7 - Form 66 Schedule of Material Submittals_Sample.xlsx

XLSX spreadsheet 36 KB Posted

Attached to
Multiple-Award Construction Contract (MACC) Holloman AFB, NM Federal contract opportunity
Solicitation number
PKB-0001
Issued by
Department of the Air Force Air Combat Command

About this file

This document is a schedule of material submittals for a construction project to build a warehouse at Holloman Air Force Base in New Mexico under multiple-award construction contract PKB-0001. The schedule lists 33 items requiring submittal to the contracting office, including air conditioning units, stairs, plumbing details, roof and ceiling plans, and as-built drawings. For each item, the schedule includes columns for the contractor to provide the required submission date, dates the submittal was received and sent to the civil engineering office for review, the return suspense date for the civil engineering office, submittal numbers, dates the contractor was notified of approval or disapproval, and remarks. The schedule provides a framework for contractors to receive necessary approvals from the Air Force for materials and plans under the multiple-award contract to construct facilities at Holloman Air Force Base.

View the file

Other files for this federal contract opportunity

Other files attached to Multiple-Award Construction Contract (MACC) Holloman AFB, NM, newest first.
File Type Posted
Amd 2 - Solicitation Amendment FA480123R00010002 SF 30.pdf PDF
Amd 2 - 3 - Section L.docx DOCX document
Amd 2 - 2a - IDIQ Coefficient Rate Schedule.xlsx XLSX spreadsheet
Amd 2 - Questions and Answers.xlsx XLSX spreadsheet
Amd 2 - 5d - Ordering Procedures - SIMPLIFIED.docx DOCX document
4 - Section M - Amd 1.docx DOCX document
4 - Section M - Amd 1.docx DOCX document
Solicitation Amendment FA480123R00010001 SF 30.pdf PDF
2b - Demonstration Project Price Sheet - Amd 1.xlsx XLSX spreadsheet
Attachment 16 - Financial Information Form - Amd 1.docx DOCX document
Attachment 17 - Bonding Information Form - Amd 1.docx DOCX document
WD - Building - NM20230025 6_9_2023 - Amd 1.pdf PDF
Questions and Answers for Amd 1.xlsx XLSX spreadsheet
5c - Ordering Procedures - BTV - Amd 1.docx DOCX document
5b - Ordering Procedures - PPT - Amd 1.docx DOCX document
Holloman AFB IFS_20230901 - Amd 1.pdf PDF
5d - Ordering Procedures - SIMPLIFIED - Amd 1.docx DOCX document
2a - IDIQ Coefficient Rate Schedule - Amd 1.xlsx XLSX spreadsheet
3 - Section L - Amd 1.docx DOCX document
4 - Section M - Amd 1.docx DOCX document
8 - Construction Cost Estimate spreadsheet - Amd 1.xlsx XLSX spreadsheet
5a - Ordering Procedures - LPTA - Amd 1.docx DOCX document
6 - Demostration project SOW R2 - Amd 1.docx DOCX document
WD - Highway - NM20230025 1_6_2023 - Amd 1.pdf PDF
WD - Heavy - NM20230008 6_9_2023 - Amd 1.pdf PDF
Attachment 17 - Bonding Information Form.docx DOCX document
Attachment 16 - Financial Information Form.docx DOCX document
3b - SubContractor Consent Letter.docx DOCX document
5b - Ordering Procedures - PPT.docx DOCX document
5c - Ordering Procedures - BTV.docx DOCX document
6 - IDIQ Demostration project SOW KWRD 210076 R1.docx DOCX document
9 - Form 3064 Construction Progress Schedule.xlsx XLSX spreadsheet
10 - Wage Determinations.pdf PDF
11 - Reserved.docx DOCX document
13 - Holloman AFB Standard Design.pdf PDF
3 - Section L - final - 1 Sep 2023.docx DOCX document
4 - Section M - final - 1 Sep 2023.docx DOCX document
5a - Ordering Procedures - LPTA.docx DOCX document
5d - Ordering Procedures - SIMPLIFIED.docx DOCX document
8 - Construction Cost Estimate spreadsheet.xlsx XLSX spreadsheet
14 - DoD Safe Instructions.pptx PPTX presentation
1 - SOLICITATION - FA480123R0001.pdf PDF
2 - IDIQ Pricing Sheet.xlsx XLSX spreadsheet
3a - Section L_Client Authorization Letter.docx DOCX document
6a - PROPOSED FLOOR PLAN - KWRD 210076.pdf PDF
12 - Base Access Instructions.pdf PDF
5 - IDIQ SOW - dated 22 Aug 2023.docx DOCX document
6b - UTILITY STE PLAN - KWRD 210076.pdf PDF
15 - Holloman AFB IFS.pdf PDF
Show all 49

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT TITLESOLICITATION / CONTRACT NO.
KWRD 21-0076Construct SFS WarehouseFA480123R0001
(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

CERTIF. OF COMPLIANCE SHOP DRAWINGS COLOR SELECTION MANUFATURUR'S RECOMMENDATION CATALOG DATA O&M RECOMMENDATIONS CALCULATIONS WARRANTY DRAWINGS REPORTS TEST RESULTS REQUIRED SUBMISSION DATE fergusog: Enter the due date from the Contractor (MM/DD/YY)

DATE RECEIVED IN CONTRACTING

fergusog: Enter the date received from the Contractor. (MM/DD/YY)

DATE TO CIVIL ENGINEERING

fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)

RETURN SUSPENSE DATE

fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

SUBMITTAL NUMBERS

fergusog: Enter the Submittal Number

DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL

fergusog: Enter Resubmittal Number

FINAL APPROVAL

fergusog: Enter the submittal final approval date

(MM/DD/YY)

REMARKS

fergusog: Enter any comments pertaining to the submittal

APPROVED

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

fergusog: Enter Resubmittal Number

DISAPPROVED

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

fergusog: Enter the submittal final approval date

(MM/DD/YY)

fergusog: Enter any comments pertaining to the submittal

GENERALThis document shall be a "live document"
1Project Specific Form 66XANTP + 5
2Construction ScheduleXANTP + 5
3Contractor's Health, Safety, and Environment PlanXANTP + 5
4Contractor's QA/QC PlanXANTP + 5
5Copy of Engineering License(s) of person or consultancy responsible for designXANTP + 5
DESIGN
6All submissions to be provided electronically.XXXXXXXXXXX
735% Design & Form 66XX
865% Design, Form 66, & Draft 1354XX
8Construction ScheduleXCNTP + 5
9
Material Submittals-Contractor to complete this section with all materials to be used in construction (Ex. Below)
10Air Conditioning Units
11Stairs
12Frame Detail
13Water heaters
14Shut-off valves
15Plumbing detail
16Roof & ceiling detail
17Exhaust fan detail
18Acoustic materials
19Smoke detector
20Fixture detail
21Interior wall schematic
22Floor drainage schematic
23Floor detail
24Electrical detail
25Toilets
26Sinks
27Showers
28Exterior color
29Exterior door
30Shower bench
31Floor mats
32As-Built Drawings
33Construction schedule
TEST RESULTS
34All submissions to be provided electronically.X
CLOSEOUT
35Warranty DocumentsXFinal + 7
36O&M ManualsFinal + 7
37DD 1354Final + 7
38As-Builts (electronic in AutoCAD & PDF)XFinal + 7