7-Project Details and Scope.pdf

PDF 151 KB Posted

Attached to
Lake Mountain School District Design-Build Services: Bus Maintenance & Transportation Facility
Solicitation number
LMSD07102026
Issued by
Utah County, Scipio Town, Utah

About this file

This is a Request for Proposals (RFP) issued by Lake Mountain School District's Department of Purchasing for Design-Build services to construct a new Bus Maintenance & Transportation Facility in Saratoga Springs, Utah. The District seeks qualified Design-Build teams consisting of general contracting firms partnered with licensed architectural and engineering sub-consultants to provide turnkey design, engineering, permitting, procurement, and construction services for an approximately 20,000 square foot facility on existing district-owned property adjacent to Westlake High School. The facility will serve dual purposes: institutional fleet maintenance operations for the district's bus fleet and a Career and Technical Education satellite program for Westlake High School students in automotive and diesel mechanics. The scope includes five heavy-duty maintenance bays, a dedicated fluid service and lubrication bay with in-ground service pit, body work bay, spray finishing booth, bus wash bay, two educational CTE bays, classroom space for 20-24 students, administrative offices, tire storage, bulk fluid and chemical storage, and supporting spaces. The RFP was issued June 22, 2026, with written questions due by July 8, 2026 at 5:00 PM MDT and proposals due July 10, 2026 by 4:00 PM MDT. The evaluation period runs July 13-15, 2026, with potential interviews July 16-17, 2026, and contract award anticipated July 20, 2026. Construction is expected to commence October 15, 2026, with substantial completion targeted for May 2027.

Proposals will be evaluated on a 100-point rubric addressing demonstrated expertise in institutional and industrial facilities (25 points), integrated team dynamics and design-build experience (20 points), schedule efficiency (15 points), references and past performance (10 points), architectural design quality and lifecycle value (10 points), and turnkey cost and value pricing (20 points). Mandatory requirements include a minimum of 10 years of relevant professional experience, current Utah Contractors License, current business license, proof of liability and workers' compensation insurance, and a 5% bid bond as required by Utah Procurement Code for contracts exceeding $50,000. A performance bond equal to 100% of the contract price will be required upon award. Submissions must be made electronically via the Utah Public Procurement Place and include Schedule A (Certification of Proposal Form), Schedule B (Technical Proposal), and Schedule C (Turnkey Cost and Value Pricing). The District reserves the right to reject any or all proposals, waive immaterial irregularities, and award the contract to the responsible proposer offering the best overall value. The contract may be canceled with 30 days' notice due to lack of funding or poor performance, and no funding obligation exists if the project is determined financially infeasible.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSALS (RFP)

PROJECT TITLE: Design-Build Services: Bus Maintenance & Transportation Facility

RFP ISSUANCE DATE: June 22, 2026

SUBMISSION DEADLINE: July 10, 2026, by 4:00 PM MDT

CONDUCTING ENTITY: Alpine School District's Department of Purchasing is the issuing procurement unit, and Lake Mountain School District is the conducting procurement unit for this RFP (referred to as “the District”).

PRIMARY CONTACTS: Julie King, Board President & Matt Isaacson, Board Vice President

EMAIL ADDRESSES: jking@lakemtn.org and misaacson@lakemtn.org

PURPOSE & PROJECT OVERVIEW

Lake Mountain School District is seeking competitive proposals from qualified, licensed Design-Build (DB) Teams—consisting of general contracting firms partnered with licensed Architectural and Engineering sub-consultants—to provide turnkey design, engineering, permitting, procurement, and construction services for a new Bus Maintenance & Transportation Facility.

The approximately 20,000 square foot purpose-built facility will be constructed on existing district-owned property within Utah County Parcel No. 66:290:0008, specifically on the current employee parking lot of the Alpine School District Transportation West facility in Saratoga Springs, Utah. The site is immediately adjacent to Westlake High School; the educational component will function as a dedicated CTE satellite program for Westlake High School students.

The selected DB team will hold single-point responsibility for a fully integrated, code-compliant facility serving both the district’s fleet maintenance operations and a Career and Technical Education (CTE) program in automotive and diesel mechanics. This procurement is conducted pursuant to the Utah Procurement Code and applicable administrative rules governing design-build contracts.

CORE DESIGN-BUILD OBJECTIVES & CONSTRAINTS

The selected Design-Build partner must balance three critical parameters throughout design and execution:

Strict Cost Control & Value Engineering: Project delivery must favor value-engineered, readily available materials and structural simplicity. Cost-effectiveness must be a primary driver in all design and procurement decisions.

High Durability & Low Lifecycle Maintenance: All material and mechanical selections must prioritize long service life, low maintenance burden, and durable wear-layers suited to a high-use institutional and industrial environment. Initial cost savings that create long-term maintenance liabilities are expressly discouraged.

Accelerated Delivery & Day-One Operational Readiness: The facility must be fully operational from the first day of occupancy—no deferred systems, incomplete punch-list items, or phased hand-offs. The DB team must include a credible fast-track strategy via a critical-path schedule which highlights key milestones and timelines demonstrating the ability to deliver completion by May 2027.

DETAILED SCOPE OF SERVICES (TURNKEY DELIVERY)

The selected DB firm is fully responsible for all architectural, engineering, civil, structural, permitting, utility coordination, and construction labor and materials.

Facility Space Program (Approximately 20,000 sq. ft.)

• Institutional Fleet Maintenance Bays (5): Heavy-duty drive-through or pull-in bays with oversized overhead doors, in-ground or surface-mounted bus-capable vehicle lifts, centralized compressed air, industrial floor drainage with interceptors, high-intensity lighting, dedicated heavy-equipment electrical circuits, petroleum-environment fire suppression and ventilation, and minimum 16-foot clear height.

• Fluid Service & Lubrication Bay (1): A dedicated pull-in bay equipped with an in-ground service pit providing below-vehicle access for fluid changes, lubrication, and undercarriage servicing of full-size school buses. The pit must meet all applicable OSHA and IFC requirements for below-grade work environments, including ventilation, lighting, non-slip surfacing, and safe egress. The bay shall include overhead fluid delivery reels or drop lines for bulk oil, coolant, transmission fluid, and grease — plumbed directly back to the bulk fluid and chemical storage room — along with a dedicated floor drain with oil/water separator, and adequate overhead clearance for full-size bus access.

• Body Work Bay (1): A dedicated bay for automotive body repair, including panel work, filling, and surface preparation by professional maintenance staff. Requires high-intensity adjustable lighting suitable for surface inspection, compressed air drops, dust collection provisions, and sufficient clearance to work around a full-size bus or vehicle.

• Spray Finishing Booth (1): A fully enclosed, dedicated spray finishing booth compliant with NFPA 33, IFC Chapter 24, and applicable OSHA standards for spray application of flammable finishes. Requires explosion-proof electrical throughout, a dedicated filtered exhaust and fresh-air supply system, fire-rated enclosure construction, an interlocked ventilation/lighting system, and appropriate fire suppression provisions.

• Bus Wash Bay (1): Drive-through capable, oil/water separator drainage meeting Utah DEQ requirements, hot and cold water supply, commercial wash equipment provisions, and minimum 16-foot clear height.

• Educational CTE Bays — Westlake High School Satellite (2): Bay configuration consistent with institutional bays for industry-standard instruction. Includes bus-capable vehicle lifts, enhanced student safety features (emergency stops, supervision sightlines), flexible demonstration/hands-on layout, and clear physical separation from institutional bays.

• CTE Classroom: Adjacent to educational bays; capacity for 20–24 students; integrated presentation technology; flexible seating and worktables; ADA-compliant throughout.

• Administrative & Office Space: Private offices, open workstations, reception area, and storage for maintenance supervisors and administrative staff.

• Tire Storage Room: Dedicated room with minimum 8-foot exterior delivery door, adequate floor load capacity, and code-required ventilation.

• Bulk Fluid & Chemical Storage Room: Adjacent to tire storage; direct exterior delivery access; compliant with Utah Fire Prevention & Safety Act and IFC/UFC requirements for flammable and combustible liquid storage, including 110% secondary containment, explosion-proof ventilation, minimum 2-hour fire-rated wall separation, and NFPA 704 signage.

• Core Support: Parts storage room with institutional bay access, separate staff and student restrooms, employee break room, custodial storage, mechanical/electrical/data rooms.

Site, Civil & Utility Work The build site is an existing paved parking lot; civil scope is minimal. The DB team shall:

• Conduct geotechnical survey and assess existing utility capacity

• Extend water, sewer, natural gas, and fiber from existing on-site tie-ins to the building footprint

• Coordinate with Rocky Mountain Power for 3-phase commercial service supporting all concurrent equipment loads

• Perform selective pavement demolition within the building footprint; repair and restripe access lanes and bus maneuvering aprons as needed

• Verify existing on-site stormwater channeling and retention system capacity; no new stormwater infrastructure is anticipated

• Construct ADA-compliant pedestrian pathways connecting the facility entrance to the parking lot and Westlake High School campus, with clear separation from bus and vehicle maneuvering areas

• Install high-efficiency LED perimeter lighting compliant with Saratoga Springs code:

maximum 3,000°K color temperature and 1-footcandle boundary spill

Code Compliance & Architectural Standards The facility must meet all Saratoga Springs Institutional Zoning requirements, including:

• Facade: raw unclad metal siding prohibited; 3-to-4-foot masonry wainscot (brick, stone, or split-face CMU) with IMP, stucco, or EIFS above; design contextually compatible with Westlake High School and the existing on-site Transportation Office building

• Mechanical screening: all rooftop units fully screened from ground view via parapets or masonry walls matching the building

• Full ADA compliance across all public-facing and student-occupied spaces

Campus Connectivity & Secure Student Access The DB team must provide a safe, ADA-compliant pedestrian connection between the facility and Westlake High School campus. The specific form—covered breezeway, paved pathway, or equivalent—will be determined in design development. Proposers must include a brief connectivity narrative in their technical proposal. The connection must:

• Be ADA-compliant with appropriate grades, surfacing, and lighting per Saratoga Springs code

• Maintain clear separation from all bus and vehicle maneuvering areas

• Include a designated access-controlled student entry point on the facility side (key-card or equivalent), separate from the staff and fleet entrance

• Coordinate with existing fencing, and site features at Westlake High School

Perimeter Security & Surveillance Infrastructure

As the maintenance building is part of a larger transportation campus, and as that campus is concurrently being expanded to include additional district services/office infrastructure, the perimeter fencing, sidewalks, entrance and access points will need to adjusted and/or expanded to fit the new design of the larger campus design.

• Perimeter Fencing Expansion: Tie directly into the property's existing perimeter barriers and extend heavy-duty commercial-grade fencing along the South East section of the property to fully incorporate and enclose the area that is currently the staff parking lot

• Integrated IP Security & Surveillance Network: Design and deploy a turnkey,

• non-proprietary Power over Ethernet (PoE) IP camera system covering the entire facility.

Exterior cameras must track newly expanded fencing perimeters and building access points with weatherproof, night-vision enclosures. Interior cameras must monitor primary areas as well as student instructional work areas. Integrated security system with larger campus technology terminating at a centralized Network Video Recorder (NVR) housed onsite with a minimum 30-day storage capacity.

• ADA-compliant walkways and access points

CTE Facility & Student Safety Compliance All CTE-designated spaces — including the educational bays and classroom — must be designed in full compliance with applicable Utah State Board of Education (USBE) facility standards, Utah Division of Occupational and Professional Licensing (DOPL) requirements for vocational instruction environments, and all relevant IBC, OSHA, and local code provisions governing student-occupied instructional spaces. This includes appropriate egress, ventilation, emergency shutoffs, sight-line requirements for instructor supervision, and hazardous material handling provisions specific to automotive and diesel mechanics instruction.

FFE

Furniture, fixtures, equipment (FFE), vehicle lifts, tools, diagnostic systems, and all other specialized operational or instructional equipment are expressly excluded from this RFP and will be procured separately by the District. The DB team is responsible for ensuring that all spaces are built to accommodate and support the intended equipment — including adequate structural provisions, utility rough-ins, and clearances — but shall not include the cost of any equipment, furnishings, or instructional technology in their submission.

SCHEDULE OF EVENTS

Event Date

RFP Issuance Date June 22, 2026

Deadline for Written Questions & Clarifications July 8, 2026, by 5:00 PM MDT

Proposal Submission Deadline July 10, 2026, by 4:00 PM MDT

Proposal Evaluations July 13-15, 2026

Interviews with Shortlisted DB Teams July 16-17, 2026 (if needed)

Contract Award July 20, 2026

Final Stamped Architectural & MEP Plans Due October 18, 2026

Target Project Substantial Completion May 2027

PROPOSAL SUBMISSION REQUIREMENTS

Mandatory Minimums The following mandatory minimums must be addressed in the technical response:

• Vendor must be able to meet the full Scope of Work

• Vendor must have a minimum of 10 years of relevant professional experience

• Vendor must submit Schedules A, B, and C

• Vendor must upload a current business license and valid State of Utah Contractors

License

• Vendor must upload proof of required liability and workers’ compensation insurance coverage

• Vendor must upload a bid bond; per Utah Procurement Code 63G-6a-1102, bids exceeding $50,000 require a 5% bid bond A performance bond will be required from the successful vendor in the amount of 100% of the contract price. (63G- 6a-1103).

Late submissions are automatically rejected. Submittals should be concise and address specific RFP items. The District reserves the right to reject any or all proposals, waive immaterial irregularities, and award a contract to the responsible proposer whose proposal provides the best overall value to the District, as determined under the evaluation criteria stated in this RFP.

Submit electronically via the Utah Public Procurement Place (UPPP). Submissions must contain:

• Schedule “A” – Certification of Proposal Form (completed and signed)

• Schedule “B” – Technical Proposal

• Schedule “C” – Turnkey Cost & Value Pricing (submitted as a separate attachment)

SCHEDULE “A” — CERTIFICATION OF PROPOSAL FORM

The District’s Certification of Proposal form completed and signed.

SCHEDULE “B” — TECHNICAL PROPOSAL

• Demonstrated Expertise in Institutional & Industrial Facilities (25 pts):

Team profiles and resumes for Lead Architect, Principal MEP Engineer, and Site Superintendent. Narrative on managing specialized loads (bay ventilation, compressed air, floor drainage, CTE equipment) while maximizing lifecycle efficiency and controlling structural costs.

• Integrated Team Dynamics & DB Experience (20 pts): Track record of single-point responsibility design-build delivery on time and within budget; experience with clear-span steel, institutional envelopes, and integrated utility systems.

• Efficiency of Proposed Schedule (15 pts): Feasibility and path logic from contract award through concurrent civil and steel procurement to May 2027 completion.

• References & Past Performance (10 pts): Punch-list management and change-order record; minimum three (3) institutional or commercial facilities of 15,000+

sq. ft. completed within the past ten (10) years with unified DB delivery.

• Architectural Design Quality & Lifecycle Value (10 pts): Demonstrated ability to deliver contextually compatible design meeting Saratoga Springs Chapter 19.16 standards, with materials, massing, and aesthetic cohesive with the adjacent Westlake High School campus and Transportation Office building. Proposals must simultaneously articulate specific strategies for long-term durability, energy efficiency, and reduced operational maintenance burden.

• Turnkey Cost & Value Pricing (20 pts): The financial competitiveness, clarity, and value-engineering logic of the comprehensive Design-Build fee structure. (Submit the completed cost sheet Schedule “C” as a separate attachment from all other required RFP submission documents).

AWARD AND CONTRACT

The District reserves the right to reject any or all proposals, waive immaterial irregularities, and award a contract to the responsible proposer whose proposal provides the best overall value to the District, as determined under the evaluation criteria stated in this RFP. The contract may be canceled upon 30 days’ notice due to lack of funding or poor performance. If funding is determined to be unavailable or not financially feasible, the District has no obligation to award or execute a contract.

Evaluation Criteria

Proposals will be reviewed by an internal evaluation selection committee and graded on a 100-point rubric. The District may appoint an evaluation committee pursuant to Utah Procurement Code. The committee may conduct discussions, interviews, clarifications, and best and final offer (BAFO) negotiations if determined to be in the best interest of the District.

Any protest relating to this procurement shall be submitted in writing to the District within the timeframes established under applicable provisions of the Utah Procurement Code. The filing of a protest shall not automatically stay the procurement unless required by law or determined by the District to be in its best interests.