7-LMSD BMF PDB RFP-2.pdf
PDF 722 KB Posted
- Attached to
- Lake Mountain School District Design-Build Services: Bus Maintenance & Transportation Facility
- Solicitation number
- LMSD12102026CS
- Issued by
- Utah County, Utah
About this file
This Request for Proposals is issued by Lake Mountain School District for progressive design-build services to design and construct a Bus Maintenance & Transportation Facility of approximately 21,600 gross square feet in Saratoga Springs, Utah on Utah County Parcel No. 66:290:0008. The project scope includes a complete building shell, full fit-out of District operational spaces including five fleet maintenance bays, one fluid service pit bay, one body work bay, one spray finishing booth, one bus wash bay, administrative offices, parts and tire storage, bulk fluid storage, staff facilities, and mechanical/electrical/data rooms, with schematic design for future Career and Technical Education (CTE) educational bays and classroom to be constructed in a later phase. A mandatory pre-submittal meeting and site walk is scheduled for Tuesday, November 24, 2026, at 10:00 AM MST at the Transportation Office on the Transportation West campus. Proposals are due Thursday, December 10, 2026, at 2:00 PM MST through the Utah Public Procurement Place (U3P). The procurement is a single-stage, value-based selection process with optional interviews. Construction is anticipated to commence in late May 2027 with substantial completion targeted for December 17, 2027, and no later than February 17, 2028, representing a 6- to 9-month construction schedule. Contract award is anticipated December 18, 2026, following a 7-day protest period.
The District has not published a construction budget; the construction price will be established through a Guaranteed Maximum Price (GMP) developed during the Design Phase based on competitively bid subcontracts. Design Phase fees are proposed as not-to-exceed amounts, with the Design Phase fee, construction general conditions, and design-build fee percentage scored separately. Proposers must submit a 5% bid bond with fee proposals. The evaluation criteria include key personnel (25 points), similar project experience (20 points), Design Phase approach and cost control (20 points), fees (15 points), schedule and fast delivery (10 points), past performance (5 points), and risk and campus operations planning (5 points), with optional interviews adding up to 20 additional points for a maximum total of 120 points. The project is funded within the District's approved budget and is subject to Utah Division of Facilities Construction and Management (DFCM) oversight under Utah Code Title 63A, Chapter 5b, Part 12. Design professionals must comply with DFCM maximum allowable fee requirements. The District has reserved the right to cancel the solicitation, reject any or all proposals, or waive immaterial irregularities, and protests must follow Utah Code Title 63G, Chapter 6a, Part 16 procedures with strict filing deadlines.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 1
LAKE MOUNTAIN SCHOOL DISTRICT
Request for Proposals – Re-Issue
Progressive Design-Build Services
Bus Maintenance & Transportation Facility
Transportation West Campus – Utah County Parcel No. 66:290:0008
Saratoga Springs, Utah
Issued Wednesday, November 18, 2026 Mandatory pre-submittal meeting
Tuesday, November 24, 2026, 10:00 AM MST
Proposals due Thursday, December 10, 2026, 2:00 PM MST Submit through Utah Public Procurement Place (U3P) Solicitation No. LMSD12102026CS
Issued by: Lake Mountain School District
Procurement Officer: Clint Sanderson | csanderson@lakemtn.org | (801) 836-5631 |
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 2
Table of Contents
1. Notice to Design-Build Teams
2. Re-Issue Summary
3. Procurement Schedule
4. Project Description
5. Related Procurement: Support Services Building
6. Project Priorities and Identified Risks
7. Scope of Services
7.1 Contract Phase 1: Design Phase
7.2 GMP and Off-Ramp
7.3 Contract Phase 2: Construction Phase
7.4 Approvals and Oversight
7.5 Construction Phasing and Campus Operations
8. Facility Space Program
9. Site and Utility Work
10. Saratoga Springs Code Compliance
11. Perimeter Security, Surveillance, and Alarm Systems
12. Exclusions
13. Solicitation Documents
14. Procurement Process
14.1 Mandatory Pre-Submittal Meeting and Site Walk
14.2 Questions and Addenda
14.3 Proposal Deadline and Submission
14.4 Business Confidential Information
14.5 Evaluation Committee and Conduct
14.6 Discussions and Best and Final Offers
14.7 Subcontractor Procurement
14.8 District Reservation of Rights
15. Proposal Requirements
16. Evaluation and Scoring
16.1 Ratings
16.2 Fee Scoring
16.3 Evaluator Scoresheet (Written)
16.4 Interviews (Optional)
16.5 Recommendation
17. Award, Agreement, and Pricing
18. Protests Appendix A – Schedule A: Certification of Proposal
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 3
1. Notice to Design-Build Teams Lake Mountain School District (the "District") is seeking a progressive design-build team (the "DB Team") to design and build a new Bus Maintenance & Transportation Facility of about 21,600 gross square feet in Saratoga Springs, Utah.
The selected team works with the District under one agreement in two contract phases:
• Design Phase. The design and cost are developed together, ending in a Guaranteed Maximum Price
("GMP").
• Construction Phase. Construction under that GMP.
Selection is a single-stage, value-based process. Each team submits one proposal covering its qualifications, Design Phase approach, and fees. Interviews are optional.
Item Detail
Project Progressive Design-Build Services: Bus Maintenance & Transportation Facility (Re-Issue)
Solicitation No. LMSD12102026CS Issued Wednesday, November 18, 2026 Mandatory pre-submittal meeting and site walk
Tuesday, November 24, 2026, 10:00 AM MST, Transportation Office, Transportation West campus
Proposals due Thursday, December 10, 2026, 2:00 PM MST Construction price Set by the GMP at the end of the Design Phase. No budget figure is published.
Site Utah County Parcel No. 66:290:0008, Transportation West campus, Saratoga
Springs, UT Construction oversight Utah Division of Facilities Construction and Management (DFCM), under Utah
Code Title 63A, Chapter 5b, Part 12, Public School Construction Oversight Procurement authority Utah Procurement Code, Utah Code Title 63G, Chapter 6a, including Part 7
(Request for Proposals) and Part 16 (Protests), and the procurement rules that apply to the District, including Utah Administrative Code Title R33 to the extent the District has adopted it
Issuing and contracting entity. Lake Mountain School District issues this solicitation, conducts the procurement, and holds the resulting contract.
Single point of contact. All communication goes in writing, through U3P, to the Procurement Officer:
• Clint Sanderson, Procurement Officer, Lake Mountain School District, csanderson@lakemtn.org, (801) 836-5631
District project leads, listed for the record only (proposers must not contact them): Julie King, Board President; Matt Isaacson, Board Vice President.
Contact about this solicitation with any board member, employee, evaluator, or DFCM staff member, from issuance through award, may result in disqualification.
Submission. All submittals are uploaded through the Utah Public Procurement Place (U3P). Late submittals are not accepted.
2. Re-Issue Summary This solicitation replaces the RFP issued June 22, 2026. The District withdrew that RFP before award because of funding timing.
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 4
This re-issue also changes the delivery method to progressive design-build. That lets the District and the selected team finish defining the building together after award, with cost visible at each step.
Firms that responded in July 2026 must submit again. Prior submittals will not be considered.
Topic June 2026 RFP This RFP
Delivery method Lump-sum design-build Progressive design-build: a Design Phase ending in a GMP, then a Construction Phase, with an off-ramp after design
Scope Full build-out, including CTE bays and classroom
Complete shell and all District operational spaces. CTE areas are built as shell for a future phase funded by CTE grants.
Parking Not addressed No parking in this scope, including accessible stalls.
Parking is provided by the Support Services Building project.
Zoning Institutional zoning referenced Site is in the City's Public School Bus Lot (PSBL) zone; no rezone needed
Approvals Not described DFCM plan review and oversight. City site plan and architectural review run concurrently, starting in the Design Phase.
Adjacent project Not referenced Support Services Building referenced only for matching technical standards and construction coordination
City design standards Summarized Specific Saratoga Springs Title 19 requirements listed, with the thresholds that affect cost
Space program Room list only Planning-level areas, with layout and program-fit studies in the Design Phase
Selection One stage, 18-day response One stage, 23-day response; optional interviews with published questions and a scoresheet
Pricing Lump sum by phase, no budget disclosed
No budget figure published. Design Phase fee, fee percentage, and general conditions proposed up front.
GMP at the end of the Design Phase.
Completion May 2027 6–9 month construction; substantial completion targeted December 17, 2027
3. Procurement Schedule All times are Mountain Time. The District may change these dates by addendum.
Event Date and time Location
RFP issued, with interview questions and reference documents
Wed., Nov. 18, 2026 U3P
Mandatory pre-submittal meeting and site walk (prime contractor and prime architect must attend)
Tue., Nov. 24, 2026, 10:00
AM
Transportation Office, Transportation West campus
Questions due Tue., Dec. 1, 2026, 5:00 PM U3P Final addendum Fri., Dec. 4, 2026, 5:00 PM U3P Proposals, fee proposal, and bid bond due Thu., Dec. 10, 2026, 2:00 PM U3P Notice whether interviews will be held By Mon., Dec. 14, 2026, 12:00 PM
U3P and email
Interviews, if held (dates reserved) Wed.–Thu., Dec. 16–17, District office; location
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 5
Event Date and time Location
2026 given in the notice Notice of intent to award Fri., Dec. 18, 2026 U3P Protest period ends (7 days; the Dec. 25 holiday moves the last day)
Mon., Dec. 28, 2026 —
Contract execution Tue., Dec. 29, 2026 — Design Phase kickoff Mon., Jan. 4, 2027 —
Project milestones (targets).
Milestone Target
Program validation and layout selected Fri., Jan. 29, 2027 Schematic Design; City site plan filed Fri., Feb. 26, 2027 Design Development; early work packages approved Fri., Apr. 2, 2027 90% CDs and GMP proposal Fri., Apr. 30, 2027 Issued-for-construction documents, GMP amendment, DFCM approval, Construction Phase Notice to Proceed
Fri., May 14, 2027
Construction start (early work packages may start sooner) Mon., May 17, 2027 Building dried in September 2027 Substantial completion (District target) Fri., Dec. 17, 2027 Substantial completion (latest acceptable; 9 months) Thu., Feb. 17, 2028 Final completion 30 days after substantial completion
Teams propose their own construction duration within 6 to 9 months. Shorter credible durations score higher.
4. Project Description The facility (the "BMF") is a single-story, purpose-built bus maintenance building of about 21,600 GSF. It sits on the existing paved staff parking lot of the Transportation West campus, right next to Westlake High School. It serves the District's fleet maintenance operations now and will later house a Career and Technical Education (CTE) automotive and diesel program for Westlake students.
This project. The DB Team designs the entire building and site, then builds:
• the complete building shell, including the future CTE areas: foundations, slab, structure, roof, envelope, overhead doors, and exterior finishes that meet City standards;
• full fit-out of all District operational spaces (see Facility Space Program);
• building-wide fire protection, fire alarm, and base utility service sized for the full building at CTE build-out;
• site, utility, fencing, security, and telecommunications work for the building and its immediate apron;
and
• rough-ins, stub-outs, and capped connections, so the future CTE phase can proceed without demolishing this project's work.
Future CTE phase (not in this contract). The CTE bays, CTE classroom, student restrooms, student entry, and pedestrian connection to Westlake High School are designed to schematic level now, so the City site plan and
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 6 building systems account for them. They are not built. The District will procure that phase separately when CTE grant funds are available. The Design Phase includes a non-binding estimate for it.
Occupancy. CTE areas are turned over as unoccupied, conditioned-to-code shell space, secured from District operational areas. The DB Team confirms with DFCM the occupancy classification and life-safety provisions that allow the operational spaces to be occupied while the CTE shell is unfinished.
CTE design criteria. The CTE spaces are finished later, but this project's design, shell, and rough-ins must already meet:
• Utah State Board of Education (USBE) facility standards for CTE automotive and diesel instruction; and
• the safety, building, and accessibility codes for student-occupied instructional space.
That includes:
• occupancy separation and egress from fleet areas under the International Building Code;
• ADA accessibility throughout student areas and along the route to Westlake High School;
• vehicle exhaust and ventilation, emergency power shutoffs, eyewash and emergency shower locations, and instructor sightlines; and
• hazardous-material handling.
The future phase must be able to meet these requirements without structural or envelope changes.
Why progressive design-build. The District has a clear program but not a locked design. Progressive design-build lets the District select a team on qualifications and fees. The District and that team then settle the bay layout, storage sizes, and program fit together, tracking cost at each step, before committing to a construction price.
Design objectives (in priority order):
1. Cost control: structural simplicity, readily available materials, and a footprint and elevation lengths sized to avoid unnecessary City articulation triggers.
2. Durability and low lifecycle maintenance: initial savings that create maintenance liabilities are discouraged.
3. Day-one readiness: all operational spaces fully working at substantial completion, with no deferred systems.
5. Related Procurement: Support Services Building The Support Services Building ("SSB") is a separate District project on the same campus. Construction starts in November 2026. Its purpose is different, so this RFP refers to it only for:
• the technical standards the BMF must match; and
• construction coordination.
Reference documents posted with this RFP include the SSB exterior elevations and materials, security, site electrical and fiber, and site and civil sheets covering the BMF area.
Item SSB standard BMF application
Exterior palette Split-face CMU (Sunroc "Java" and "Cinnamon"), honed CMU ("Cream"), Kingspan insulated metal panel ("Regal Blue" and "Slate Blue"), medium bronze coping
Same products and colors, but fewer of them (see Saratoga Springs Code Compliance)
Fence and gates Precast concrete fence, ornamental pedestrian gates, heavy-duty double-leaf vehicle gates
Same on public-facing runs. The District may approve a lower-cost product on the southeast run.
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 7
Item SSB standard BMF application
Video surveillance Axis Communications IP cameras; District-furnished network video recorder (NVR) and video management software
Axis cameras on the same NVR and software
Access control District platform used at the SSB Same head-end and credential format, listed in the reference documents
Exterior lighting control
Campus astronomical timeclock (Lutron Vive) BMF exterior lighting tied to the same timeclock
Fire alarm and intrusion
SSB has its own systems BMF ties to the existing Transportation Office systems, not the SSB
Construction coordination. The BMF team works only within its limit of work and a staging area the District assigns apart from the SSB's. The limit of work is the building footprint plus 10 feet, aprons, utility and conduit trenches, and the fence line shown on the campus exhibit posted with this RFP.
While both projects are active, the BMF team:
• shares its schedule monthly;
• attends a joint coordination meeting every two weeks;
• gives 72 hours' notice before utility shutdowns, lane closures, or crane picks; and
• keeps bus routes open at all times.
Staff and accessible parking are built by the SSB project before the BMF team mobilizes.
6. Project Priorities and Identified Risks Cost control is the first priority, followed by schedule. The District has not commissioned a separate programming study. Progressive design-build lets the District and the selected team resolve open program questions in the Design Phase, with cost visible at each step, rather than having proposers price them as contingency.
Risk What the District knows What proposers should address
Concurrent construction on the same campus
SSB is under construction from November
Staging, access, and delivery coordination
Active bus operations Buses operate from the campus year-round, including summer
Site logistics that keep bus entry and exit routes and fire access open at all times
Subsurface conditions under existing pavement
Existing paved lot; no BMF-specific geotechnical data yet
Geotechnical scope and how unknowns are carried into the GMP
Below-grade pit and in-ground lift provisions
Groundwater depth unknown Waterproofing, dewatering, and pit design assumptions
Utility and telecom capacity Existing on-site tie-ins; 3-phase service not yet confirmed; the Transportation Office main network room (MDF) is on the west side of that building
Early Rocky Mountain Power application;
conduit route from the MDF
Program fit and the 20,000 sf threshold
The District's preferred program is about
21,600 GSF
Layout and cost options in the Design Phase
City review timing Site is zoned PSBL; site plan not yet filed Concurrent submittal strategy that absorbs City comments without delay
Long-lead items Steel, overhead doors, switchgear, rooftop units
Early work packages during the Design Phase
Future CTE compatibility CTE program will be finished later Rough-ins and shell decisions that avoid
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 8
Risk What the District knows What proposers should address rework Funding This project is funded within the approved budget; the CTE phase depends on grants
Scope that stands alone if the CTE phase is delayed
7. Scope of Services The DB Team holds single-point responsibility, under one agreement in two contract phases, for:
• design, approvals, construction, commissioning, and closeout of this project; and
• schematic design of the future CTE phase.
7.1 Contract Phase 1: Design Phase
The Design Phase is paid as a not-to-exceed fee. The DB Team:
• validates the program with the District and delivers a layout and program-fit study first;
• develops the design through schematic design (SD), design development (DD), and construction documents (CDs), with an open-book cost model updated at each milestone;
• leads design meetings, estimating, scheduling, constructability reviews, and lifecycle-cost value engineering;
• prepares City and DFCM submittals and the non-binding CTE phase estimate;
• competitively bids subcontracts under the Utah Procurement Code, with the District observing;
• proposes early work packages (foundations, steel, long-lead items) for District approval by amendment;
and
• submits a GMP proposal at about 90% CDs.
Design Phase milestone Deliverable District/DFCM review
Program validation and layout study
Two or three layouts with area, cost, and code comparison; the District selects one
5 business days
Schematic Design Plans, elevations, system narratives, SD cost model; City site plan filed
10 business days
Design Development Coordinated drawings, outline specifications, DD cost model, early work packages
10 business days
90% CDs and GMP proposal Stamped-ready documents; GMP built from bid subcontracts, fee, general conditions, and contingency
10 business days
Issued for Construction Final stamped documents with DFCM and City comments addressed
7.2 GMP and Off-Ramp
• If the District accepts the GMP, it signs a GMP amendment and issues the Construction Phase Notice to
Proceed.
• If the GMP is not acceptable to the District after good-faith negotiation, the District may end the agreement after the Design Phase. It then pays the earned Design Phase fee and uses the design documents to complete the project another way.
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 9
7.3 Contract Phase 2: Construction Phase
Construction is under the GMP, and savings are returned to the District. The Construction Phase also includes:
• commissioning of HVAC, exhaust, compressed air, fluid distribution, fire protection, fire alarm and intrusion integration, and controls;
• staff training;
• as-builts (PDF and CAD/Revit), O&M manuals, and warranties; and
• a closed punch list.
The District will not accept substantial completion while operational systems are incomplete.
7.4 Approvals and Oversight
DFCM oversight. DFCM provides plan review and construction oversight. The DB Team:
• submits documents at the milestones DFCM requires;
• responds to DFCM comments;
• coordinates inspections; and
• obtains the certificate of occupancy as DFCM directs.
Concurrent City approvals. Starting at SD, the DB Team prepares and submits, on the District's behalf, the City site plan application (Chapter 19.14) and architectural review materials (Section 19.16.02). It attends City meetings and incorporates conditions of approval. City approvals run in parallel with DFCM review. Only a written District Notice to Proceed releases design phases, early work packages, or construction.
Other approvals. The DB Team obtains:
• the UDAQ fugitive dust plan;
• Utah DEQ stormwater coverage, if the disturbance requires it;
• utility applications (Rocky Mountain Power, Enbridge Gas Utah, City water and sewer);
• fire code official review; and
• oil/water separator discharge approval.
The District pays City impact and connection fees. The DB Team applies for them.
7.5 Construction Phasing and Campus Operations
Construction runs from late spring through fall 2027, and buses operate from this campus year-round, including summer. The DB Team:
• keeps at least one bus entry route and one bus exit route open at all times, with full-size bus turning paths, unless the District approves a temporary alternative in writing;
• maintains fire apparatus access roads, hydrant and fire department connection access, and emergency egress from all occupied campus buildings, as the International Fire Code and the fire code official require, including during trenching and paving;
• keeps accessible pedestrian routes open and separated from buses and construction traffic;
• submits a site logistics and traffic control plan at DD for District and fire code official approval, and updates it before each phase change;
• schedules deliveries, crane picks, and lane closures outside bus departure and return windows (the
District provides these at the pre-construction meeting), with 72 hours' notice and an approved detour for any route closure; and
• keeps the campus perimeter secure while fences and gates are relocated.
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 10
8. Facility Space Program Areas are planning targets that the Design Phase will confirm.
• "Full" means complete in this project.
• "Shell" means enclosed, sprinklered, and heated to code minimum, with rough-ins and capped stubs for the future CTE phase.
Space Qty Target sf Build Key requirements
Fleet maintenance bays 5 6,000 Full Full-size bus capable; 18 ft minimum clear height; overhead doors at least 14 ft wide by 16 ft high; drains to oil/water separator; compressed air; 480V/3-phase circuits; vehicle exhaust and ventilation; high-output LED lighting
Fluid service and lubrication pit bay
1 1,200 Full Bus-length pit meeting OSHA and IFC below-grade requirements;
overhead reels for oil, coolant, ATF, grease, and used-oil return, piped to the bulk fluid room; dedicated drain and separator
Body work bay 1 1,200 Full Adjustable inspection lighting; compressed air; dust collection provisions
Spray finishing booth 1 1,200 Full NFPA 33 and IFC Chapter 24; explosion-proof electrical; filtered exhaust and makeup air; fire-rated enclosure; interlocked ventilation and lighting; suppression. Booth unit is District-furnished.
Bus wash bay 1 1,400 Full Direct exterior exit; 18 ft minimum clear height; hot and cold water; separator drainage meeting Utah DEQ requirements;
corrosion-resistant finishes
CTE educational bays 2 2,400 Shell Own exterior vehicle entrance and overhead door(s), at least 12 ft wide by 14 ft high, on an approach separate from fleet bus entrances and drive aisles; demising separation from fleet bays;
capped utilities
CTE classroom 1 900 Shell 20–24 students; adjacent to CTE bays Student restrooms — 250 Shell Plumbing rough-in Administration and offices — 1,200 Full Supervisor offices, open workstations, reception, files; counts set in the Design Phase Parts storage 1 1,600 Full Direct access from fleet bays; up to half may be on a mezzanine Tire storage 1 800 Full Exterior delivery door at least 8 ft; floor load for stacked tires;
code ventilation Bulk fluid and chemical storage
1 400 Full Adjacent to tire storage; exterior delivery door; 110% secondary containment; explosion-proof ventilation; 2-hour separation;
NFPA 704 signage
Staff restrooms, lockers, showers
— 400 Full Separate from student restrooms
Break room 1 400 Full Kitchenette Custodial 1 80 Full Mop sink Mechanical, electrical, data — 600 Full Sized for CTE build-out loads; interior rooms (City 19.16.07.6) Walls, structure, circulation — 1,600 — About 8% of gross area Total 21,630
Program fit. With the District's preferred storage sizes and realistic walls and circulation, the program totals about 21,600 GSF. That is above the 20,000 sf footprint at which City Chapter 19.16 requires heavier articulation (see Saratoga Springs Code Compliance). During design, the DB Team will work to keep the building under 20,000 sf where possible, for example with a parts mezzanine or tighter planning. If the full program cannot fit, it will price the added articulation.
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 11
Bay layout. The DB Team proposes the bay layout and vehicle circulation. The layout study compares options for footprint, door count, cost, heating loss, bus turning paths, and pedestrian safety. In every option:
• the wash bay exits directly outdoors;
• the spray booth meets NFPA 33 separation and has its own exterior access; and
• the CTE bays keep their separate vehicle entrance.
Owner-furnished items. The District furnishes the vehicle lifts, tools, diagnostic systems, spray booth unit, wash equipment, shelving, and furniture. The DB Team provides the structure, embeds, pits, casings, utility connections, and clearances for them, and installs in-ground lift casings in the slab pour. The District owns three in-ground lifts purchased for the West transportation building; the Design Phase confirms whether they are installed here.
9. Site and Utility Work There is no grading or stormwater redesign. Civil work, under stamped civil documents, is limited to:
• geotechnical investigation of the footprint and pit locations;
• water, fire line, sewer, and natural gas extensions from existing points of connection;
• Rocky Mountain Power 3-phase service sized for CTE build-out loads, with the load letter submitted within 30 days of the Design Phase Notice to Proceed;
• a telecommunications and alarm pathway: underground conduit (at least two 4-inch conduits plus one spare, with pull boxes) from the Transportation Office MDF, on the west side of that building, to the BMF telecom room, carrying single-mode fiber and copper;
• interior roof drains piped to the existing campus storm system, or to landscaped areas where City standards allow;
• pavement removal within the footprint. Existing asphalt stays where it works for bus entry and exit.
Where it is disturbed, or needed to complete bus circulation, it is replaced with heavy-duty asphalt and restriped;
• concrete aprons at overhead doors and the wash bay, designed for bus axle loads;
• oil/water separators for bay, pit, and wash drainage, discharging to sanitary sewer;
• an accessible route from existing accessible parking to the staff entrance. No parking of any kind, including accessible stalls, is in scope; the Design Phase confirms that existing accessible stalls serve this building under code;
• building-mounted LED lighting meeting City Chapter 19.11, tied to the campus timeclock;
• landscaping where buses don't drive, matching the design and style of existing campus landscaping, with drip irrigation tied to the campus system, plus restoration of disturbed landscaping around the Transportation Office;
• relocation or replacement of fences and gates between the Transportation Office and the new building, and replanting that area to match the campus; and
• a trash enclosure meeting City 19.16.03.5, if the Design Phase confirms one is needed.
Westlake connection (future CTE phase; design only). Show on the City site plan an accessible pedestrian route from the future student entry to Westlake High School, separated from bus areas and lit to City standards. Install conduit for future access control and lighting along the route where nearby trenching makes it practical.
10. Saratoga Springs Code Compliance The District intends the building to:
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 12
• meet Saratoga Springs Title 19, Chapter 19.16 (Site and Architectural Design Standards); and
• be compatible with Westlake High School and the existing Transportation Office building.
The site is in the Public School Bus Lot (PSBL) land use zone (Chapter 19.04), which provides for a bus lot, administrative office space, and maintenance facilities.
The District reserves its rights under Utah Code 10-20-304, which addresses municipal land use requirements for school district property. Any decision to rely on that section is the District's, not the DB Team's.
Cost-driving thresholds. Two thresholds in Chapter 19.16 drive cost. The District expects designs that stay under them unless a team shows the trade-off is worth it.
Trigger Below threshold At or above threshold District direction Building footprint of 20,000 sf (19.16.05)
Elevations over 40 ft need a combined 5 ft of elevation shifts plus two treatments at 20 ft intervals; projections 36 in.;
roofline steps 12 in.
Elevations over 60 ft need a combined 20 ft of elevation shifts plus two treatments at 50 ft intervals; projections 5 ft; roofline steps 36 in.
Stay under 20,000 sf where possible (see Program fit)
Over 15,000 sf with a front elevation wider than 200 ft (19.16.08)
Section 19.16.08 does not apply Additional articulation every 50/75/200 ft, articulated corners, a 15 ft entry amenity zone, 25% street-level glazing, 5% glazing on all facades, 20% premium materials on the primary facade
Keep the front elevation under 200 ft
Standards that apply regardless (non-residential, 19.16.05 and 19.16.07):
• Four-sided architecture: every elevation visible to the public gets the same design attention as the front.
• Materials and colors: two to four exterior materials and two to four major colors. No single material or color may exceed 75% of any elevation (windows, doors, and accents excluded).
• CMU: no more than 50% of any elevation. Plain grey unfinished CMU only as an accent.
• Metal: architectural metal panel permitted; corrugated metal limited to 25% of each elevation. Stock
"off-the-shelf" metal buildings are prohibited, as are buildings over 75% metal. A pre-engineered steel frame is acceptable with a compliant envelope.
• Prohibited finishes: veneer tile, stucco stone or brick patterns, wood as a primary finish, untreated aluminum or metal window frames.
• Roofs and rooftop equipment: flat roofs screened by parapets on all sides. Rooftop equipment is fully screened from all horizontal views, with screens using two of three building finishes; or equipment is placed on grade and screened.
• Building services: roof drains, conduit, piping, and roof ladders inside the building; electrical panels and communications equipment in interior rooms where possible.
• Canopies over pedestrian areas: project at least 5 ft with 8 ft clearance; posts at least 6 in.; no backlighting.
• Setback: building at least 5 ft from drives and parking, except at overhead doors and at corners protected by bollards.
• Screening: service and storage areas screened with solid masonry or architectural precast walls and opaque metal gates. Chain-link screening is not accepted.
• Pedestrian connections: from the building to adjacent sidewalks and to the Westlake campus, shown on the site plan (19.16.03.1).
Design direction: a scaled-back SSB palette. The BMF is a maintenance building. It should look like a simpler member of the same campus, not a second SSB.
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 13
• Two materials: split-face CMU ("Java") and Kingspan insulated metal panel ("Slate Blue"), with "Regal Blue" panel as the single accent at the entry and one corner, and medium bronze coping.
• CMU base: because no material may exceed 75% of an elevation (doors and windows excluded), expect a CMU base of roughly 6 to 8 feet, or full-height CMU at corners and the entry, rather than a 3 to 4 foot wainscot. Teams confirm this by elevation in their compliance matrix.
• Roof: one flat roof behind a parapet tall enough to hide rooftop units, with the parapet stepped at the entry and corner to meet articulation rules; or ground-mounted equipment, screened.
• Glazing: only where the program uses it (offices, break room, entry), plus overhead door vision panels.
• Not wanted: honed CMU, storefront walls, or decorative canopies beyond the code-required entry element.
Teams may propose alternatives that meet the standards above at lower first or lifecycle cost.
Submittal requirement. The SD submittal includes:
• a Chapter 19.16 compliance matrix (section, requirement, how the design complies); and
• the City-required renderings and material boards.
Source: Saratoga Springs Chapter 19.16, current text including Ord. 26-16 and 26-25. Proposers must verify against the code in effect at the time of application.
11. Perimeter Security, Surveillance, and Alarm Systems The DB Team extends the campus perimeter around the former staff lot, secures the BMF, and ties the BMF fire alarm and intrusion systems to the existing Transportation Office. The SSB stays on its own systems.
• Perimeter fence: extend fencing along the southeast portion of the property to enclose the former staff lot, tied into existing barriers. Fence and gates match the SSB precast concrete fence and gate details.
The District may approve a lower-cost product on the non-street-facing southeast run. Gate quantities are set in the Design Phase.
• Access control: card readers at the staff entrance, delivery door, and vehicle gates, on the District platform used at the SSB. Conduit and door hardware prepared for the future CTE student entry.
• Video surveillance: Axis Communications IP cameras (the District standard) at the fence line, gates, entries, overhead doors, apron, bays, parts room, and bulk fluid room; night-capable exterior housings;
recording to the District-furnished NVR with at least 30 days of retention; camera locations and conduit for future CTE areas.
• Fire alarm: a new addressable fire alarm control panel (FACP), networked over the fiber pathway to the existing Transportation Office FACP, so the campus keeps one phone line and one monitoring account.
The Design Phase confirms the existing panel's make and network capability and specifies a compatible panel.
• Intrusion: new zones and keypads on the existing Transportation Office intrusion system, over the same pathway, with door contacts on exterior doors and alarm points in the bulk fluid room.
• Separation from the SSB: no fire alarm, intrusion, or network connection to the SSB.
The District approves final device locations at DD.
12. Exclusions The DB Team designs for these items but does not include them in its fees or the GMP:
• future CTE phase construction: CTE bay, classroom, and student restroom fit-out; student entry hardware; Westlake pedestrian connection;
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 14
• furniture, fixtures, and equipment, including vehicle lifts, spray booth unit, wash equipment, tools, diagnostic systems, shelving, instructional technology, and network electronics;
• parking of any kind, including accessible stalls, and any campus work under the SSB contract;
• City impact and utility connection fees (paid by the District; applied for by the DB Team); and
• third-party special inspections and materials testing (contracted by the District, consistent with DFCM practice).
13. Solicitation Documents The solicitation documents are this RFP, all addenda, and the reference documents posted with this RFP on U3P:
• Schedule A, Certification of Proposal (Appendix A);
• Schedule C, Fee Proposal Form, issued as a separate document and uploaded separately as the sealed fee submission;
• DFCM Performance References Form;
• Claim of Business Confidentiality form;
• the draft progressive design-build agreement, based on DFCM's progressive design-build agreement form;
• the campus exhibit (limit of work, staging area, and fence and landscape extents); and
• SSB sheets: exterior elevations and materials, security, site electrical and fiber, and site and civil sheets covering the BMF area. The access control maker and credential format are listed in the reference documents.
14. Procurement Process
14.1 Mandatory Pre-Submittal Meeting and Site Walk
A mandatory pre-submittal meeting and site walk will be held on the date, at the time, and at the location in the Procurement Schedule. The prime contractor and the prime architect must each have an authorized representative present for the entire meeting and must sign the attendance log.
Failure to attend will result in disqualification of any proposer that does not have an authorized representative present for the entire meeting.
A recording of the meeting may not substitute for attendance. After the meeting, the District will publish an addendum with the attendance log, minutes, any documents distributed, and any verbal modification to the solicitation.
14.2 Questions and Addenda
Submit all questions and requests for clarification in writing through U3P by the questions deadline. The District answers by addendum posted on U3P by the final addendum date. All addenda become part of the solicitation and must be acknowledged in Schedule A.
After the proposal deadline, the District may issue a limited addendum only to proposers that submitted proposals, as the Utah Procurement Code allows.
14.3 Proposal Deadline and Submission
Upload proposals to U3P by the deadline. Proposals still uploading at the posted closing time will not be accepted, so allow enough time to finish.
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 15
Proposals are not opened before the deadline. After the deadline, a proposer may not change its proposal in a way that harms the District's interest or fair competition.
A proposer may withdraw its proposal in writing at any time before contract award.
Proposals remain valid for 90 days after the due date.
14.4 Business Confidential Information
A proposer claiming protected status for trade secrets, protected commercial information, or non-individual financial information under Utah Code 63G-2-305 and 63G-2-309 must submit, with its proposal:
• a Claim of Business Confidentiality form with a concise statement of the reasons for the claim;
• a version marked "Redacted Version," with the protected information blacked out or removed; and
• a non-redacted version marked "Protected Business Confidential."
Without a Claim of Business Confidentiality and a redacted copy, the proposal is a public record.
Fees and pricing cannot be designated confidential. A proposal designated in its entirety as "protected," "confidential," or "proprietary" is non-responsive unless the designation is removed.
After award, the District discloses records as the Government Records Access and Management Act and the applicable procurement rules provide.
14.5 Evaluation Committee and Conduct
The District appoints an Evaluation Committee of at least three members under the Utah Procurement Code.
It includes at least:
• a District representative;
• the Transportation Director; and
• an independent architect or construction professional.
The District may add other District staff as evaluators, provided the same evaluators score every proposer.
Before taking part, each evaluator signs a conflict-of-interest and confidentiality statement. Each evaluator uses independent judgment and does not communicate with proposers outside the official process.
Committee deliberations may be held in private.
DFCM may, at its option, take part in interviews, evaluation, scoring, and past-performance ratings. Its participation is welcome but not required.
Proposers may not contact, or offer gifts or gratuities to, District board members or employees, Evaluation Committee members, or DFCM staff to influence the selection, or in a way that gives the appearance of influencing it. This applies from issuance through award. Violation may result in disqualification.
14.6 Discussions and Best and Final Offers
The Committee may:
• hold clarifications with a proposer to better understand whether the proposer is responsible or its proposal responsive; and
• with the approval of the procurement official, request best and final offers from responsive proposers, under the conditions in Utah Code 63G-6a-707.5.
14.7 Subcontractor Procurement
The DB Team competitively bids subcontracts under the Utah Procurement Code, with the District observing.
This applies to subcontracts not specifically included in the DB Team's proposal. They are procured with a
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 16 standard procurement process, or an authorized exception, in the same manner as if the District procured them directly.
The DB Team reports each selected subcontractor to the District and updates the list as subcontractors are added. The District may audit compliance.
14.8 District Reservation of Rights
The District may cancel this solicitation, reject any or all proposals, or waive immaterial irregularities when that is in its best interest. It may also determine that a proposer is not responsible.
15. Proposal Requirements Submit one PDF organized by the tabs below, on 8.5×11 pages in 10-point type or larger. Schedule C, the Fee Proposal Form, is issued as a separate document. Submit it as a separate PDF, uploaded separately as the sealed fee submission.
The page limit is 13 pages plus two 11×17 pages (organizational chart and schedule). Covers, tab dividers, and forms do not count. Pages over the limit will not be read. Hyperlinks to outside content will not be evaluated.
Pass/fail requirements. A proposal missing any of these is non-responsive:
• The prime contractor holds a current Utah general building contractor license (B100 or E100), and the prime architect holds a current Utah architect license.
• The prime contractor signs as the single contracting entity for the team and has at least 10 years of continuous operation.
• A signed Certification of Proposal (Schedule A), and a debarment, suspension, and termination certification for the prime contractor and the prime design firm.
• A current Utah business license, proof of required liability and workers' compensation insurance, and a 5% bid bond with the fee proposal.
• Attendance by the prime contractor and the prime architect at the mandatory pre-submittal meeting.
• Eligibility under the DFCM qualified contractor registry for public school construction, as required by
Utah Code 63A-5b-1203(6) and 63A-5b-1216. Proposers list their registry status in Schedule A.
Tab Content Page limit
1. Letter of introduction Firms, single point of contact, capacity to start January 4, 2027 1
2. Team and key personnel Org chart (11×17); one-page resumes for the DB Project Manager, Project Architect, Superintendent, MEP Engineer, and Preconstruction Estimator; Utah license numbers; percent of time committed
5 + 11×17
3. Similar project experience Up to 4 projects completed in the last 10 years: at least 2 design-build (progressive preferred) and at least 2 vehicle maintenance, transportation, or industrial service facilities of 15,000 sf or more. For each: owner, size, delivery method, original vs. final cost and schedule, and which proposed staff worked on it
4. Design Phase approach and cost control
How design and cost develop together; cost model reporting; how layout, storage, program fit, and future CTE questions get resolved with the District; how the GMP is built and subcontracts are bid; early work packages
5. Schedule and fast delivery Critical-path schedule (11×17) from contract to final completion, showing Design Phase milestones, City and DFCM reviews, GMP, long-lead items, and SSB coordination; one-page narrative on the fastest credible path to opening
1 + 11×17
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 17
Tab Content Page limit
6. Risk and campus operations
Ranked risks with mitigation; plan for year-round bus operations, fire access, and SSB coordination
7. References DFCM Performance References Form for 3 projects Form
8. Fee proposal (separate PDF, sealed)
Schedule C (issued as a separate document; upload separately) and 5% bid bond
Form
9. Certifications Schedule A, debarment statement, licenses Forms
16. Evaluation and Scoring The Evaluation Committee evaluates each responsive proposal from a responsible proposer, using only the criteria below.
# Criterion Points Tab Full points for
1 Key personnel 25 2 DB Project Manager 10, Project Architect 6, Superintendent 5, MEP Engineer 2, Preconstruction Estimator 2: years in role, comparable projects, time committed
2 Similar project experience 20 3 Vehicle maintenance or industrial service facilities, delivered design-build by this team, on cost and schedule
3 Design Phase approach and cost control
20 4 A clear, collaborative process with cost visible at every milestone and a credible path to a cost-effective GMP
4 Fees 15 8 See Fee Scoring 5 Schedule and fast delivery 10 5 Credible critical path; 6–9 month construction; shorter credible durations score higher 6 Past performance 5 7 DFCM ratings and reference scores, averaged 7 Risk and campus operations 5 6 Site-specific, ranked risks; workable plan for bus operations and
SSB coordination Written total 100 8 Interviews (optional) +20 — Interview scoresheet below Maximum total 120
16.1 Ratings
Each evaluator rates criteria 1–3 and 5–7 on the scale below and records a short justification. The Committee's score for each criterion is the average of the evaluators' scores:
Points = (average rating ÷ 5) × criterion points
Rating Meaning
5 Exceeds the requirement with specific, verifiable evidence; no weaknesses 4 Fully meets the requirement with specific evidence; minor weaknesses 3 Meets the requirement; some content generic 2 Partly meets the requirement; significant gaps 1 Minimal or unconvincing 0 Not addressed, or contradicts the RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP
Lake Mountain School District – Bus Maintenance & Transportation Facility – Progressive Design-Build RFP | Page 18
16.2 Fee Scoring
Fees are scored by component, so no budget figure is needed:
• Design Phase fee: 6 points
• Construction Phase general conditions: 5 points
• DB fee percentage: 4 points For each component: points = (lowest proposed ÷ proposer's proposed) × component points. Bonds and insurance percentages are reviewed for reasonableness but not scored.
Fee proposals are kept separate from the Evaluation Committee. Schedule C, the Fee Proposal Form, is issued as a separate document and must be uploaded separately as the sealed fee submission. Evaluators will not see fee information until the Committee has submitted its final scores for all other criteria, including any interviews. The Procurement Officer then scores the fees using the formula above and calculates each proposer's total score.
16.3 Evaluator Scoresheet (Written)
# Criterion Points Rating (0–5) Score Notes
1 Key personnel 25 2 Similar project experience 20 3 Design Phase approach and cost control 20 4 Fees 15 Components 5 Schedule and fast delivery 10 6 Past performance 5 7 Risk and campus operations 5 Total 100
16.4 Interviews (Optional)
The Committee may vote to hold interviews, and the vote is recorded in the procurement file.
• Notice and dates: proposers are told by noon on Monday, December 14, 2026, whether interviews will be held. Interviews are December 16–17, 2026. If no notice is sent, there are no interviews.
• Who is interviewed: every responsive proposer. If more than five propose, the five highest written totals, plus any proposer within 3 points of fifth place.
• Length: up to 60 minutes and no longer: a presentation of up to 15 minutes, then the five questions below, in order.
• Attendees: DB Project Manager, Project Architect, Superintendent, and MEP Engineer; six people maximum. A key person absent without a District-approved substitute scores 0 on interview criterion I4.
Written scores are not affected.
• Scoring: written scores are final before interviews, and interview points are added to them. Answers that contradict the written proposal score 2 or lower, and the written proposal governs.
• Ties: go to the proposer with the higher combined Fee and Schedule scores.
# Criterion Points Rating (0–
5) Score Question
I1 Team experience and project fit
4 How have your contractor and design firms delivered design-build…
This is the start of the file's text. The full file is on GovTribe.