This is a Critical Finding Inspection Report from the USDA Forest Service documenting structural deficiencies identified during an inspection of the W Fork of San Juan River bridge on Route 648 in Colorado (Structure Number 021306000001024).

The bridge, located 13.7 miles northeast of Pagosa Springs at mile point 2.50, was inspected on April 8, 2026, by Team Lead Benjamin Glenn and reviewed by Jason Hefter. The overall structure condition is rated as Fair (F). A critical finding was initially documented on October 22, 2025, following the 2025 Colorado October 10-13 Four Corners Monsoon Storms event, with the finding status remaining RO-Active as of the April 2026 inspection. The critical issue involves abutment undermining on the right abutment caused by scour from flooding and rain events. The CF Criterion requires immediate correction of scour or hydraulic problems. Initial actions included closing the bridge and placing temporary riprap to divert flow toward the channel center on October 22, 2025. As of April 6, 2026, the bridge remained closed. Riprap has been installed under and around the entire right abutment including wing walls; however, the scour hole persists and has grown significantly (50%) at one measurement location. Future corrective actions required include underpinning or replacing the abutment and adding scour countermeasures and stream training measures. Condition summary ratings are: B.C.01 - 6, B.C.02 - 7, B.C.03 - 6, B.C.04 - N, B.C.09 - 2, and B.C.11 - 1. The report includes extensive photographic documentation of scour conditions, riprap installation, abutment damage, guard rail damage, and deck-abutment joint gaps.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STRUCTURE NUMBER- 021306000001024 TEAM LEADER- Benjamin Glenn

INSPECTION DATE- 04/08/2026 STRUCTURE CONDITION- F - Fair

CRITICAL FINDING INSPECTION REPORT

Structure Name W FORK OF SAN

JUAN RIVER

Route Number 648

Structure Mile Point 2.50

Admin Org 021306

State 8 - Colorado

County 08079

Latitude 37.44988333333333

Longitude -106.91113611111112

Inspection Team Lead

Inspection Reviewer

Benjamin Glenn, 04/13/2026

Jason Hefter, 04/13/2026

© OpenStreetMap contributors

Location: 13.7 MI NNE OF PAGOSA SPG

37.44988, -106.91114

MAP PAGE

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER Route Number: 648, Mile Point: 2.50

Structure Number: #021306000001024 / Critical Finding

CRITICAL FINDINGS

Critical Finding ID:

Forest Specific Event Name: 2025 CO Oct10-13 FS Four Corners Monsoon Storms

CF Status: RO-Active

CF Inspection Date: 10/22/2025

CF Inspection Interval: 3

CF Found Date: 10/22/2025

Event Description/Cause (B4):

Rain

CF Criterion (B5): A - Immediate correction of scour or hydraulic problems needed

If Other (B5A):

Event Type/Cause (B12): B - Flood If Other (B12A):

Deterioration (B13): Other - Please explain If Other (B13A): Abutment undermining

Detailed Deficiency (B14): Other - Please explain If Other (B14A): Abutment undermining

CF Results (B15): D - Settlement or loss of support If Other (B15A):

Initial Actions (B17): Close bridge, place temporary riprap to divert flow to center of channel

10/22/2025

Resolved Actions (B19):

Future Actions (B20): Underpin or replace abutment, add scour countermeasures and stream training measures

CF Remarks:

--Bridge closure in place as of 10/23/2025 (10/22/2025).-- Rip rap has been installed under and around the entire right abutment, including wing walls. Scour hole persists and at one measurement location has grown significantly (50%).

Closure should remain in effect until undermining can be permanently fixed. (4/6/2026)

Condition Summary: B.C.01 - 6 B.C.02 - 7 B.C.03 - 6 B.C.04 - N B.C.09 - 2 B.C.11 - 1

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER nbibridges_31395_Top down view right abutment nbibridges-Side profile right abutment

Left abutment- Post 9 Cross section-Post 8

PHOTOS

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER

Cross section-Post 7 Cross section-Post 6

Cross section-Post 5 Cross section-Post 4

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER

Cross section-Post 3 Cross section-Post 2

Cross section-Right abutment-Post 1 Right abutment

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER

Right abutment measurement on top of toe 3 ft top of toe at 1 foot downstream of center right abutmnet

2 ft from top of toe at center of right abutmnet 4 ft from top of toe at upstream wing wall corner

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER

Upstream right abutment wing wall scour hole Upstream right abutment toe corner

Right abutment looking upstream Downstream right wing wall, rip rap installation

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER

Channel looking upstream Photo looking upstream at right abutment

Measurement reference with 12ft rod Center scour hole. 4 ft behind abutment wall. 6 foot from foot toe face

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER

Upstream right wing wall measurement from top of footer. Three 4' lengths Channel looking downstream

Right abutment Looking downstream measurement from top of footer Upstream right guard rail damage

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER

Downstream deck abutment joint gap Upstream deck abutment joint gap

Guard rail tree strike right abutment Downstream deck abutment joint gap

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER

Upstream deck, abutment joint gap Channel downstream photo

Channel upstream photo

Team Lead: Benjamin Glenn, Inspection Date: 04/08/2026

Bridge Name: W FORK OF SAN JUAN RIVER