This is a Questions and Answers document for federal contract opportunity CO ERFO FS SNJUAN 2026-1(1) Fall Creek Road.
The document addresses procedural inquiries from potential bidders. Regarding site access, no formal site visit is scheduled, but the project site is open and accessible to the public for self-directed inspection. The proposal submission deadline is July 28, 2026, as specified in page A-1, box 13. For project performance timelines, bidders are directed to Section 108 of the solicitation documents for the overall period of performance and completion deadline. Work commences upon issuance of the Notice-to-Proceed, with the final completion date specified in Section 108. The questions and answers were issued on two dates: July 14, 2026 and July 28, 2026.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for CO ERFO FS SNJUAN 2026-1(1) Fall Creek Road
July 14, 2026
Questions Answers 1 Is a site visit scheduled or can I arrange a site visit for the project? There is no site visit scheduled. The site is open and accessible to the public.
2 When is it due? Please see page A-1, box 13
July 28, 2026
Questions Answers 1 What is the overall period of performance for all work to be completed on this project?
See Section 108
2 Specifically, when can we start and what is the final deadline for completion?
Start once Notice-to-Proceed is issued, and reference Section 108 for completion.