11-05. Submittal Form- Pricing- All Regions- 2025-09-30 AMENDED.xlsx

XLSX spreadsheet 33 KB Posted

Attached to
UDOT RFP- Fiber Optic and ATMS Construction Services
Solicitation number
UDOT260084MP
Issued by
Utah

About this file

This is a comprehensive pricing submittal form for maintenance, repair, and installation of Intelligent Transportation Systems (ITS) and Fiber Optic Systems for the Utah Department of Transportation (UDOT), covering multiple regions. The document details an extensive line-item pricing schedule for various construction services, including traffic control, conduit installation, trenching, directional boring, junction box installations, communication cabling, splicing and testing, labor rates, and environmental controls. The contract is set to run until 03/31/2028 with no renewal options, and UDOT anticipates making multiple contract awards to qualified contractors who can perform fast-turnaround construction services across five defined regions.

The pricing document provides unit prices for over 230 specific line items, ranging from traffic control services to detailed fiber optic cable installation and environmental restoration work. Pricing varies by region and includes detailed specifications for different installation techniques, depths, distances, and equipment types. Contractors will be compensated on a line-item basis for actual work performed, with pricing established for specific quantities and service types. The document indicates that contractors must adhere to UDOT's standards and specifications, and the state retains the right to reopen the solicitation to allow additional contractors to submit responses at any time. The pricing structure allows for precise cost estimation and flexible deployment of construction services across Utah's transportation infrastructure.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pricing Per Region

Maintenance, Repair, and Installation of the ITS and Fiber Optic System

Item Pricing- AMENDED 2025-09-30

Region 1 Region 2 Region 3 Region 4- East Region 4- West

NODESCRIPTIONUNITUNIT PRICE
Traffic Control
1Traffic Control for Work - Beyond the Shoulder - up to 1,000 feetLump
2Traffic Control for Work - Shoulder Operation - up to 1,000 feetLump
3Traffic Control for Work - Single Lane Closure - up to 1,000 feetLump
4Traffic Control for Work - Two Lane Closure - up to 1,000 feetLump
5Traffic Control in an Urban Intersection Under 50 MPH (TC-5)Lump
6Traffic Control Temporary Pedestrian Access Reroute (TC-6)Lump
7Traffic Control for Work - Project Specific (bid following contractor shortlist)ProjectN/AN/AN/AN/AN/A
8Police SupportInvoiceN/AN/AN/AN/AN/A
9Additional Advance Warning Arrow PanelDev/day
10Attenuator TruckHour
11Variable Message Sign (VMS)Dev/day
12Rumble StripsDay
13FlaggingHr
Conduit
141 1/4 inch ConduitFt
152 inch ConduitFt
163 inch ConduitFt
171D ConduitFt
182D ConduitFt
194D ConduitFt
202 inch Galvanized Rigid ConduitFt
212 inch Liquidtight Flexible ConduitFt
224 inch Galvanized Rigid ConduitFt
234 inch Liquidtight Flexible ConduitFt
246 inch Galvanized Rigid ConduitFt
256 inch Liquidtight Flexible ConduitFt
26Individual 12.7/10mm MicroductFt
27Individual 16/13mm MicroductFt
28Three 12.7/10mm Microducts with one No. 14 Locate WireFt
2918/14mm Microduct BundleFt
30No. 14 Locate Wire placed in New or Existing ConduitFt
31Detectable Pull Tape placed in Existing ConduitFt
State Furnished Conduit
32Install State Furnished Conduit (up to eight conduits, 3 inch diameter or less)Ft
33Install State Furnished Conduit (more than eight conduits, 3 inch diameter or less)Ft
34Install One State Furnished Microduct in Existing ConduitFt
35Install Three State Furnished Microducts in Existing ConduitFt
Installation
36Install State Furnished Conduit ( up to eight conduits, 3 inch diameter or less) Trench and Rock Saw adder for additional conduit placement up to a 4D, 16-1.25” conduits (or similar product bundle size)Ft
37Trenching 3 feet Deep - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
38Trenching 3 feet Deep - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
39Trenching 3 feet Deep - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
40Trenching 3 feet Deep - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
41Trenching 5 feet Deep - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
42Trenching 5 feet Deep - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
43Trenching 5 feet Deep - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
44Trenching 5 feet Deep - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
45Trenching 4 feet Deep - In Pavement - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
46Trenching 4 feet Deep - In Pavement - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
47Trenching 4 feet Deep - In Pavement - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
48Trenching 4 feet Deep - In Pavement - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
49Rock Saw 26 inches Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
50Rock Saw 26 inches Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
51Rock Saw 26 inches Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
52Rock Saw 26 inches Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
53Rock Saw 3 feet Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
54Rock Saw 3 feet Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
55Rock Saw 3 feet Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
56Rock Saw 3 feet Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
57Rock Saw 4 feet Deep and 5 inches Minimum Width - In Pavement - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
58Rock Saw 4 feet Deep and 5 inches Minimum Width - In Pavement - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
59Rock Saw 4 feet Deep and 5 inches Minimum Width - In Pavement - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
60Rock Saw 4 feet Deep and 5 inches Minimum Width - In Pavement - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
61Rock Saw 3 feet Deep and 5 inches Minimum Width - Outside Pavement - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
62Rock Saw 3 feet Deep and 5 inches Minimum Width - Outside Pavement - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
63Rock Saw 3 feet Deep and 5 inches Minimum Width - Outside Pavement - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
64Rock Saw 3 feet Deep and 5 inches Minimum Width - Outside Pavement - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
65Rock Saw 5 feet Deep and 5 inches Minimum Width - Outside Pavement - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
66Rock Saw 5 feet Deep and 5 inches Minimum Width - Outside Pavement - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
67Rock Saw 5 feet Deep and 5 inches Minimum Width - Outside Pavement - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
68Rock Saw 5 feet Deep and 5 inches Minimum Width - Outside Pavment - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size)Ft
69Directional Bore - 4 inch Diameter Product Bundle - 0 Feet to 2,000 FeetFt
70Directional Bore - 4 inch Diameter Product Bundle - 2,000 Feet to 4,000 FeetFt
71Directional Bore - 4 inch Diameter Product Bundle - 4,000 Feet to 10,000 FeetFt
72Directional Bore - 4 inch Diameter Product Bundle - 10,000+ FeetFt
73Directional Bore - 8 inch Diameter Product Bundle - 0 Feet to 2,000 FeetFt
74Directional Bore - 8 inch Diameter Product Bundle - 2,000 Feet to 4,000 FeetFt
75Directional Bore - 8 inch Diameter Product Bundle - 4,000 Feet to 10,000 FeetFt
76Directional Bore - 8 inch Diameter Product Bundle - 10,000+ FeetFt
77Directional Bore - 12 inch Diameter Product Bundle - 0 Feet to 2,000 FeetFt
78Directional Bore - 12 inch Diameter Product Bundle - 2,000 Feet to 4,000 FeetFt
79Directional Bore - 12 inch Diameter Product Bundle - 4,000 Feet to 10,000 FeetFt
80Directional Bore - 12 inch Diameter Product Bundle - 10,000+ FeetFt
8124 inch Wide Conduit Hanger Assembly between Bridge GirdersEa
8224 inch Wide Conduit Hanger Assembly under Bridge Deck OverhangEa
83Bridge Attached Conduit System - Project Specific (bid following contractor shortlist)ProjectN/AN/AN/AN/AN/A
8430' Wood Pole with Riser StandoffsEa
8530' Wood Pole without Riser Standoffs and Ground AnchorEa
863/8" Aerial Strand with Aerial Microduct MD7 Attached to Existing Pole(s)Ft
87Conduit Entry into Existing BuildingLump
Proofing & Conduit Repair
88Spot Repair 1 1/4 inch Conduit less than 100 feet10ft increment
89Spot Repair 2 inch Conduit less than 100 feet10ft increment
90Spot Repair 3 inch Conduit less than 100 feet10ft increment
91Spot Repair MD7 16/13 Microduct less than 100 feet10ft increment
92Spot Repair MD7 18/14 Microduct less than 100 feet10ft increment
93Spot Repair Individual Microduct (12.7/10 or 16/13) less than 100 feet10ft increment
94Spot Repair 1D Conduit less than 100 feet10ft increment
95Spot Repair 2D Conduit less than 100 feet10ft increment
96Spot Repair 4D Conduit less than 100 feet10ft increment
97Proofing Existing Conduit with State approved MandrelFt
98Proof Existing MicroductFt
Junction Boxes
99Type I - Polymer Concrete Junction Box (24" Deep)Ea
100Type II - Polymer Concrete Junction Box (24" Deep)Ea
101Type III - Polymer Concrete Junction Box (24" Deep)Ea
102Type II - Polymer Concrete Junction Box (36" Deep)Ea
103Type III - Polymer Concrete Junction Box (36" Deep)Ea
104Type II - High Density Polyethylene (HDPE) Junction Box (36" Deep)Ea
105Type III - High Density Polyethylene (HDPE) Junction Box (36" Deep)Ea
106Type II - Hybrid Junction Box (PC Body with HDPE lids) (36" Deep)Ea
107Type III - Hybrid Junction Box (PC Body with HDPE lids) (36" Deep)Ea
108Replace Type I - Polymer Concrete Junction Box LidEa
109Replace Type II - Polymer Concrete Junction Box LidEa
110Replace Type III - Polymer Concrete Junction Box LidEa
111Replace Type II - HDPE Junction Box LidEa
112Replace Type III - HDPE Junction Box LidEa
113Concrete Collar for Type I - Junction BoxEa
114Concrete Collar for Type II - Junction BoxEa
115Concrete Collar for Type III - Junction BoxEa
116Concrete Floor in Type I - Junction BoxEa
117Concrete Floor in Type II - Junction BoxEa
118Concrete Floor in Type III - Junction BoxEa
119Type I Junction Box Precast CollarEa
120Type II Junction Box Precast CollarEa
121Type III Junction Box Precast CollarEa
122Remove Type I Junction BoxEa
123Remove Type II Junction BoxEa
124Remove Type III Junction BoxEa
125Remove Junction Box Larger than Type IIIEa
126Grout or Epoxy PatchingEa
127General Maintenance of Junction BoxEa
128Pre-Cast Utility Vault (4'x4'x51")Ea
129Pre-Cast Utility Vault (4'x6'-6"x84")Ea
130Furnish and Install Locate Ball or Disk in Existing Junction BoxEa
131Furnish and Install Maintenance MarkerEa
State Furnished Junction Boxes
132Install State Furnished Type II Junction BoxEa
133Install State Furnished Type III Junction BoxEa
Communication Cabling
134Single Mode Non Armored Fiber Optic Drop Cable - 6 Strand - with Six Port Fiber Distribution Unit - 200 Feet (includes 200 feet of cable length)Ea
135Single Mode Non Armored Fiber Optic Drop Cable - 6 Strand (additional cable length beyond 200 feet)Ft
136Single Mode Non Armored Fiber Optic Drop Cable - 12 Strand - with Twelve Port Fiber Distribution Unit - 200 Feet (includes 200 feet of cable length)Ea
137Single Mode Non Armored Fiber Optic Drop Cable - 12 Strand (additional cable length beyond 200 feet)Ft
138Single Mode (Armored or Non Armored) Fiber Optic Cable - 12 Strand CountFt
139Single Mode (Armored or Non Armored) Fiber Optic Cable - 24 Strand CountFt
140Single Mode (Armored or Non Armored) Fiber Optic Cable - 72 Strand CountFt
141Single Mode (Armored or Non Armored) Fiber Optic Cable - 144 Strand CountFt
142Single Mode (Armored or Non Armored) Fiber Optic Cable - 288 Strand CountFt
143Single Mode Micro Fiber Optic Cable - 72 StrandFt
144Single Mode Micro Fiber Optic Cable - 144 StrandFt
145Single Mode Micro Fiber Optic Cable - 288 StrandFt
146Fiber Optic Cable RemovalFt
147Cat 5e CableFt
State Furnished Communication Cabling
148Install State Furnished Single Mode Micro Fiber Optic CableFt
149Install State Furnished SMF CableFt
Splicing and Testing
150Remove and Replace Fiber Optic Splice EnclosureEa
151Install Splice EnclosureEa
152Open and Close Existing Splice CaseEa
1531-6 Fusion Splices at one locationEa Splice
1547-12 Fusion Splices at one locationEa Splice
15513-48 Fusion Splices at one locationEa Splice
15649-96 Fusion Splices at one locationEa Splice
15797-144 Fusion Splices at one locationEa Splice
158144-288 Fusion Splices at one locationEa Splice
159Install 72 CT Patch Panel in BuildingEa
160Install 144 CT Patch Panel in BuildingEa
161Install 288 CT Patch Panel in BuildingEa
162Terminate Patch PanelEa Strand
163Terminate ST Connector / AnerobicEa
164Bare End Fiber Optic TestEa Strand
165Fiber Optic Light Source/Power Meter Test and OTDR TraceEa
Labor
166Labor - TechnicianHr
167Labor Emergency Rate - TechnicianHr
168Labor- Journeyman ElectricianHr
169Labor - Electrician TechnicianHr
170Locating of UDOT infrastructureHr
171Locating of UDOT infrastructureDay
Removal and Restoration
172Subsurface Utility Exploration - Vacuum Excavation - Pot HolesEa
173Subsurface Utility Exploration - Mechanical Excavation - Pot HolesEa
174Trench Backfill in PavementCu Ft
175Remove and Replace HMA Surface, up to 4,000 square feetSq Ft
176Place HMA Surface/ Roto mill - Project specific (bid following contractor shortlist)ProjectN/AN/AN/AN/AN/A
177Asphalt Repair (HMA)Actual CostN/AN/AN/AN/AN/A
178SandTons
179Free Draining Granular Backfill BorrowTons
180Untreated Base CourseTons
181Geotextile ( Separation or Stabilization)Sq Yd
182Flowable FillCu Yd
183Concrete Curb (any type) - Less than 50 feetFt
184Concrete Curb (any type) - Greater than 50 feetFt
185Concrete FlatworkSq Ft
186Furnish/Install Chain Link FencingActual CostN/AN/AN/AN/AN/A
187Striping/Pavement MarkingsActual CostN/AN/AN/AN/AN/A
188Remove and Replace SidewalkSq Ft
189Remove and Replace Stamped Decorative SurfaceSq Ft
190Remove and Replace Curb and GutterFt
191Install and Remove Temporary Cold PatchSq Ft
192Pavement Marking Paint - 4 inch White or YellowFt
193Pavement Marking Tape - 4 inch White or YellowFt
194Remove and Replace LandscapingSq Ft
195Remove and Re-Install Existing Delineator PostEa
196Remove Existing Delineator PostEa
197Delineator Post - SteelEa
198Delineator Post - Flexible PlasticEa
Environmental Controls
199Temporary Erosion and Sediment Control - Check DamFt
200Temporary Erosion and Sediment Control - Silt Fence Slope BarrierFt
201Temporary Erosion and Sediment Control - Slope DrainFt
202Temporary Erosion and Sediment Control - Drop Inlet BarrierFt
203Temporary Erosion and Sediment Control - Sediment TrapCu Ft
204Temporary Erosion and Sediment Control - Curb inlet BarrierFt
205Temporary Erosion and Sediment Control - Temporary BermEa
206Temporary Erosion and Sediment Control - 9 inch Fiber RollFt
207Broadcast Seed1000 Sq Ft
208Drill Seed1000 Sq Ft
209Environmental Control Supervisor (ECS)Week
Contractor Furnished ITS Equipment Installation
210ITS Cabinet FoundationEa
211CCTV Pole FoundationEa
212Highway Luminare Pole FoundationEa
213Underground Service Pedestal - New Installation w/ BaseEa
214H-Frame (Complete)Ea
215Electrical Disconnect on Existing H-FrameEa
216Transformer on Existing H-FrameEa
217Install Solar Panel AssemblyEa
218Install Solar Batter AssemblyEa
219RHH-USE2-RHW2, AWG 2-6 (copper)Ft
220RHH-USE2-RHW2, AWG 8-12 (copper)Ft
221RHH-USE2-RHW2, AWG 14 (copper)Ft
222Bare Copper Ground Wire, No. 6Ft
223Ground Rod 3/4" x 10'Ft
State Furnished ITS Equipment Installation
224334 ATMS CabinetEa
225Pole Mount 336 ITS CabinetEa
226CCTV Pole - 45 feetEa
227CCTV Pole - 60 - 80 feetEa
228Highway Luminare PoleEa
229CCTV AssemblyEa
230Non-Intrusive Detector AssemblyEa
231IP Radio AssemblyEa
232Solar Panel AssemblyEa
233Solar Battery AssemblyEa
Incidental Materials
997Pick up and delivery of UDOT materials ( small loads, pick up truck )Mile
998Pick up and dellivery of UDOT materials ( Large loads, semi truck )Mile
999Incidental ItemsInvoiceN/AN/AN/AN/AN/A

File details come from the government source that posted it. Updated .