinite Delivery Indefinite Quantity (IDIQ) contract to provide maintenance, repair, and improvement services for Customs and Border Protection's (CBP) tactical infrastructure (TI) assets within the San Diego Sector in California.

The contract will have two execution tiers: 1) Scheduled Maintenance, and 2) Unscheduled Maintenance. The Scheduled Maintenance portion will be firm fixed price, while the Unscheduled Maintenance work valued at $750,000 or less per activity will be fixed unit price task orders. The contract has a one-year base period with four one-year option periods. The total estimated value of the contract is the sum of the program management, the fixed price scheduled maintenance, and the total estimated value of all unscheduled maintenance task orders. This is an 8(a) set-aside procurement. Offerors must complete the provided Line Item Summary and Materials-Equipment-Unit Pricing sheets as part of their price proposal.

View the file

Other files for this federal contract opportunity

Other files attached to CBP San Diego Sector Maintenance, newest first.
File Type Posted
Attachment 8b WD CA20240001 04-05-2024.pdf PDF
Attachment 6 Work Plan Development Process.pptx PPTX presentation
Attachment 5 Work Estimate Form.xlsx XLSX spreadsheet
Attachment 3 Materials-Equipment-Unit_Pricing_Sheet 02022024.xlsx XLSX spreadsheet
Attachment 4 Notional_Plan 2023_01_30.xlsx XLSX spreadsheet
Attachment 7 TI Design Standards.pdf PDF
Attachment 9 Work Activity Report.xlsx XLSX spreadsheet
Attachment 1 SOW 01292024.docx DOCX document
Attachment 8a WD 2015-5635 rev-23 12-26-2023.pdf PDF
Attachment 6 Work Plan Development Process.pdf PDF
70B01C24R00002429 SDC TI Maint - cover.pdf PDF
Attachment 2 Line Item Summary 01222024.xlsx XLSX spreadsheet
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

70B01C24R00002429

SECTION I SCHEDULES

I.1 DESCRIPTION: The anticipated contract is a single-award indefinite delivery / indefinite quantity

(IDIQ) contract with ability to issue firm fixed price task orders and may contain two portions. The first is a firm fixed price portion for scheduled maintenance services at all locations throughout the San Diego Sector. The second is for fixed unit priced task orders for unscheduled repairs valued at $750,000.00 or less per activity ($2,000 for work covered by the Wage Rate Requirements (Construction) statute, 40 U.S.C. chapter 31, Subchapter IV, formerly known as the Davis Bacon Act and $2,500 for work covered by the Service Contract Labor Standards statute, 41 U.S.C. chapter 67, formerly known as the Service Contract Act, Subpart 22.10). Firm fixed price task orders will be awarded in accordance with (IAW) the ordering instructions contained within this contract and the Statement of Work (SOW).

I.2 MINIMUM GUARANTEE: The minimum guarantee is the first task order issued for scheduled maintenance and program management for the base period, which will be issued at the time of award for the IDIQ.

I.3 MAXIMUM AMOUNT: The maximum dollar value of the contract is the sum of the program management, the fixed price scheduled maintenance portion of the contract, and the total estimated value of all task order work for unscheduled maintenance for the one-year base period and four one-year option periods. The maximum will be stated in the awarded contract as the ceiling price (not-to-exceed amount) for all task orders under the IDIQ ordering period. The maximum shall not be exceeded except as may be provided for by formal modification to the contract.

I.4 CONTRACT LINE ITEMS: See Attachments 2 “Line Item Summary” and 3 “Materials-Equipment-

Unit Pricing_Sheet”. The Offeror shall complete Attachment 2 “Line Item Summary” and Attachment 3 “Materials-Equipment-Unit_Pricing_Sheet” as part of their price proposal.

I.5 INDEFINITE QUANTITY (IQ) ESTIMATES: Once the estimated amounts for the IQ work have been reached, additional task orders may be issued as long as the overall not-to-exceed (NTE) amount of the IQ portion of contract for all periods (one-year base period and four one-year option periods is not exceeded and the Contractor agrees by signing the task order(s).

I.6 SCHEDULE OF SUPPLIES/SERVICES: See Attachment 2 “Line Item Summary” for information and applicable periods of performance for the contract.

I.7 The anticipated IDIQ contract does not obligate any funding. The individual Task Orders placed against the contract will obligate the funding. See 52.216-18 Ordering and ORDERING

PROCEDURES - SERVICES (OCT 2007).

SECTION II CONTRACT CLAUSES*

* Construction clauses are only applicable to construction projects and not applicable to projects for commercial items / services. In accordance with the Statement of Work, the Government will indicate if the task order project is Construction or Commercial Services.

II.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.acquisition.gov

I. FEDERAL ACQUISITION REGULATION (48 CHAPTER 1) CLAUSES

NUMBER TITLE

II.2 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020)

II.3 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS

(NOV 2021)

II.4 52.202-1 DEFINITIONS (JUN 2020)

II.5 52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APRIL 1985)

II.6 52.203-3 GRATUITIES (APR 1984)

II.7 52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)

II.8 52.203-7 ANTI-KICKBACK PROCEDURES (JUN 2020)

II.9 52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR

IMPROPER ACTIVITY (MAY 2014)

II.10 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)

II.11 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS

(JUN 2020)

II.12 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT

PAPER (MAY 2011)

II.13 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)

II.14 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020)

II.15 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND

CERTIFICATIONS (DEC 2014)

II.16 52.204-22 ALTERNATIVE LINE ITEM PROPOSAL (JAN 2017)

II.17 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS

(NOV 2015)

II.18 52.209-13 VIOLATIONS OF ARMS CONTROL TREATIES OR AGREEMENTS – CERTIFICATION

(NOV 2021)

II.19 52.212-4 CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS (NOV 2023)

II.20 52.215-2 AUDIT AND RECORDS-NEGOTIATION (JUN 2020)

II.21 52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS – OVERTIME

COMPENSATION (MAY 2018)

II.22 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (AUG 2018)

II.23 52.222-7 WITHHOLDING OF FUNDS (MAY 2014)

II.24 52.222-8 PAYROLLS AND BASIC RECORDS (JUL 2021)

II.25 52.222-9 APPRENTICES AND TRAINEES (JUL 2005)

II.26 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)

II.27 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)

II.28 52.222-12 CONTRACT TERMINATION--DEBARMENT (MAY 2014)

II.29 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND

RELATED REGULATIONS (MAY 2014)

II.30 52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)

II.31 52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)

II.32 52.222-22 PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999)

II.33 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APR

2015)

II.34 52.222–55 MINIMUM WAGES UNDER EXECUTIVE ORDER 14026 (JAN 2022)

II.35 52.222–62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2022)

II.36 52.223-6 DRUG-FREE WORKPLACE (MAY 2001)

II.37 52.227-1 AUTHORIZATION AND CONSENT (JUN 2020)

II.38 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT

(JUN 2020)

II.39 52.227-4 PATENT INEMNITY – CONSTRUCTION CONTRACTS (DEC 2007)

II.40 52.227-23 PROPOSAL DATA (TECHNICAL) (JUN 1987)

II.41 52.228-2 ADDITIONAL BOND SECURITY (OCT 1997) Clause will be incorporated as needed at the Task Order level.

II.42 FAR 52.228-5 INSURANCE-WORK OF A GOVERNMENT INSTALLATION (JAN 1997)

II.43 52.228-11 PLEDGES OF ASSETS (FEB 2021)

II.44 52.228-12 PROSPECTIVE SUBCONTRACTORS REQUEST FOR BONDS (DEC 2022)

II.45 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JUL 2000)

II.46 52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)

II.47 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION (JUN 2020) See deviation at II.122

II.48 52.229-4 FEDERAL, STATE, AND LOCAL TAXES (STATE AND LOCAL ADJUSTMENTS) (FEB

2013)

II.49 52.232-17 INTEREST (MAY 2014)

II.50 52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)

II.51 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)

II.52 52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)

II.53 52.233-1 DISPUTES (MAY 2014)

II.54 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)

II.55 52.236-2 DIFFERING SITE CONDITIONS (APR 1984)

II.56 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)

II.57 52.236-4 PHYSICAL DATA (APR 1984)

II.58 52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)

II.59 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)

II.60 52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)

II.61 52.236-8 OTHER CONTRACTS (APR 1984)

II.62 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984)

II.63 52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)

II.64 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)

II.65 52.236-12 CLEANING UP (APR 1984)

II.66 52.236-13 ACCIDENT PREVENTION (NOV 1991)

II.67 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACT (APR 1984)

II.68 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)

II.69 52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)

II.70 52.236-28 PREPARATION OF PROPOSALS-CONSTRUCTION (OCT 1997)

II.71 52.242-13 BANKRUPTCY (JUL 1995)

II.72 52.242.14 SUSPENSION OF WORK (APR 1984)

II.73 52.243-4 CHANGES (JUN 2007)

II.74 52.244-5 COMPETITION IN SUBCONTRACTING (DEC 1996)

II.75 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

II.76 52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)

II.77 52.248-3 VALUE ENGINEERING – CONSTRUCTION (OCT 2020)

II.78 52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT ALT I (SEPT 1996)

II.79 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)

II.80 52.253-1 COMPUTER GENERATED FORMS (JAN 1991)

II.81 52.225-9 BUY AMERICAN--CONSTRUCTION MATERIALS (OCT 2022)

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material.

The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together.

Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

_None_[Contracting Officer to list applicable excepted materials or indicate "none"]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description Unit of Quantity Price Measure (Dollars)* Item 1:

Foreign construction material ________ ________ ________ Domestic construction material ________ ________ ________

Item 2:

Foreign construction material ________ ________ ________ Domestic construction material ________ ________ ________

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response, if oral, attach summary.] [Include other applicable supporting information.] [*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate is issued).]

(End of clause)

II.82 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within time period specified in the order (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the date specified in the order.* The time stated for completion shall include final cleanup of the premises.

II.83 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR

EXECUTIVE ORDERS—COMMERCIAL ITEM (FEB 2024)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (DEC 2023) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015).

(5) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (MAR

2023) ( 31 U.S.C. 3903 and 10 U.S.C. 3801).

(6) 52.233-3, Protest After Award (AUG 1996) ( 31 U.S.C. 3553).

(7) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 ( 19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.]

_X_ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (JUN

2020), with Alternate I (NOV 2021) ( 41 U.S.C. 4704 and 10 U.S.C. 4655).

_X_ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (NOV

2021) ( 41 U.S.C. 3509)).

__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

_X_ (4) 52.203-17, Contractor Employee Whistleblower Rights (NOV 2023) ( 41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community—see FAR 3.900(a).

_X_ (5) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN

2020) (Pub. L. 109-282) ( 31 U.S.C. 6101 note).

__ (6) [Reserved].

_X_ (7) 52.204-14, Service Contract Reporting Requirements (OCT 2016) (Pub. L. 111-117, section 743 of Div. C).

_X_ (8) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (OCT 2016) (Pub. L. 111-117, section 743 of Div. C).

_X_ (9) 52.204-27, Prohibition on a ByteDance Covered Application (JUN 2023) (Section 102 of Division R of Pub. L. 117-328).

(10) 52.204–28, Federal Acquisition Supply Chain Security Act Orders—Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts. (DEC 2023) ( Pub. L.

115–390, title II).

__ (11)

(i) 52.204–30, Federal Acquisition Supply Chain Security Act Orders—Prohibition. (DEC

2023) ( Pub. L. 115–390, title II).

__ (ii) Alternate I (DEC 2023) of 52.204–30.

_X_ (12) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021) ( 31 U.S.C. 6101 note).

_X_ (13) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) ( 41 U.S.C. 2313).

__ (14) [Reserved].

__ (15) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (OCT 2022) ( 15 U.S.C. 657a).

__ (16) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (OCT 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer) ( 15 U.S.C. 657a).

__ (17) [Reserved]

__ (18)

(i) 52.219-6, Notice of Total Small Business Set-Aside (NOV 2020) ( 15 U.S.C. 644).

__ (ii) Alternate I (MAR 2020) of 52.219-6.

__ (19)

(i) 52.219-7, Notice of Partial Small Business Set-Aside (NOV 2020) ( 15 U.S.C. 644).

__ (ii) Alternate I (MAR 2020) of 52.219-7.

_X_ (20) 52.219-8, Utilization of Small Business Concerns (FEB 2024) ( 15 U.S.C. 637(d)(2) and (3)).

__ (21)

(i) 52.219-9, Small Business Subcontracting Plan (SEP 2023) ( 15 U.S.C. 637(d)(4)).

__ (ii) Alternate I (NOV 2016) of 52.219-9.

__ (iii) Alternate II (NOV 2016) of 52.219-9.

__ (iv) Alternate III (JUN 2020) of 52.219-9.

__ (v) Alternate IV (SEP 2023) of 52.219-9.

__ (22)

(i) 52.219-13, Notice of Set-Aside of Orders (MAR 2020) ( 15 U.S.C. 644(r)).

__ (ii) Alternate I (MAR 2020) of 52.219-13.

_X_ (23) 52.219-14, Limitations on Subcontracting (OCT 2022) ( 15 U.S.C. 637s). NOTE: See Deviated version of clause below

__ (24) 52.219-16, Liquidated Damages—Subcontracting Plan (SEP

2021) ( 15 U.S.C. 637(d)(4)(F)(i)).

__ (25) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (FEB

2024) ( 15 U.S.C. 657f).

_X_ (26)

(i) 52.219-28, Post Award Small Business Program Rerepresentation (FEB

2024)( 15 U.S.C. 632(a)(2)).

__ (ii) Alternate I (MAR 2020) of 52.219-28.

__ (27) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (OCT 2022) ( 15 U.S.C. 637(m)).

__ (28) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (OCT 2022) ( 15 U.S.C. 637(m)).

__ (29) 52.219-32, Orders Issued Directly Under Small Business Reserves (MAR

2020) ( 15 U.S.C. 644(r)).

__ (30) 52.219-33, Nonmanufacturer Rule (SEP 2021) ( 15U.S.C. 637(a)(17)).

_X_ (31) 52.222-3, Convict Labor (JUN 2003) (E.O.11755).

_X_ (32) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (FEB 2024) .

_X_ (33) 52.222-21, Prohibition of Segregated Facilities (APR 2015).

_X_ (34)

(i) 52.222-26, Equal Opportunity (SEP 2016) (E.O.11246).

__ (ii) Alternate I (FEB 1999) of 52.222-26.

_X_ (35)

(i) 52.222-35, Equal Opportunity for Veterans (JUN 2020) ( 38 U.S.C. 4212).

__ (ii) Alternate I (JUL 2014) of 52.222-35.

_X_ (36)

(i) 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020) ( 29 U.S.C. 793).

__ (ii) Alternate I (JUL 2014) of 52.222-36.

_X_ (37) 52.222-37, Employment Reports on Veterans (JUN 2020) ( 38 U.S.C. 4212).

__ (38) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC

2010) (E.O. 13496).

__ (39)

(i) 52.222-50, Combating Trafficking in Persons (NOV 2021) ( 22 U.S.C. chapter 78 and E.O.

13627).

__ (ii) Alternate I (MAR 2015) of 52.222-50 ( 22 U.S.C. chapter 78 and E.O. 13627).

_X_ (40) 52.222-54, Employment Eligibility Verification (MAY 2022) (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)

__ (41)

(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (May 2008) ( 42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (ii) Alternate I (MAY 2008) of 52.223-9 ( 42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (42) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) (E.O. 13693).

__ (43) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (JUN 2016) (E.O. 13693).

__ (44)

(i) 52.223-13, Acquisition of EPEAT®-Registered Imaging Equipment (JUN 2014) (E.O.s 13423 and 13514).

__ (ii) Alternate I (OCT 2015) of 52.223-13.

__ (45)

(i) 52.223-14, Acquisition of EPEAT®-Registered Televisions (JUN 2014) (E.O.s 13423 and 13514).

__ (ii) Alternate I (Jun2014) of 52.223-14.

__ (46) 52.223-15, Energy Efficiency in Energy- Consuming Products (MAY 2020) ( 42 U.S.C. 8259b).

__ (47)

(i) 52.223-16, Acquisition of EPEAT®-Registered Personal Computer Products (OCT

2015) (E.O.s 13423 and 13514).

__ (ii) Alternate I (JUN 2014) of 52.223-16.

_X_ (48) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN

2020) (E.O. 13513).

__ (49) 52.223-20, Aerosols (JUN 2016) (E.O. 13693).

__ (50) 52.223-21, Foams (Jun2016) (E.O. 13693).

__ (51)

(i) 52.224-3 Privacy Training (JAN 2017) (5 U.S.C. 552 a).

__ (ii) Alternate I (JAN 2017) of 52.224-3.

_X_ (52)

(i) 52.225-1, Buy American-Supplies (OCT 2022) ( 41 U.S.C. chapter 83).

__ (ii) Alternate I (OCT 2022) of 52.225-1.

__ (53)

(i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (NOV 2023) ( 19 U.S.C.

3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, 19 U.S.C. chapter 29 (sections 4501-4732), Public Law 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109- 283, 110-138, 112-41, 112-42, and 112-43.

__ (ii) Alternate I [Reserved].

__ (iii) Alternate II (DEC 2022) of 52.225-3.

__ (iv) Alternate III (FEB 2024) of 52.225-3.

__ (v) Alternate IV (Oct 2022) of 52.225-3.

__ (54) 52.225-5, Trade Agreements (NOV 2023) ( 19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

_X_ (55) 52.225-13, Restrictions on Certain Foreign Purchases (FEB 2021) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

__ (56) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).

__ (57) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) ( 42 U.S.C. 5150).

__ (58) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov2007) ( 42 U.S.C. 5150).

__ (59) 52.229-12, Tax on Certain Foreign Procurements (FEB 2021).

__ (60) 52.232-29, Terms for Financing of Purchases of Commercial Products and Commercial Services (NOV 2021) ( 41 U.S.C. 4505, 10 U.S.C. 3805).

__ (61) 52.232-30, Installment Payments for Commercial Products and Commercial Services (NOV 2021) ( 41 U.S.C. 4505, 10 U.S.C. 3805).

_X_ (62) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (OCT2018) ( 31 U.S.C. 3332).

__ (63) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (Jul 2013) ( 31 U.S.C. 3332).

__ (64) 52.232-36, Payment by Third Party (MAY 2014) ( 31 U.S.C. 3332).

__ (65) 52.239-1, Privacy or Security Safeguards (AUG 1996) ( 5 U.S.C. 552a).

_X_ (66) 52.242-5, Payments to Small Business Subcontractors (JAN

2017) ( 15 U.S.C. 637(d)(13)).

__ (67)

(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (NOV 2021) ( 46 U.S.C. 55305 and 10 U.S.C. 2631).

__ (ii) Alternate I (APR 2003) of 52.247-64.

__ (iii) Alternate II (NOV 2021) of 52.247-64.

(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.]

_X_ (1) 52.222-41, Service Contract Labor Standards (AUG 2018) ( 41 U.S.C. chapter67).

_X_ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (MAY 2014) ( 29 U.S.C. 206 and 41 U.S.C. chapter 67).

_X_ (3) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts) (AUG 2018) ( 29 U.S.C. 206 and 41 U.S.C. chapter 67).

__ (4) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (May 2014) ( 29U.S.C.206 and 41 U.S.C. chapter 67).

__ (5) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) ( 41 U.S.C. chapter 67).

__ (6) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (MAY 2014) ( 41 U.S.C. chapter 67).

_X_ (7) 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026 (JAN

2022).

_X_ (8) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2022) (E.O. 13706).

__ (9) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (Jun 2020) ( 42 U.S.C. 1792).

(d) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, as defined in FAR 2.101, on the date of award of this contract, and does not contain the clause at 52.215-2, Audit and Records-Negotiation.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(e)

(1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), (c), and (d) of this clause, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (e)(1), in a subcontract for commercial products or commercial services. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause-

(i) 52.203-13, Contractor Code of Business Ethics and Conduct (NOV

2021) ( 41 U.S.C. 3509).

(ii) 52.203-17, Contractor Employee Whistleblower Rights (NOV 2023) ( 41 U.S.C. 4712).

(iii) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(iv) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by KasperskyLab Covered Entities (DEC 2023) (Section 1634 of Pub. L. 115-91).

(v) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(vi) 52.204-27, Prohibition on a ByteDance Covered Application (JUN 2023) (Section 102 of Division R of Pub. L. 117-328).

(vii)

(A) 52.204–30, Federal Acquisition Supply Chain Security Act Orders—Prohibition. (DEC

2023) ( Pub. L. 115–390, title II).

(B) Alternate I (DEC 2023) of 52.204–30.

(viii) 52.219-8, Utilization of Small Business Concerns (FEB 2024) ( 15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds the applicable threshold specified in FAR 19.702(a) on the date of subcontract award, the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.

(ix) 52.222-21, Prohibition of Segregated Facilities (APR 2015).

(x) 52.222-26, Equal Opportunity (SEP 2015) (E.O.11246).

(xi) 52.222-35, Equal Opportunity for Veterans (JUN 2020) ( 38 U.S.C. 4212).

(xii) 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020) ( 29 U.S.C. 793).

(xiii) 52.222-37, Employment Reports on Veterans (JUN 2020) ( 38 U.S.C. 4212).

(xiv) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC

2010) (E.O. 13496). Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.

(xv) 52.222-41, Service Contract Labor Standards (AUG 2018) ( 41 U.S.C. chapter 67).

(xvi)

(A) 52.222-50, Combating Trafficking in Persons (NOV 2021) ( 22 U.S.C. chapter 78 and E.O 13627).

(B) Alternate I (MAR 2015) of 52.222-50 ( 22 U.S.C. chapter 78 and E.O. 13627).

(xvii) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) ( 41 U.S.C. chapter 67).

(xviii) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (MAY 2014) ( 41 U.S.C. chapter 67).

(xix) 52.222-54, Employment Eligibility Verification (MAY 2022) (E.O. 12989).

(xx) 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026 (JAN

2022).

(xxi) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2022) (E.O. 13706).

(xxii)

(A) 52.224-3, Privacy Training (Jan 2017) ( 5 U.S.C. 552a).

(B) Alternate I (JAN 2017) of 52.224-3.

(xxiii) 52.225-26, Contractors Performing Private Security Functions Outside the United States (OCT 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).

(xxiv) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (JUN

2020) ( 42 U.S.C. 1792). Flow down required in accordance with paragraph (e) of FAR clause 52.226-6.

(xxv) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) ( 31 U.S.C. 3903 and 10 U.S.C. 3801). Flow down required in accordance with paragraph (c) of 52.232-40.

(xxvi) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (NOV

2021) ( 46 U.S.C. 55305 and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247-64.

(2) While not required, the Contractor may include in its subcontracts for commercial products and commercial services a minimal number of additional clauses necessary to satisfy its contractual obligations.

(End of clause)

II.84 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (FEB 2024)

(a) Definitions. As used in this clause—

Commercial product, commercial service and commercially available off-the-shelf item have the meanings contained in Federal Acquisition Regulation (FAR) 2.101.

Subcontract includes a transfer of commercial products or commercial services between divisions, subsidiaries, or affiliates of the Contractor or subcontractor at any tier.

(b) To the maximum extent practicable, the Contractor shall incorporate, and require its subcontractors at all tiers to incorporate, commercial products, commercial services, or non-developmental items as components of items to be supplied under this contract.

(c) (1) The Contractor shall insert the following clauses in subcontracts for commercial products or commercial services:

(i) 52.203-13, Contractor Code of Business Ethics and Conduct (Nov 2021) ( 41 U.S.C. 3509), if the subcontract exceeds the threshold specified in FAR 3.1004(a) on the date of subcontract award, and has a performance period of more than 120 days. In altering this clause to identify the appropriate parties, all disclosures of violation of the civil False Claims Act or of Federal criminal law shall be directed to the agency Office of the Inspector General, with a copy to the Contracting Officer.

(ii) 52.203-15, Whistleblower Protections Under the American Recovery and Reinvestment Act of

2009 (Jun 2010) (Section 1553 of Pub. L. 111-5), if the subcontract is funded under the Recovery Act.

(iii) 52.203-17, Contractor Employee Whistleblower Rights (Nov 2023) ( 41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community—see FAR 3.900(a).

(iv) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

(Jan 2017).

(v) 52.204-21, Basic Safeguarding of Covered Contractor Information Systems (Nov 2021) , other than subcontracts for commercially available off-the-shelf items, if flow down is required in accordance with paragraph (c) of FAR clause 52.204-21.

(vi) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab Covered Entities (Dec 2023) (Section 1634 of Pub. L. 115-91).

(vii) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance

Services or Equipment. (Nov 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(viii) 52.204-27, Prohibition on a ByteDance Covered Application (Jun 2023) (Section 102 of Division

R of Pub. L. 117-328).

(ix) (A) 52.204–30, Federal Acquisition Supply Chain Security Act Orders—Prohibition. (Dec 2023)

(Pub. L. 115–390, title II).

(B) Alternate I (Dec 2023) of 52.204–30.

(x) 52.219-8, Utilization of Small Business Concerns (Feb 2024) (15 U.S.C.637(d)(2) and (3)), if the subcontract offers further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds the applicable threshold specified in FAR 19.702(a) on the date of subcontract award, the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.

(xi) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).

(xii) 52.222-26, Equal Opportunity (Sept 2016) (E.O.11246).

(xiii) 52.222-35, Equal Opportunity for Veterans (Jun 2020) (38 U.S.C.4212(a));

(xiv) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020)( 29 U.S.C.793).

(xv) 52.222-37, Employment Reports on Veterans (Jun 2020) (38 U.S.C.4212).

(xvi) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010)

(E.O. 13496), if flow down is required in accordance with paragraph (f) of FAR clause 52.222-40.

(xvii) (A) 52.222-50, Combating Trafficking in Persons (Nov 2021) (22 U.S.C. chapter 78 and E.O.

13627).

(B) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

(xviii) 52.222-55, Minimum Wages for Contractor Workers under Executive Order 14026 (Jan 2022), if flow down is required in accordance with paragraph (k) of FAR clause 52.222-55.

(xix) 52.222-62, Paid Sick Leave Under Executive Order 13706 (Jan 2022) (E.O. 13706), if flow down is required in accordance with paragraph (m) of FAR clause 52.222-62.

(xx) (A) 52.224-3, Privacy Training (Jan 2017) ( 5 U.S.C. 552a) if flow down is required in accordance with 52.224-3(f).

(B) Alternate I (Jan 2017) of 52.224-3, if flow down is required in accordance with 52.224-3(f) and the agency specifies that only its agency-provided training is acceptable).

(xxi) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct

2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).

(xxii) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) , if flow down is required in accordance with paragraph (c) of FAR clause 52.232-40.

(xxiii) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Nov 2021) ( 46

U.S.C. 55305 and 10 U.S.C.2631), if flow down is required in accordance with paragraph (d) of FAR clause 52.247-64.

(2) While not required, the Contractor may flow down to subcontracts for commercial products or commercial services a minimal number of additional clauses necessary to satisfy its contractual obligations.

(d) The Contractor shall include the terms of this clause, including this paragraph (d), in subcontracts awarded under this contract.

II.85 52.204-23 - PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES

DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018)

(DEVIATION 20-05)

(a) Definitions. As used in this clause –

“Covered article” means any hardware, software, or service that–

(1) Is developed or provided by a covered entity;

(2) Includes any hardware, software, or service developed or provided in whole or in part by a covered entity; or

(3) Contains components using any hardware or software developed in whole or in part by a covered entity.

“Covered entity” means –

(1) Kaspersky Lab;

(2) Any successor entity to Kaspersky Lab;

(3) Any entity that controls, is controlled by, or is under common control with Kaspersky Lab; or

(4) Any entity of which Kaspersky Lab has a majority ownership.

(b) Prohibition. Section 1634 of Division A of the National Defense Authorization Act for Fiscal Year 2018

(Pub. L. 115-91) prohibits Government use of any covered article. The Contractor is prohibited from—

(1) Providing any covered article that the Government will use on or after October 1, 2018; and

(2) Using any covered article on or after October 1, 2018, in the development of data or deliverables first produced in the performance of the contract.

(c) Reporting requirement.

(1) In the event the Contractor identifies a covered article provided to the Government during contract performance, or the Contractor is notified of such by a subcontractor at any tier or any other source, the Contractor shall report, in writing via email, to the Contracting Officer, Contracting Officer’s Representative, and the Enterprise Security Operations Center (SOC) at NDAA_Incidents@hq.dhs.gov, with required information contained in the body of the email. In the case of the Department of Defense, the Contractor shall report to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Enterprise SOC, Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) and Contracting Officer’s Representative(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.

(2) The Contractor shall report the following information pursuant to paragraph (c)(1) of this clause:

(i) Within 1 business day from the date of such identification or notification: the contract number; the order number(s), if applicable; supplier name; brand; model number (Original Equipment Manufacturer (OEM) number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.

(ii) Within 10 business days of submitting the report pursuant to paragraph (c)(1) of this clause: any further available information about mitigation actions undertaken or recommended. In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of a covered article, any reasons that led to the use or submission of the covered article, and any additional efforts that will be incorporated to prevent future use or submission of covered articles.

(d) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts, including subcontracts for the acquisition of commercial items.

II.86 52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND

VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (DEVIATION 20-05) (DEC 2020)

(a) Definitions. As used in this clause --

“Backhaul” means intermediate links between the core network, or backbone network, and the small subnetworks at the edge of the network (e.g., connecting cell phones/towers to the core telephone network). Backhaul can be wireless (e.g., microwave) or wired (e.g., fiber optic, coaxial cable, Ethernet).

“Covered foreign country” means The People’s Republic of China.

“Covered telecommunications equipment or services” means --

(1) Telecommunications equipment produced by Huawei…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .