CO ERFO FS SNJUAN 2026-1(1) Fall Creek Road Bid Tabulation Report.pdf

PDF 549 KB Posted

Attached to
CO ERFO FS SNJUAN 2026-1(1) Fall Creek Road
Solicitation number
6982AF26B000006
Issued by

About this file

This is a Bid Tabulation Report for a road construction project located on federal land managed by the Rio Grande National Forest in Colorado. The project, designated CO ERFO FS SNJUAN 2026-1(1) and titled Fall Creek Road, was solicited under Solicitation No. 6982AF26B000006. The bid opening occurred on August 13, 2026, in Lakewood, Colorado, with bids opened by Denise Martinez. Eight contractors submitted responsive bids ranging from $3,209,922.07 to $6,487,949.37, with Sterling-AJI Construction Joint Venture marked as non-responsive. The Engineer's Estimate was established at $4,350,000.00. The lowest responsive bid was submitted by Gideon Contracting, LLC at $3,223,036.19.

The project encompasses extensive roadway improvement work including mobilization, survey and staking, quality control, erosion control, clearing and grubbing, excavation, embankment construction, riprap placement, culvert installation, temporary stream diversion, and erosion control products. Line-item pricing is detailed across numerous pay items with unit costs and quantities specified for each contractor. Key construction elements include precast reinforced concrete box culverts (80 linear feet at 16 feet span, 8 feet rise), embankment construction using reinforced soil slopes (3,250 cubic yards), placed riprap (Classes 4 and 6), temporary traffic control, field office establishment, and environmental design work for streambed material (45 cubic yards). Labor costs cover general labor, equipment rental (dump trucks, wheel loaders, hydraulic excavators), and specialized survey services. The report was generated on August 24, 2026, by Contract Specialist Denise Martinez.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID TABULATION REPORT

Project No. : CO ERFO FS SNJUAN 2026-1(1) Project Name: FALL CREEK ROAD

Contractor Responsive? Base Schedule A McKenzie Construction & Site Development, LLC $6,487,949.37

Central Southern Construction Corp. $5,036,150.00

Kovilic Construction Company Inc $4,769,250.00 Medved Global, Inc. $4,250,347.44 Crossfire Aggregate Services, LLC $4,187,018.71 Johnson Construction, Inc. $4,095,180.00 Gideon Contracting, LLC $3,223,036.19 Sterling-AJI Construction Joint Venture No $3,209,922.07

Engineer's Estimate $4,350,000.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

Generated by : Denise Martinez

Project No. : CO ERFO FS SNJUAN 2026-1(1)

Project Name: FALL CREEK ROAD Division: Central Federal Lands

Schedule: A Schedule Type: Base Lead Designer:

Solicitation No. : 6982AF26B000006 Opened at: Lakewood, CO Opened by: Denise Martinez State: CO County: Mineral, Archuleta Federal Land: Rio Grande National

Forest Bid Open Date and Time: 08/13/2026

Contract Awarded to: Award Date:

Contractor Comment Bid Amount Responsive McKenzie Construction & Site Development, LLC, 2301 Calvert St NW, Washington, DC, 20008

$6,487,949.37

Central Southern Construction Corp., 119 Sewald Street, Jacksonville, FL, 32204

$5,036,150.00

Kovilic Construction Company Inc, 3721 N Carnation Street, Franklin Park, IL, 60131

$4,769,250.00

Medved Global, Inc., 246363 Road L, Cortez, CO, 81321

$4,250,347.44

Crossfire Aggregate Services, LLC, 223 Chicken Hawk Lane, Ignacio, CO, 81137

$4,187,018.71

I certify that this Bid Tabulation reflects the offers received for this solicitation

Signed:

Title:

Date:

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

Generated by : Denise Martinez

Contract Specialist

Johnson Construction, Inc., 124 W. 2nd Street, Rifle, CO, 81650

$4,095,180.00

Gideon Contracting, LLC, 2243 East Commerce Street, San Antonio, TX, 78203

$3,223,036.19

Sterling-AJI Construction Joint Venture, 909 East 68th Avenue, Denver, CO, 80229

$3,209,922.07 No

Engineer's Estimate $4,350,000.00

Project No. : CO ERFO FS SNJUAN 2026-1(1) Project Name: FALL CREEK ROAD Schedule: A Schedule Type: Base

Line Item Number

Pay Item Number Description Contractor Quantity Unit Unit Price Amount

A0100 15101-0000 MOBILIZATION McKenzie Construction & Site Development, LLC

$1,904,028.39

Central Southern Construction Corp. $700,000.00

Johnson Construction, Inc. $600,000.00

Kovilic Construction Company Inc $500,000.00

Medved Global, Inc. $391,078.00 Gideon Contracting, LLC $75,450.89

Sterling-AJI Construction Joint Venture

$61,286.40

Crossfire Aggregate Services, LLC $44,636.24

Engineer's Estimate ALL LPSM LPSM $500,290.00

A0120 15201-0000 CONSTRUCTION

SURVEY AND

STAKING

Central Southern Construction Corp. $350,000.00

Sterling-AJI Construction Joint Venture

$82,992.00

McKenzie Construction & Site Development, LLC

$79,934.22

Johnson Construction, Inc. $75,000.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0120 15201-0000 CONSTRUCTION

SURVEY AND

STAKING

Gideon Contracting, LLC $57,764.70

Kovilic Construction Company Inc $50,000.00

Medved Global, Inc. $42,520.00 Crossfire Aggregate Services, LLC $30,745.57

Engineer's Estimate ALL LPSM LPSM $43,750.00

A0140 15301-0000 CONTRACTOR

QUALITY CONTROL

McKenzie Construction & Site Development, LLC

$659,392.04

Central Southern Construction Corp. $350,000.00

Kovilic Construction Company Inc $300,000.00

Gideon Contracting, LLC $105,667.13

Medved Global, Inc. $60,743.00 Johnson Construction, Inc. $50,000.00

Crossfire Aggregate Services, LLC $31,514.34

Sterling-AJI Construction Joint Venture

$10,000.00

Engineer's Estimate ALL LPSM LPSM $100,000.00

A0160 15501-0000 CONSTRUCTION

SCHEDULE

Central Southern Construction Corp. $50,000.00

Johnson Construction, Inc. $20,000.00

Kovilic Construction Company Inc $20,000.00

Medved Global, Inc. $18,223.00 Gideon Contracting, LLC $18,004.98

McKenzie Construction & Site Development, LLC

$14,352.65

Sterling-AJI Construction Joint Venture

$10,000.00

Crossfire Aggregate Services, LLC $4,059.17

Engineer's Estimate ALL LPSM LPSM $16,000.00

A0180 15701-0000 SOIL EROSION

CONTROL

Central Southern Construction Corp. $100,000.00

Johnson Construction, Inc. $65,000.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0180 15701-0000 SOIL EROSION

CONTROL

McKenzie Construction & Site Development, LLC

$55,722.06

Sterling-AJI Construction Joint Venture

$51,072.00

Kovilic Construction Company Inc $50,000.00

Gideon Contracting, LLC $40,388.80

Crossfire Aggregate Services, LLC $33,591.53

Medved Global, Inc. $30,371.00 Engineer's Estimate ALL LPSM LPSM $50,000.00

A0200 15720-0000 STORMWATER

POLLUTION

PREVENTION PLAN

McKenzie Construction & Site Development, LLC

$60,959.59

Central Southern Construction Corp. $50,000.00

Medved Global, Inc. $30,979.00 Sterling-AJI Construction Joint Venture

$25,536.00

Johnson Construction, Inc. $25,000.00

Gideon Contracting, LLC $13,698.69

Crossfire Aggregate Services, LLC $12,851.17

Kovilic Construction Company Inc $10,000.00

Engineer's Estimate ALL LPSM LPSM $5,000.00

A0220 20101-0000 CLEARING AND

GRUBBING

Sterling-AJI Construction Joint Venture

1.500 $44,556.91 $66,835.37

Central Southern Construction Corp. 1.500 $27,500.00 $41,250.00

Kovilic Construction Company Inc 1.500 $25,000.00 $37,500.00

Crossfire Aggregate Services, LLC 1.500 $23,465.80 $35,198.70

Gideon Contracting, LLC 1.500 $16,774.87 $25,162.31

Johnson Construction, Inc. 1.500 $15,000.00 $22,500.00

Medved Global, Inc. 1.500 $14,578.00 $21,867.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0220 20101-0000 CLEARING AND

GRUBBING

McKenzie Construction & Site Development, LLC

1.500 $13,508.37 $20,262.56

Engineer's Estimate 1.500 ACRE $3,300.00 $4,950.00

A0240 20304-1000 REMOVAL OF

STRUCTURES AND

OBSTRUCTIONS

Central Southern Construction Corp. $150,000.00

Kovilic Construction Company Inc $100,000.00

McKenzie Construction & Site Development, LLC

$77,673.17

Sterling-AJI Construction Joint Venture

$52,348.80

Medved Global, Inc. $34,016.00 Johnson Construction, Inc. $30,000.00

Crossfire Aggregate Services, LLC $27,946.94

Gideon Contracting, LLC $26,606.98

Engineer's Estimate ALL LPSM LPSM $41,500.00

A0260 20401-0000 ROADWAY

EXCAVATION

Kovilic Construction Company Inc 330.000 $150.00 $49,500.00

Central Southern Construction Corp. 330.000 $80.00 $26,400.00

Sterling-AJI Construction Joint Venture

330.000 $76.60 $25,278.00

Johnson Construction, Inc. 330.000 $70.00 $23,100.00

McKenzie Construction & Site Development, LLC

330.000 $50.65 $16,714.50

Gideon Contracting, LLC 330.000 $46.27 $15,269.10

Medved Global, Inc. 330.000 $45.00 $14,850.00 Crossfire Aggregate Services, LLC 330.000 $31.31 $10,332.30

Engineer's Estimate 330.000 CUYD $65.00 $21,450.00

A0280 20420-0000 EMBANKMENT

CONSTRUCTION

Johnson Construction, Inc. 1,200.000 $175.00 $210,000.00

Sterling-AJI Construction Joint Venture

1,200.000 $127.68 $153,216.00

Kovilic Construction Company Inc 1,200.000 $125.00 $150,000.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0280 20420-0000 EMBANKMENT

CONSTRUCTION

Central Southern Construction Corp. 1,200.000 $80.00 $96,000.00

Gideon Contracting, LLC 1,200.000 $78.98 $94,776.00

Medved Global, Inc. 1,200.000 $72.50 $87,000.00 McKenzie Construction & Site Development, LLC

1,200.000 $55.72 $66,864.00

Crossfire Aggregate Services, LLC 1,200.000 $50.98 $61,176.00

Engineer's Estimate 1,200.000 CUYD $100.00 $120,000.00

A0300 20420-0000 EMBANKMENT

CONSTRUCTION

(REINFORCED SOIL

SLOPE)

Crossfire Aggregate Services, LLC 3,250.000 $375.65 $1,220,862.50

Sterling-AJI Construction Joint Venture

3,250.000 $331.97 $1,078,902.50

Central Southern Construction Corp. 3,250.000 $200.00 $650,000.00

Johnson Construction, Inc. 3,250.000 $190.00 $617,500.00

Kovilic Construction Company Inc 3,250.000 $190.00 $617,500.00

Medved Global, Inc. 3,250.000 $182.00 $591,500.00 Gideon Contracting, LLC 3,250.000 $166.46 $540,995.00

McKenzie Construction & Site Development, LLC

3,250.000 $104.17 $338,552.50

Engineer's Estimate 3,250.000 CUYD $120.00 $390,000.00

A0320 25101-0400 PLACED RIPRAP,

CLASS 4

Crossfire Aggregate Services, LLC 210.000 $385.11 $80,873.10

McKenzie Construction & Site Development, LLC

210.000 $360.60 $75,726.00

Gideon Contracting, LLC 210.000 $358.86 $75,360.60

Johnson Construction, Inc. 210.000 $305.00 $64,050.00

Kovilic Construction Company Inc 210.000 $300.00 $63,000.00

Medved Global, Inc. 210.000 $243.00 $51,030.00 Central Southern Construction Corp. 210.000 $200.00 $42,000.00

Sterling-AJI Construction Joint Venture

210.000 $71.50 $15,015.00

Engineer's Estimate 210.000 CUYD $300.00 $63,000.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0340 25101-0600 PLACED RIPRAP,

CLASS 6

McKenzie Construction & Site Development, LLC

5,300.000 $391.41 $2,074,473.00

Crossfire Aggregate Services, LLC 5,300.000 $332.13 $1,760,289.00

Medved Global, Inc. 5,300.000 $304.00 $1,611,200.00 Kovilic Construction Company Inc 5,300.000 $300.00 $1,590,000.00

Johnson Construction, Inc. 5,300.000 $265.00 $1,404,500.00

Gideon Contracting, LLC 5,300.000 $231.81 $1,228,593.00

Central Southern Construction Corp. 5,300.000 $200.00 $1,060,000.00

Sterling-AJI Construction Joint Venture

5,300.000 $71.50 $378,950.00

Engineer's Estimate 5,300.000 CUYD $320.00 $1,696,000.00 A0360 27001-0000 GROUT Crossfire Aggregate

Services, LLC 4.000 $10,730.11 $42,920.44

Johnson Construction, Inc. 4.000 $10,000.00 $40,000.00

Sterling-AJI Construction Joint Venture

4.000 $6,224.40 $24,897.60

Central Southern Construction Corp. 4.000 $5,000.00 $20,000.00

Kovilic Construction Company Inc 4.000 $5,000.00 $20,000.00

Gideon Contracting, LLC 4.000 $3,339.72 $13,358.88

Medved Global, Inc. 4.000 $2,885.00 $11,540.00 McKenzie Construction & Site Development, LLC

4.000 $2,163.63 $8,654.52

Engineer's Estimate 4.000 CUYD $20,000.00 $80,000.00

A0380 30202-2000 ROADWAY

AGGREGATE,

METHOD 2

Crossfire Aggregate Services, LLC 500.000 $223.08 $111,540.00

Central Southern Construction Corp. 500.000 $120.00 $60,000.00

Gideon Contracting, LLC 500.000 $111.99 $55,995.00

Johnson Construction, Inc. 500.000 $110.00 $55,000.00

Medved Global, Inc. 500.000 $103.00 $51,500.00 Kovilic Construction Company Inc 500.000 $100.00 $50,000.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0380 30202-2000 ROADWAY

AGGREGATE,

METHOD 2

McKenzie Construction & Site Development, LLC

500.000 $83.45 $41,725.00

Sterling-AJI Construction Joint Venture

500.000 $57.46 $28,730.00

Engineer's Estimate 500.000 TON $120.00 $60,000.00

A0420 60103-0000 CONCRETE,

HEADWALL &

WINGWALLS

(CONCRETE BOX

CULVERT)

Kovilic Construction Company Inc 2.000 $125,000.00 $250,000.00

McKenzie Construction & Site Development, LLC

2.000 $78,531.76 $157,063.52

Central Southern Construction Corp. 2.000 $70,000.00 $140,000.00

Johnson Construction, Inc. 2.000 $57,800.00 $115,600.00

Medved Global, Inc. 2.000 $54,668.00 $109,336.00 Sterling-AJI Construction Joint Venture

2.000 $41,496.00 $82,992.00

Gideon Contracting, LLC 2.000 $39,376.01 $78,752.02

Crossfire Aggregate Services, LLC 2.000 $36,698.12 $73,396.24

Engineer's Estimate 2.000 EACH $70,000.00 $140,000.00

A0440 60220-4760 16 FEET SPAN, 8

FEET RISE PRECAST

REINFORCED

CONCRETE BOX

CULVERT

Medved Global, Inc. 80.000 $10,781.86 $862,548.80 Sterling-AJI Construction Joint Venture

80.000 $10,038.84 $803,107.20

Central Southern Construction Corp. 80.000 $8,000.00 $640,000.00

Kovilic Construction Company Inc 80.000 $6,900.00 $552,000.00

McKenzie Construction & Site Development, LLC

80.000 $6,119.23 $489,538.40

Crossfire Aggregate Services, LLC 80.000 $5,062.18 $404,974.40

Johnson Construction, Inc. 80.000 $3,600.00 $288,000.00

Gideon Contracting, LLC 80.000 $2,010.93 $160,874.40

Engineer's Estimate 80.000 LNFT $10,000.00 $800,000.00

A0460 61702-1500 TERMINAL SYSTEM,

TYPE MGS

TANGENT

Gideon Contracting, LLC 2.000 $25,536.22 $51,072.44

Crossfire Aggregate Services, LLC 2.000 $15,128.15 $30,256.30

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0460 61702-1500 TERMINAL SYSTEM,

TYPE MGS

TANGENT

Central Southern Construction Corp. 2.000 $10,000.00 $20,000.00

McKenzie Construction & Site Development, LLC

2.000 $6,754.18 $13,508.36

Kovilic Construction Company Inc 2.000 $6,250.00 $12,500.00

Johnson Construction, Inc. 2.000 $6,200.00 $12,400.00

Sterling-AJI Construction Joint Venture

2.000 $5,107.20 $10,214.40

Medved Global, Inc. 2.000 $1,214.00 $2,428.00 Engineer's Estimate 2.000 EACH $7,200.00 $14,400.00

A0480 61707-0000 STRUCTURE

TRANSITION

RAILING

Gideon Contracting, LLC 27.000 $1,766.34 $47,691.18

Crossfire Aggregate Services, LLC 27.000 $1,022.08 $27,596.16

Central Southern Construction Corp. 27.000 $500.00 $13,500.00

Medved Global, Inc. 27.000 $304.00 $8,208.00 Sterling-AJI Construction Joint Venture

27.000 $283.73 $7,660.71

McKenzie Construction & Site Development, LLC

27.000 $278.61 $7,522.47

Kovilic Construction Company Inc 27.000 $250.00 $6,750.00

Johnson Construction, Inc. 27.000 $140.00 $3,780.00

Engineer's Estimate 27.000 LNFT $500.00 $13,500.00

A0500 62201-0150 DUMP TRUCK, 7

CUBIC YARD

MINIMUM

CAPACITY

Central Southern Construction Corp. 20.000 $300.00 $6,000.00

McKenzie Construction & Site Development, LLC

20.000 $297.75 $5,955.00

Gideon Contracting, LLC 20.000 $244.91 $4,898.20

Johnson Construction, Inc. 20.000 $200.00 $4,000.00

Crossfire Aggregate Services, LLC 20.000 $198.53 $3,970.60

Medved Global, Inc. 20.000 $197.00 $3,940.00 Sterling-AJI Construction Joint Venture

20.000 $178.75 $3,575.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0500 62201-0150 DUMP TRUCK, 7

CUBIC YARD

MINIMUM

CAPACITY

Kovilic Construction Company Inc 20.000 $150.00 $3,000.00

Engineer's Estimate 20.000 HOUR $190.00 $3,800.00

A0520 62201-0900 WHEEL LOADER, 2

CUBIC YARD

MINIMUM RATED

CAPACITY

McKenzie Construction & Site Development, LLC

20.000 $427.04 $8,540.80

Central Southern Construction Corp. 20.000 $300.00 $6,000.00

Medved Global, Inc. 20.000 $288.00 $5,760.00 Kovilic Construction Company Inc 20.000 $250.00 $5,000.00

Sterling-AJI Construction Joint Venture

20.000 $236.21 $4,724.20

Johnson Construction, Inc. 20.000 $190.00 $3,800.00

Crossfire Aggregate Services, LLC 20.000 $185.65 $3,713.00

Gideon Contracting, LLC 20.000 $168.74 $3,374.80

Engineer's Estimate 20.000 HOUR $235.00 $4,700.00

A0540 62201-3150 HYDRAULIC

EXCAVATOR, 1.0

CUBIC YARD

MINIMUM

CAPACITY WITH

THUMB

ATTACHMENT

McKenzie Construction & Site Development, LLC

20.000 $493.79 $9,875.80

Medved Global, Inc. 20.000 $350.00 $7,000.00 Sterling-AJI Construction Joint Venture

20.000 $325.58 $6,511.60

Central Southern Construction Corp. 20.000 $300.00 $6,000.00

Johnson Construction, Inc. 20.000 $250.00 $5,000.00

Kovilic Construction Company Inc 20.000 $250.00 $5,000.00

Crossfire Aggregate Services, LLC 20.000 $185.65 $3,713.00

Gideon Contracting, LLC 20.000 $168.74 $3,374.80

Engineer's Estimate 20.000 HOUR $300.00 $6,000.00 A0560 62301-0000 GENERAL LABOR McKenzie

Construction & Site Development, LLC

40.000 $171.71 $6,868.40

Kovilic Construction Company Inc 40.000 $150.00 $6,000.00

Central Southern Construction Corp. 40.000 $120.00 $4,800.00

Gideon Contracting, LLC 40.000 $117.64 $4,705.60

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0560 62301-0000 GENERAL LABOR Crossfire Aggregate Services, LLC 40.000 $114.77 $4,590.80

Sterling-AJI Construction Joint Venture

40.000 $95.76 $3,830.40

Medved Global, Inc. 40.000 $85.00 $3,400.00 Johnson Construction, Inc. 40.000 $75.00 $3,000.00

Engineer's Estimate 40.000 HOUR $75.00 $3,000.00

A0580 62302-1100 SPECIAL LABOR,

HIRED SURVEY

SERVICES

McKenzie Construction & Site Development, LLC

10.000 $403.29 $4,032.90

Johnson Construction, Inc. 10.000 $350.00 $3,500.00

Sterling-AJI Construction Joint Venture

10.000 $255.36 $2,553.60

Central Southern Construction Corp. 10.000 $250.00 $2,500.00

Gideon Contracting, LLC 10.000 $211.33 $2,113.30

Medved Global, Inc. 10.000 $200.00 $2,000.00 Crossfire Aggregate Services, LLC 10.000 $190.04 $1,900.40

Kovilic Construction Company Inc 10.000 $150.00 $1,500.00

Engineer's Estimate 10.000 HOUR $225.00 $2,250.00

A0600 62402-0200 PROVIDING AND

PLACING TOPSOIL,

3-INCH DEPTH

Sterling-AJI Construction Joint Venture

0.310 $201,635.64 $62,507.05

Crossfire Aggregate Services, LLC 0.310 $115,866.78 $35,918.70

Johnson Construction, Inc. 0.310 $75,000.00 $23,250.00

Gideon Contracting, LLC 0.310 $64,441.95 $19,977.00

Medved Global, Inc. 0.310 $57,769.00 $17,908.39 Kovilic Construction Company Inc 0.310 $50,000.00 $15,500.00

Central Southern Construction Corp. 0.310 $20,000.00 $6,200.00

McKenzie Construction & Site Development, LLC

0.310 $12,827.23 $3,976.44

Engineer's Estimate 0.310 ACRE $35,000.00 $10,850.00

A0620 62510-2000 SEEDING,

HYDRAULIC

METHOD

Sterling-AJI Construction Joint Venture

0.350 $36,480.00 $12,768.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0620 62510-2000 SEEDING,

HYDRAULIC

METHOD

Kovilic Construction Company Inc 0.350 $25,000.00 $8,750.00

Crossfire Aggregate Services, LLC 0.350 $20,374.25 $7,130.99

Central Southern Construction Corp. 0.350 $20,000.00 $7,000.00

McKenzie Construction & Site Development, LLC

0.350 $17,695.40 $6,193.39

Gideon Contracting, LLC 0.350 $13,994.76 $4,898.17

Johnson Construction, Inc. 0.350 $10,000.00 $3,500.00

Medved Global, Inc. 0.350 $5,206.00 $1,822.10 Engineer's Estimate 0.350 ACRE $2,000.00 $700.00

A0640 62515-2000 MULCHING,

HYDRAULIC

METHOD

Sterling-AJI Construction Joint Venture

0.350 $36,480.00 $12,768.00

Johnson Construction, Inc. 0.350 $30,000.00 $10,500.00

Kovilic Construction Company Inc 0.350 $25,000.00 $8,750.00

Central Southern Construction Corp. 0.350 $20,000.00 $7,000.00

Crossfire Aggregate Services, LLC 0.350 $16,180.97 $5,663.34

McKenzie Construction & Site Development, LLC

0.350 $15,500.29 $5,425.10

Medved Global, Inc. 0.350 $12,149.00 $4,252.15 Gideon Contracting, LLC 0.350 $9,642.48 $3,374.87

Engineer's Estimate 0.350 ACRE $2,600.00 $910.00

A0660 62801-0000 TEMPORARY

STREAM

DIVERSION

Central Southern Construction Corp. $250,000.00

Gideon Contracting, LLC $179,288.38

Johnson Construction, Inc. $150,000.00

Kovilic Construction Company Inc $100,000.00

McKenzie Construction & Site Development, LLC

$75,326.38

Medved Global, Inc. $72,871.00 Sterling-AJI Construction Joint Venture

$61,286.40

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0660 62801-0000 TEMPORARY

STREAM

DIVERSION

Crossfire Aggregate Services, LLC $10,207.82

Engineer's Estimate ALL LPSM LPSM $40,000.00

A0680 62901-1200 ROLLED EROSION

CONTROL

PRODUCT, TYPE 5.A

Gideon Contracting, LLC 650.000 $164.79 $107,113.50

Medved Global, Inc. 650.000 $24.30 $15,795.00 Sterling-AJI Construction Joint Venture

650.000 $23.57 $15,320.50

Crossfire Aggregate Services, LLC 650.000 $22.78 $14,807.00

Central Southern Construction Corp. 650.000 $20.00 $13,000.00

Johnson Construction, Inc. 650.000 $18.00 $11,700.00

Kovilic Construction Company Inc 650.000 $10.00 $6,500.00

McKenzie Construction & Site Development, LLC

650.000 $8.10 $5,265.00

Engineer's Estimate 650.000 SQYD $30.00 $19,500.00

A0700 63308-2000 OBJECT MARKER,

TYPE 2

Gideon Contracting, LLC 4.000 $1,902.01 $7,608.04

Johnson Construction, Inc. 4.000 $1,000.00 $4,000.00

Kovilic Construction Company Inc 4.000 $1,000.00 $4,000.00

Central Southern Construction Corp. 4.000 $500.00 $2,000.00

McKenzie Construction & Site Development, LLC

4.000 $472.79 $1,891.16

Crossfire Aggregate Services, LLC 4.000 $366.85 $1,467.40

Sterling-AJI Construction Joint Venture

4.000 $319.20 $1,276.80

Medved Global, Inc. 4.000 $273.00 $1,092.00 Engineer's Estimate 4.000 EACH $250.00 $1,000.00

A0720 63308-3000 OBJECT MARKER,

TYPE 3

Gideon Contracting, LLC 4.000 $2,254.23 $9,016.92

Johnson Construction, Inc. 4.000 $1,000.00 $4,000.00

Kovilic Construction Company Inc 4.000 $1,000.00 $4,000.00

Central Southern Construction Corp. 4.000 $500.00 $2,000.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0720 63308-3000 OBJECT MARKER,

TYPE 3

McKenzie Construction & Site Development, LLC

4.000 $472.79 $1,891.16

Crossfire Aggregate Services, LLC 4.000 $400.95 $1,603.80

Sterling-AJI Construction Joint Venture

4.000 $319.20 $1,276.80

Medved Global, Inc. 4.000 $273.00 $1,092.00 Engineer's Estimate 4.000 EACH $300.00 $1,200.00

A0740 63501-0000 TEMPORARY

TRAFFIC CONTROL

Central Southern Construction Corp. $100,000.00

Kovilic Construction Company Inc $100,000.00

Johnson Construction, Inc. $75,000.00

Gideon Contracting, LLC $54,701.76

Medved Global, Inc. $42,520.00 McKenzie Construction & Site Development, LLC

$37,090.80

Crossfire Aggregate Services, LLC $30,483.84

Sterling-AJI Construction Joint Venture

$11,491.20

Engineer's Estimate ALL LPSM LPSM $35,000.00 A0760 63701-0000 FIELD OFFICE McKenzie

Construction & Site Development, LLC

1.000 $137,373.34 $137,373.34

Johnson Construction, Inc. 1.000 $50,000.00 $50,000.00

Kovilic Construction Company Inc 1.000 $50,000.00 $50,000.00

Central Southern Construction Corp. 1.000 $42,000.00 $42,000.00

Gideon Contracting, LLC 1.000 $32,535.61 $32,535.61

Sterling-AJI Construction Joint Venture

1.000 $31,000.00 $31,000.00

Medved Global, Inc. 1.000 $24,297.00 $24,297.00 Crossfire Aggregate Services, LLC 1.000 $5,629.57 $5,629.57

Engineer's Estimate 1.000 EACH $50,000.00 $50,000.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0780 64704-1000 ENVIRONMENTAL

DESIGN,

STREAMBED

MATERIAL

Gideon Contracting, LLC 45.000 $1,346.07 $60,573.15

Central Southern Construction Corp. 45.000 $500.00 $22,500.00

Johnson Construction, Inc. 45.000 $500.00 $22,500.00

Kovilic Construction Company Inc 45.000 $500.00 $22,500.00

Medved Global, Inc. 45.000 $348.00 $15,660.00 McKenzie Construction & Site Development, LLC

45.000 $346.15 $15,576.75

Crossfire Aggregate Services, LLC 45.000 $254.63 $11,458.35

Sterling-AJI Construction Joint Venture

45.000 $222.19 $9,998.55

Engineer's Estimate 45.000 CUYD $250.00 $11,250.00

Report Generated on 08/24/2026 9:00 AM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]