7-10. Sample Score Sheet 2025-09-29.doc

DOC document 82 KB Posted

Attached to
UDOT RFP- Fiber Optic and ATMS Construction Services
Solicitation number
UDOT260084MP
Issued by
Utah

About this file

This document is a Request for Proposal (RFP) scoring sheet issued by the Utah Department of Transportation (UDOT) for Fiber Optic Maintenance, Repair, and Installation services. The solicitation seeks qualified contractors to provide construction services with a contract period ending 03/31/2028 and no renewal options. UDOT anticipates making multiple contract awards for fast-turnaround, straightforward construction services where contractors will be paid on a line-item basis for work performed. The evaluation process includes three stages: mandatory minimum requirements (pass/fail), technical proposal evaluation (60 points), and cost proposal evaluation (40 points).

The scoring methodology uses a comprehensive point system that evaluates contractors on experience (40 points), resources (10 points), and internal policies (10 points). Cost proposals will be scored based on a ratio calculation where the lowest proposed cost receives maximum points, and proposals more than double the lowest cost receive zero points. Contractors must be certified in Fiber Optic Installation and Work Zone safety, with scoring ranging from zero (fail) to five (excellent). The state retains the right to reopen the solicitation to allow additional contractors to submit responses at any time, emphasizing flexibility in contractor selection for these specialized construction services.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL

Fiber Optic Maintenance, Repair, and Installation Proposal Evaluation Score Sheet

Firm Name:

Evaluator:

Date:

Stage 1: Determination of Responsiveness (Pass/Fail):

Mandatory Minimum Requirements
Pass
Fail
Notes

1. Contractor must be Certified in Fiber Optic Installation.

2. Contractor must be certified in Work Zone safety and SWIP training

Responses that fail in any of the above will not proceed on to the Technical Evaluation Stage.

Stage 2: Detailed Technical Evaluation (Scored):

Technical Evaluation

EVALUATION CRITERIA
Points Possible
Score

(1 - 5)

Weight
Points

1. Experience

· Demonstrated Experience in Fiber Optic Installation
40 points

X 8

2. Resources

· Staffing and equipment resources to address project work under this contract in a timely manner.
10 points

X 2

3. Policies

· Internal policies, safety standards and plan, and quality control procedures to minimize mistakes, ensure a safe work environment, and ensure high quality construction.
10 points

X 2

Total Technical Evaluation Points (60 points possible)

Stage 3: Cost Proposal Evaluation (Scored):

Cost Evaluation

Evaluation Criteria
Points Possible
Points
· Total Project Cost (predetermined sample project)
40 points
*Inserted by UDOT Procurement

Total Cost Evaluation Points (40 points possible)

TOTAL EVALUATION POINTS (100 POINTS POSSIBLE)

Evaluation of Cost Proposals: The offeror with the lowest total cost will receive the maximum available Cost points. All other offerors will receive points as determined by the ratio* of their cost to the lowest offered cost. Final cost scores will be calculated based on the following:

*Ratio Calculation: Points assigned to each offeror’s Cost Proposal will be based on the Lowest Proposed Cost. The offeror with the Lowest Proposed Cost will receive 100% of the cost points. All other offerors will receive a portion of the total cost points based on what percentage higher their proposed cost is than the Lowest Proposed Cost. An Offeror whose proposed cost is more than double (200%) the Lowest Proposed Cost will receive no points. The formula to compute the points is: Cost Points x (2- (Proposed Cost/ Lowest Proposed Cost)).

SOLICITATION CRITERIA SCORE SUMMARY

Final Selection Criteria
Max. Score Available
Stage 1: Mandatory Minimum Requirement
Pass/Fail
Stage 2: Technical Proposal
60
Stage 3: Cost Proposal
40
Total Solicitation Points Possible
100

Scoring:

(a) Five points (Excellent): The proposal addresses and exceeds all of the requirements or criteria described in the RFP.

(b) Four points (Good): The proposal addresses all of the requirements or criteria described in the RFP and, in some respects, exceeds them.

(c) Three points (Satisfactory): The proposal addresses all of the requirements or criteria described in the RFP in a minimum satisfactory manner.

(d) Two points (Unsatisfactory): The proposal addresses the requirements or criteria described in the RFP in an unsatisfactory manner; or

(e) One point (Poor): The proposal inadequately addresses the requirements or criteria described in the RFP or cannot be assessed due to incomplete information; or

(f) Zero (Fail): The proposal fails to address the requirements or criteria described in the RFP or cannot be assessed due to missing information.