7-SCOPE OF WORK.pdf

PDF 3 MB Posted

Attached to
26B-025 Southeastern Livestock Pavilion Grandstand Repair
Solicitation number
26B-025
Issued by
Marion County, Orlando City, Florida

About this file

Summary of Scope of Work for SELP Grandstands Repair

This scope of work document outlines the repair and renovation requirements for metal grandstands at Southeastern Livestock Pavilion (SELP) in Ocala, Florida, as defined by the Marion County Parks & Recreation Department. The project involves comprehensive repairs to the steel support structure and complete replacement of handrails in the front arena grandstands located at 2232 NW Jacksonville Road. The required work includes replacing one vertical angle member, replacing bent or kinked bracing angles, repairing broken welds, replacing and tightening fasteners with new stainless steel or galvanized hardware, sandblasting and repainting all steel supporting systems, and fabricating and installing new 42-inch-high metal handrails with gray powder-coated finish. All welding must be performed by certified welders in accordance with AWS D1.1 standards and inspected by a licensed structural engineer. The project timeline allows for 60 calendar days to substantial completion and 15 calendar days to final completion from the notice to proceed, with work scheduled Monday through Friday from 8:00 AM to 5:00 PM. A pre-bid walkthrough is recommended and will be conducted prior to the proposal due date, with a pre-construction meeting to be held after contract execution and prior to work commencement.

The contractor shall be responsible for obtaining all permits, adhering to applicable construction codes and regulations of the City of Ocala and State of Florida, and providing all materials, labor, and equipment necessary for completion. Painting specifications include SSPC-SP6 commercial blast cleaning followed by application of Rust-Oleum Zinsser Bulls Eye 123 Primer and Sherwin Williams 6454 Shamrock oil-based paint in accordance with manufacturer specifications. All new handrails must be fabricated from steel with engineered shop drawings sealed by a Florida professional engineer verifying compliance with current Florida Building Code requirements. The contractor must maintain a clean and safe work area, remove all debris daily, protect surrounding areas from sandblast debris and paint splatter, and assume responsibility for any damage caused by negligence. The Marion County Parks & Recreation Department will coordinate work areas and event schedule requirements with the SELP Manager.

View the file

Other files

File Type Posted
3-DISCLOSURE OF SUBCONTRACTORS AND SUPPLIERS.pdf PDF
6-LOCATION MAP.pdf PDF
1-ITB - GENERAL TERMS AND CONDITIONS.pdf PDF
5-BID BOND FORM.pdf PDF
4-SIMILAR WORK DETAIL FORM.pdf PDF
2-VENDOR INFORMATION FORM.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Marion County Parks & Recreation Department SELP Grandstands Repair ∙ Dave Baillie Jr Arena

Marion County Parks & Recreation Department is seeking the best-qualified contractor to repair the metal grandstands in the front arena at Southeastern Livestock Pavilion, which is located at 2232 NW Jacksonville Road, Ocala, FL 34470.

Background and Observations On August 15th, 2023, a structural observation was conducted by Hobson Structural Engineering for the grandstands in the Front Arena at Southeastern Livestock Pavilion.

The following are statements provided by Hobson Structural Engineering:,

• There are two sets of bleachers at the referenced project constructed using steel angles, wide flanges, and pipe columns. The majority, if not all, of the connections in the structure are made using welds.

• The benches, risers, and walkways are a mix of aluminum and wooden planks held to the structure below with bolts or hidden fasteners.

• The overall “feel” of stability of the structure i.e., motion induced movements or deflections, trip hazards, broken or missing pieces, and damaged structural members withing the framing was also observed. The grandstands felt sound overall.

• The seats and walkways appeared straight and level. Most of the planking used for the seats and walkways was in good condition.

• A few of the aluminum planks appear to have had the fasteners come lose.

• The structural steel members were in good condition except for a few braces that were bent, a kinked vertical compression member, and one brace which was noticed to have had the welded end connection broken.

• Members that are severely bent out of plane or kinked should be replaced as the steel cannot be reshaped after being deformed.

• There was widespread corrosion located throughout both bleacher structures. None of the corrosion appeared to be at a concerning level but should be addressed to prolong the life of the structure.

• The corrosion should be cleaned/removed by blasting media or mechanical means and then recoated with appropriate paint.

Scope of Work

Intent

• The required work consists of repairing and painting the support system and replacing all handrails, (excluding the platform handrails), for the metal grandstands in the front arena at the Southeastern Livestock Pavilion. This scope includes only the grandstand steel framing and associated braces identified in Exhibit A. Work excludes any structural members not identified in the structural observation report unless additional deterioration is discovered and the additional work is approved by the Project Manager.

Code

• The contractor shall be responsible for obtaining all permits and adhere to all licensing requirements.

• The contractor shall conform to all applicable construction codes, ordinances, laws and regulations of the City of Ocala and the State of Florida.

General

• Prior to submitting a bid, it is highly recommended that the prospective contractor visits the site and become thoroughly familiar with all pertinent conditions.

• A pre-bid walk-through will be conducted at the project site with all interested contractors prior to the proposal due date. At that time, questions related to the areas of work can be presented and discussed.

• A pre-construction meeting shall be held at the project site after execution of the contract and prior to commencement of the work.

• Contractor shall provide a construction schedule to Parks & Recreation for approval no later than two days after receiving a Notice to Proceed.

• Contractor shall maintain a clean and safe work area throughout construction.

• Contractor shall, at the end of each workday, remove all debris, hazardous and potentially dangerous materials.

• Material Staging Area shall be determined by Project Manager.

• Contractor shall meet the requirements of completing the project as stipulated or implied.

Structural Repairs Contractor shall perform the following structural repairs in accordance with Exhibit A:

• Replace (1) vertical angle (Recommendation 1)

• Replace bracing angles that bent out of shape, or kinked (Recommendation 2)

• Repair broken welds or similar conditions (Recommendation 3)

• Replace and tighten fasteners using new stainless steel or galvanized fasteners at periodic intervals of supporting members (Recommendation 5)

• All welding shall be performed by certified welders in accordance with AWS D1.1 standards.

• All welds shall be inspected by a licensed structural engineer prior to acceptance.

• Contractor shall provide a written inspection and repair summary to the Project Manager.

Painting

• Contractor shall remove all wood seating and decking planks prior to painting and reinstall them with new stainless steel or galvanized fasteners.

• Contractor shall replace any damaged wood planks.

• Sandblast all steel supporting systems and components in accordance with SSPC-SP6

(commercial blast cleaning) and repaint the structure as identified in Exhibit A - Recommendation 4.

• The contractor shall protect all ground and adjacent assets from sandblast debris, remove debris from the site, and dispose of waste materials in compliance with FDEP regulations.

• Any damage to adjacent areas or assets caused by negligence during sandblasting shall be repaired at contractor’s expense.

• Contractor shall prime and paint with industrial grade, exterior-use coatings suitable for structural steel; approved systems include:

o Primer – one (1) coat; Rust-Oleum Zinsser® Bulls Eye 123 Primer; Gray o Paint – two (2) coats; Sherwin Williams 6454 Shamrock; oil base paint

• Contractor shall prime and paint all exposed edges of steel beams, columns, braces and supports.

• Contractor shall adhere to all manufacturers’ written instructions and recommendations in the technical data sheet for application and minimum dry film thickness.

• Contractor shall cover and protect the ground in the immediate work area from paint splatter.

• Contractor shall promptly clean up any paint drips or splatters caused by the work.

• Work shall not be performed when surfaces are damp, or when adverse weather conditions exist or threaten.

• Do not paint light fixtures, fans, signage, wood fencing, electrical panels and conduits, downspouts or arena roof columns.

Handrails

• Contractor shall remove and dispose of all existing wood and chain-link handrails, including wood planks, angle braces, chain-link fencing, and fasteners.

• Contractor shall fabricate and install new 42-inch-high metal handrails that meet the following requirements:

o Color: Gray; powder coated o Top rail, bottom rail and posts: 1-1/2” Diameter tubular o Vertical pickets: 5/8“ Diameter tubular o Post spacing: 6’-0” O.C.

o Material: Steel o Openings: 4” maximum o Connection: Handrail shall be secured to the existing grandstand support structure o Fasteners: Stainless steel or galvanized

• Contractor shall submit engineered shop drawings sealed by a Florida professional engineer verifying compliance with the current Florida Building Code (FBC) for guardrail and handrail load requirements.

• Contractor shall field verify conditions prior to fabrication.

Schedule of Work

• 60 calendars days to Substantial Completion + 15 calendar days to Final Completion from the Notice to Proceed.

• Work schedule: Monday thru Friday 8:00 AM – 5:00 PM

• Contractor shall provide a detailed construction sequencing plan identifying daily work areas and phasing to minimize disruptions and maintain site safety.

Contractor Responsibility The Contractor shall:

1. Schedule a visit with Parks & Recreation Department to identify any conditions during construction that may affect cost, progress, and work performance.

2. Coordinate with Parks & Recreation Department prior to any work being performed.

3. Provide all materials, labor and equipment necessary to complete the work.

4. Have all applicable licenses and be able to comply with all applicable local, state, and federal laws and regulations that apply to the proposed construction.

5. Be responsible for any damage to equipment, facilities, and utilities that occurs due to their negligence.

6. Contractor shall be responsible for receiving, storing, and securing all materials, equipment and other items to be used in accomplishing the work.

7. Contractor shall be responsible for all equipment and materials brought onto the project site and shall replace damaged or stolen items at its expense.

8. Ensure the project site is protected from pedestrians and non-essential construction vehicles by means of caution tape and/or protective fencing in order to provide a safe working environment for construction and non-construction personnel.

County Responsibility The Marion County Parks & Recreation Department shall coordinate with the SELP Manager for approved work areas and event schedule requirements.

Plans & Details Exhibit A - Observations of Bleachers, Southeastern Livestock Pavilion (SELP) Performed by Hobson Structural Engineering, PA

Exhibit B - Site Plan Performed by Marion County Parks & Recreation

Photograph No. 7 – Wooden handrail

Photograph No. 8 – Chain-Link handrail

H o b s o n S t r u c t u r a l E n g i n e e r i n g, P. A.

P.O. Box 3972 · Seminole · Florida · 33775

(850) 933 - 4819

August 15, 2023

Marion County Board of County Commissioners 2602 SE Eighth St.

Ocala, FL 34471

Attn: Jared Goodspeed, Director ǀ Facilities Management

Re: Observations of Bleachers Southeastern Livestock Pavilion (SELP) Ocala, FL

Dear Mr. Goodspeed, This report is being provided to document our findings and recommendations toward the bleacher structures at the referenced property above.

I. Introduction

Per your request, a representative of this office provided a site visit to SELP to perform a visual observation of the bleacher structures and provide our opinion on the structure’s overall condition.

II. Background and Observations

There are two sets of bleachers at the referenced project constructed using steel angles, wide flanges, and pipe columns. The majority, if not all, of the connections in the structure are made using welds. The benches, risers, and walkways are a mix of aluminum and wooden planks held to the structure below with bolts or hidden fasteners.

During the site visit we walked the top side of the bleachers and underneath. We were looking for the overall “feel” of stability of the structure i.e., motion induced movements or deflections, trip hazards, broken or missing pieces, and damaged structural members withing the framing. The bleachers felt sound overall. The seats and walkways appeared straight and level. Most of the planking used for the seats and walkways was in good condition. A few of the aluminum planks appear to have had the fasteners come lose. Maintenance should periodically check for loose or missing fasteners and tighten or replace as required.

The structural steel members were in good condition save a few braces that were bent, a kinked vertical compression member, and one brace which was noticed to have had the welded end connection broken. Members that are severely bent out of plane or kinked should be replaced as the steel cannot be reshaped after being deformed. There

EXHIBIT A

OBSERVATIONS OF BLEACHERS

was widespread corrosion located throughout both bleacher structures. None of the corrosion appeared to be at a concerning level but should be addressed to prolong the life of the structure. The corrosion should be cleaned/removed by blasting media or mechanical means and then recoated with an appropriate paint.

III. Field Photographs

Photograph No. 1 – East side bleachers. Note the wooden planks used for walkway and seats.

Photograph No. 2 – East bleacher walkway. Note that the walkway uses aluminum planks/decking. Some the planks bowed under weight indicating that they are most likely missing fasteners.

Photograph No. 3 – Typical view of the framing beneath the bleacher. Structure is composed of mostly angles.

Photograph No. 4 – Another view of the framing beneath the bleachers. Upper level framing is similar to the lower level and is supported by two columns lines with wide flange steel beams.

Photograph No. 5 – Vertical angle member that has twisted and deformed. This angle should be repaired. Multiple options of repair exist and should be orchestrated with a contractor and engineer.

Photograph No. 6 – Location where angle brace has broken loose from its connection.

Member should be re welded to the post.

IV. Conclusions

After visual evaluation it is our professional opinion that the bleachers are overall in good condition. The bleachers felt very sturdy and solid while walking on the top surface, the walkways had little to no bounce, and the supporting structure appeared to be well constructed. There were very minor issues found that should be repaired and/or corrected but do not pose any immediate issues to their use. Those items are as follows:

• (1) vertical angle needs to be replaced. This angle was located on the east side bleachers (see photograph no 5).

• Some of bracing angles have been bent out of shape, or kinked. These should be replaced with new members.

• Broken welds or similar conditions should be repaired (see photograph no. 6)

• Most of the steel appeared to be experiencing some level of corrosion.

Recommendation is to clean the steel surfaces and repaint the structure.

• Some of the aluminum planks bounce over the supporting members. This is most likely because the hidden fasteners have come loose. A thorough walk-through by maintenance personnel to replace and tighten fasteners at periodic intervals would be beneficial.

HSE reserves the right to alter and/or amend this report and the recommendations and conclusions herein, should more or differing information become available. No analysis or calculation was performed on the bleacher structure. This report is provided for the exclusive use of Marion County Board of County Commissioners and is not intended for use by any third-party entities.

Report Respectfully Submitted, Hobson Structural Engineering, P.A.

Daryl R. Hobson, P.E., S.E.

Florida P.E. No. #84399

SO

U

TH

EA

ST

ER

N L

IV

ES

TO

C

K

PA

VI

LI

O N

SI

TE

P

LA

N

EXHIBIT B SITE PLAN

AutoCAD SHX Text

RAMP

AutoCAD SHX Text

STAIRS

AutoCAD SHX Text

SEATING

AutoCAD SHX Text

HANDRAIL

AutoCAD SHX Text

RAMP

AutoCAD SHX Text

RAMP

AutoCAD SHX Text

EAST GRANDSTANDS

AutoCAD SHX Text

MAIN ARENA

AutoCAD SHX Text

WEST GRANDSTANDS

AutoCAD SHX Text

ENTRANCE

AutoCAD SHX Text Date

AutoCAD SHX Text Sheet Of

AutoCAD SHX Text L-01

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text Revision

AutoCAD SHX Text 09/18/2025

AutoCAD SHX Text

AutoCAD SHX Text Review:

AutoCAD SHX Text Approval:

AutoCAD SHX Text Job #

AutoCAD SHX Text Dwg #

AutoCAD SHX Text

JBA

AutoCAD SHX Text Date

AutoCAD SHX Text Drawn:

AutoCAD SHX Text

SGH

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL GRANDSTAND SEATING

AutoCAD SHX Text N.T.S

AutoCAD SHX Text

MAIN ARENA LAYOUT

AutoCAD SHX Text N.T.S

Project Manager
Site Supervisor
Background and Observations
Intent
Code
General
Structural Repairs
Painting
Handrails
Schedule of Work
Contractor Responsibility
County Responsibility
Field Photographs