BidTabulationReport.pdf

PDF 743 KB Posted

Attached to
NV FLAP NYE 10(1) Bob Ruud Mem Hwy & Bell Vista Ave
Solicitation number
6982AF26B000003
Issued by

About this file

Bid Tabulation Report Summary

This is a Bid Tabulation Report for Federal Lands Highway Project NV FLAP NYE 10(1), titled "Bob Ruud Memorial Highway & Bell Vista Avenue," located in Nye County, Nevada on Ash Meadows National Wildlife Refuge. The solicitation number is 6982AF26B000003, opened on June 10, 2026 in Lakewood, Colorado. The project falls under the Central Federal Lands Division and includes two base schedules (A and B) with multiple line items spanning site preparation, construction, drainage, paving, concrete work, landscaping, and traffic control.

Schedule A base bids ranged from $21,005,166.00 (Amrize Southwest Inc, lowest) to $34,282,797.00 (Steve Manning Construction Inc, highest), with eight contractors responding. Schedule B base bids ranged from $26,528,454.90 (Amrize Southwest Inc, lowest) to $44,852,360.00 (Steve Manning Construction Inc, highest), also with eight contractors. The Engineer's Estimate for Schedule A was $25,484,435.00 and for Schedule B was $32,897,260.00. Major work categories include mobilization, survey and staking, clearing and grubbing, embankment construction, asphalt concrete pavement (72,000-87,000 tons depending on schedule), pipe culverts in various sizes (12-inch through 72-inch), concrete work, reinforcing steel, erosion control, dust control, temporary traffic control, and signage systems. Unit prices and line-item amounts are provided for each contractor across all pay items. The report was certified by Contract Specialist Denise Annette Martinez on June 23, 2026.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID TABULATION REPORT

Project No. : NV FLAP NYE 10(1) Project Name: BOB RUUD MEM HWY & BELL VISTA AVE

Contractor Responsive? Base Schedule A Steve Manning Construction Inc $34,282,797.00 McKenzie Construction & Site Development, LLC $33,755,162.20

AE West LLC $33,517,093.54 W. W. Clyde & Co. $24,282,940.40 Road and Highway Builders $23,333,333.00 Hat Creek Construction & Materials, Inc. $23,445,989.00

Las Vegas Paving Corporation $21,539,000.00 Amrize Southwest Inc $21,005,166.00 Engineer's Estimate $25,484,435.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

Generated by : Denise Martinez

Contractor Responsive? Base Schedule B Steve Manning Construction Inc $44,852,360.00 McKenzie Construction & Site Development, LLC $43,992,094.96

AE West LLC $41,527,409.68 W. W. Clyde & Co. $31,429,324.60 Road and Highway Builders $30,555,555.00 Hat Creek Construction & Materials, Inc. $29,994,499.00

Las Vegas Paving Corporation $27,591,000.00 Amrize Southwest Inc $26,528,454.90 Engineer's Estimate $32,897,260.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

Project No. : NV FLAP NYE 10(1) Project Name: BOB RUUD MEM

HWY & BELL VISTA

AVE

Division: Central Federal Lands

Schedule: A Schedule Type: Base Lead Designer:

Solicitation No. : 6982AF26B000003 Opened at: Lakewood, CO Opened by: Ryan Phillips State: NV County: Nye Federal Land: Ash Meadows NWR Bid Open Date and Time: 06/10/2026

Contract Awarded to: Award Date:

Contractor Comment Bid Amount Responsive Steve Manning Construction Inc, 5211 Churn Creek Road, Redding, CA, 96002

$34,282,797.00

McKenzie Construction & Site Development, LLC, 2301 Calvert St NW, Washington, DC, 20008

$33,755,162.20

AE West LLC, 3112 Spring Hollow Court, Ann Arbor, MI, 48105

$33,517,093.54

W. W. Clyde & Co., 869 N 1500 W, Orem, UT, 84057

$24,282,940.40

Hat Creek Construction & Materials, Inc., 24339 Highway 89 N, Burney, CA, 96013

$23,445,989.00

Road and Highway Builders $23,333,333.00

I certify that this Bid Tabulation reflects the offers received for this solicitation

Signed:

Title:

Date:

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

Generated by : Denise Martinez

Contract Specialist

Las Vegas Paving Corporation, 4420 S. Decatur Blvd, Las Vegas, NV, 89103

$21,539,000.00

Amrize Southwest Inc, 4675 WEST TECO #140, LAS VEGAS, NV, 89118

$21,005,166.00

Engineer's Estimate $25,484,435.00

Project No. : NV FLAP NYE 10(1) Project Name: BOB RUUD MEM HWY & BELL VISTA

AVE

Schedule: A Schedule Type: Base

Line Item Number

Pay Item Number Description Contractor Quantity Unit Unit Price Amount

A0010 15101-0000 MOBILIZATION McKenzie Construction & Site Development, LLC

$5,581,151.70

Steve Manning Construction Inc $3,200,000.00

W. W. Clyde & Co. $2,425,689.00 Road and Highway Builders $2,309,913.00

Hat Creek Construction & Materials, Inc.

$2,300,000.00

AE West LLC $2,082,880.02 Las Vegas Paving Corporation $942,941.00

Amrize Southwest Inc $698,700.00 Engineer's Estimate ALL LPSM LPSM $2,310,529.80

A0020 15215-1000 SURVEY AND

STAKING,

APPROACH ROAD

Steve Manning Construction Inc 32.000 $3,000.00 $96,000.00

Las Vegas Paving Corporation 32.000 $2,800.00 $89,600.00

W. W. Clyde & Co. 32.000 $1,818.00 $58,176.00 AE West LLC 32.000 $1,725.00 $55,200.00 McKenzie Construction & Site Development, LLC

32.000 $1,621.00 $51,872.00

Road and Highway Builders 32.000 $1,000.00 $32,000.00

Amrize Southwest Inc 32.000 $805.80 $25,785.60 Hat Creek Construction & Materials, Inc.

32.000 $400.00 $12,800.00

Engineer's Estimate 32.000 EACH $710.00 $22,720.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0030 15215-3000 SURVEY AND

STAKING,

DRAINAGE

STRUCTURE

Las Vegas Paving Corporation 52.000 $2,800.00 $145,600.00

AE West LLC 52.000 $2,300.00 $119,600.00 McKenzie Construction & Site Development, LLC

52.000 $2,212.00 $115,024.00

Steve Manning Construction Inc 52.000 $1,800.00 $93,600.00

Hat Creek Construction & Materials, Inc.

52.000 $1,200.00 $62,400.00

Road and Highway Builders 52.000 $1,000.00 $52,000.00

Amrize Southwest Inc 52.000 $785.70 $40,856.40 W. W. Clyde & Co. 52.000 $448.00 $23,296.00 Engineer's Estimate 52.000 EACH $1,300.00 $67,600.00

A0040 15225-0000 SLOPE, REFERENCE,

AND CLEARING

AND GRUBBING

CONTROL

Amrize Southwest Inc 15.500 $22,997.00 $356,453.50 Steve Manning Construction Inc 15.500 $16,000.00 $248,000.00

Las Vegas Paving Corporation 15.500 $15,100.00 $234,050.00

McKenzie Construction & Site Development, LLC

15.500 $7,997.00 $123,953.50

Hat Creek Construction & Materials, Inc.

15.500 $5,400.00 $83,700.00

W. W. Clyde & Co. 15.500 $4,505.00 $69,827.50 AE West LLC 15.500 $2,300.00 $35,650.00 Road and Highway Builders 15.500 $1,000.00 $15,500.00

Engineer's Estimate 15.500 MILE $8,400.00 $130,200.00

A0050 15236-2000 SURVEY CONTROL,

GRADE FINISHING

McKenzie Construction & Site Development, LLC

31.000 $29,533.00 $915,523.00

Las Vegas Paving Corporation 31.000 $14,500.00 $449,500.00

Amrize Southwest Inc 31.000 $10,377.00 $321,687.00 W. W. Clyde & Co. 31.000 $7,508.00 $232,748.00 Steve Manning Construction Inc 31.000 $6,000.00 $186,000.00

Hat Creek Construction & Materials, Inc.

31.000 $4,200.00 $130,200.00

AE West LLC 31.000 $3,680.00 $114,080.00 Road and Highway Builders 31.000 $1,000.00 $31,000.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0050 15236-2000 SURVEY CONTROL,

GRADE FINISHING Engineer's Estimate 31.000 MILE $5,800.00 $179,800.00

A0060 15301-0000 CONTRACTOR

QUALITY CONTROL

Road and Highway Builders $1,300,000.00

Hat Creek Construction & Materials, Inc.

$894,091.00

Amrize Southwest Inc $705,470.00 Las Vegas Paving Corporation $570,000.00

Steve Manning Construction Inc $506,000.00

W. W. Clyde & Co. $436,035.00 AE West LLC $412,297.61 McKenzie Construction & Site Development, LLC

$267,800.00

Engineer's Estimate ALL LPSM LPSM $350,000.00

A0070 15401-0000 CONTRACTOR

TESTING

Road and Highway Builders $1,200,000.00

Hat Creek Construction & Materials, Inc.

$1,100,500.00

W. W. Clyde & Co. $823,216.00 McKenzie Construction & Site Development, LLC

$770,852.00

Steve Manning Construction Inc $700,000.00

AE West LLC $509,450.44 Las Vegas Paving Corporation $42,000.00

Amrize Southwest Inc $30,935.00 Engineer's Estimate ALL LPSM LPSM $370,000.00

A0080 15501-0000 CONSTRUCTION

SCHEDULE

W. W. Clyde & Co. $163,723.00 Road and Highway Builders $150,000.00

Hat Creek Construction & Materials, Inc.

$50,000.00

Steve Manning Construction Inc $40,000.00

McKenzie Construction & Site Development, LLC

$25,750.00

Amrize Southwest Inc $21,199.00 AE West LLC $18,768.02

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0080 15501-0000 CONSTRUCTION

SCHEDULE

Las Vegas Paving Corporation $1.00

Engineer's Estimate ALL LPSM LPSM $100,000.00

A0090 15701-0000 SOIL EROSION

CONTROL

McKenzie Construction & Site Development, LLC

$1,348,723.00

AE West LLC $923,183.46 Road and Highway Builders $400,000.00

W. W. Clyde & Co. $386,797.00 Steve Manning Construction Inc $280,000.00

Amrize Southwest Inc $276,695.00 Hat Creek Construction & Materials, Inc.

$70,000.00

Las Vegas Paving Corporation $54,000.00

Engineer's Estimate ALL LPSM LPSM $400,000.00

A0100 15720-0000 STORM WATER

POLLUTION

PREVENTION PLAN

Hat Creek Construction & Materials, Inc.

$50,000.00

AE West LLC $34,500.00 Steve Manning Construction Inc $30,000.00

W. W. Clyde & Co. $29,264.00 Amrize Southwest Inc $25,981.00 McKenzie Construction & Site Development, LLC

$25,750.00

Las Vegas Paving Corporation $18,500.00

Road and Highway Builders $5,000.00

Engineer's Estimate ALL LPSM LPSM $10,000.00

A0110 15802-0000 WATERING FOR

DUST CONTROL

AE West LLC $909,654.79 Road and Highway Builders $700,000.00

McKenzie Construction & Site Development, LLC

$529,715.00

Steve Manning Construction Inc $300,000.00

Amrize Southwest Inc $256,470.00 Hat Creek Construction & Materials, Inc.

$200,000.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0110 15802-0000 WATERING FOR

DUST CONTROL

Las Vegas Paving Corporation $140,000.00

W. W. Clyde & Co. $51,085.00 Engineer's Estimate ALL LPSM LPSM $350,000.00

A0120 20101-0000 CLEARING AND

GRUBBING

Steve Manning Construction Inc 46.000 $14,000.00 $644,000.00

Road and Highway Builders 46.000 $4,000.00 $184,000.00

W. W. Clyde & Co. 46.000 $3,294.00 $151,524.00 McKenzie Construction & Site Development, LLC

46.000 $2,575.00 $118,450.00

Hat Creek Construction & Materials, Inc.

46.000 $2,500.00 $115,000.00

Las Vegas Paving Corporation 46.000 $2,500.00 $115,000.00

Amrize Southwest Inc 46.000 $2,129.00 $97,934.00 AE West LLC 46.000 $880.59 $40,507.14 Engineer's Estimate 46.000 ACRE $4,400.00 $202,400.00

A0130 20301-0700 REMOVAL OF

DELINEATOR

McKenzie Construction & Site Development, LLC

146.000 $72.00 $10,512.00

Steve Manning Construction Inc 146.000 $72.00 $10,512.00

AE West LLC 146.000 $28.75 $4,197.50 Amrize Southwest Inc 146.000 $22.50 $3,285.00 Las Vegas Paving Corporation 146.000 $22.00 $3,212.00

Road and Highway Builders 146.000 $20.00 $2,920.00

Hat Creek Construction & Materials, Inc.

146.000 $18.00 $2,628.00

W. W. Clyde & Co. 146.000 $6.65 $970.90 Engineer's Estimate 146.000 EACH $16.20 $2,365.20

A0140 20301-2400 REMOVAL OF SIGN Road and Highway Builders 54.000 $400.00 $21,600.00

Steve Manning Construction Inc 54.000 $110.00 $5,940.00

McKenzie Construction & Site Development, LLC

54.000 $103.00 $5,562.00

AE West LLC 54.000 $86.25 $4,657.50 Amrize Southwest Inc 54.000 $61.80 $3,337.20 Las Vegas Paving Corporation 54.000 $60.00 $3,240.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0140 20301-2400 REMOVAL OF SIGN W. W. Clyde & Co. 54.000 $55.00 $2,970.00 Hat Creek Construction & Materials, Inc.

54.000 $40.00 $2,160.00

Engineer's Estimate 54.000 EACH $160.00 $8,640.00

A0150 20301-2400 REMOVAL OF SIGN

(POST ONLY)

W. W. Clyde & Co. 44.000 $414.00 $18,216.00 Road and Highway Builders 44.000 $400.00 $17,600.00

Steve Manning Construction Inc 44.000 $110.00 $4,840.00

McKenzie Construction & Site Development, LLC

44.000 $103.00 $4,532.00

AE West LLC 44.000 $86.25 $3,795.00 Amrize Southwest Inc 44.000 $61.80 $2,719.20 Las Vegas Paving Corporation 44.000 $60.00 $2,640.00

Hat Creek Construction & Materials, Inc.

44.000 $50.00 $2,200.00

Engineer's Estimate 44.000 EACH $100.00 $4,400.00

A0160 20302-2100 REMOVAL OF PIPE

CULVERT

Steve Manning Construction Inc 1,320.000 $180.00 $237,600.00

AE West LLC 1,320.000 $131.60 $173,712.00 McKenzie Construction & Site Development, LLC

1,320.000 $103.00 $135,960.00

Road and Highway Builders 1,320.000 $90.00 $118,800.00

Amrize Southwest Inc 1,320.000 $56.20 $74,184.00 W. W. Clyde & Co. 1,320.000 $55.00 $72,600.00 Las Vegas Paving Corporation 1,320.000 $54.00 $71,280.00

Hat Creek Construction & Materials, Inc.

1,320.000 $22.00 $29,040.00

Engineer's Estimate 1,320.000 LNFT $70.00 $92,400.00 A0170 20402-0000 SUBEXCAVATION Amrize Southwest Inc 500.000 $454.50 $227,250.00

Steve Manning Construction Inc 500.000 $290.00 $145,000.00

Las Vegas Paving Corporation 500.000 $176.00 $88,000.00

Hat Creek Construction & Materials, Inc.

500.000 $165.00 $82,500.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0170 20402-0000 SUBEXCAVATION McKenzie Construction & Site Development, LLC

500.000 $133.00 $66,500.00

AE West LLC 500.000 $106.06 $53,030.00 W. W. Clyde & Co. 500.000 $103.00 $51,500.00 Road and Highway Builders 500.000 $30.00 $15,000.00

Engineer's Estimate 500.000 CUYD $168.00 $84,000.00

A0180 20420-0000 EMBANKMENT

CONSTRUCTION

Steve Manning Construction Inc 10,000.000 $150.00 $1,500,000.00

Las Vegas Paving Corporation 10,000.000 $134.00 $1,340,000.00

Road and Highway Builders 10,000.000 $110.00 $1,100,000.00

Amrize Southwest Inc 10,000.000 $107.70 $1,077,000.00 McKenzie Construction & Site Development, LLC

10,000.000 $88.00 $880,000.00

Hat Creek Construction & Materials, Inc.

10,000.000 $85.00 $850,000.00

AE West LLC 10,000.000 $61.57 $615,700.00 W. W. Clyde & Co. 10,000.000 $20.00 $200,000.00 Engineer's Estimate 10,000.000 CUYD $60.00 $600,000.00

A0190 21101-1000 ROADWAY

OBLITERATION,

METHOD 1

McKenzie Construction & Site Development, LLC

800.000 $36.00 $28,800.00

Hat Creek Construction & Materials, Inc.

800.000 $20.00 $16,000.00

Steve Manning Construction Inc 800.000 $20.00 $16,000.00

Las Vegas Paving Corporation 800.000 $15.00 $12,000.00

Road and Highway Builders 800.000 $10.00 $8,000.00

Amrize Southwest Inc 800.000 $9.80 $7,840.00 AE West LLC 800.000 $6.88 $5,504.00 W. W. Clyde & Co. 800.000 $6.85 $5,480.00 Engineer's Estimate 800.000 SQYD $19.00 $15,200.00

A0200 25101-0200 PLACED RIPRAP,

METHOD A, CLASS

2 (FILLED AND

TOPPED)

Road and Highway Builders 350.000 $500.00 $175,000.00

Las Vegas Paving Corporation 350.000 $447.00 $156,450.00

W. W. Clyde & Co. 350.000 $398.00 $139,300.00 AE West LLC 350.000 $346.94 $121,429.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0200 25101-0200 PLACED RIPRAP,

METHOD A, CLASS

2 (FILLED AND

TOPPED)

McKenzie Construction & Site Development, LLC

350.000 $319.00 $111,650.00

Steve Manning Construction Inc 350.000 $292.00 $102,200.00

Amrize Southwest Inc 350.000 $290.50 $101,675.00 Hat Creek Construction & Materials, Inc.

350.000 $250.00 $87,500.00

Engineer's Estimate 350.000 CUYD $340.00 $119,000.00

A0210 25101-0300 PLACED RIPRAP,

METHOD A, CLASS

3 (FILLED AND

TOPPED)

Road and Highway Builders 300.000 $500.00 $150,000.00

W. W. Clyde & Co. 300.000 $381.00 $114,300.00 McKenzie Construction & Site Development, LLC

300.000 $319.00 $95,700.00

Steve Manning Construction Inc 300.000 $310.00 $93,000.00

Amrize Southwest Inc 300.000 $285.60 $85,680.00 Las Vegas Paving Corporation 300.000 $270.00 $81,000.00

Hat Creek Construction & Materials, Inc.

300.000 $250.00 $75,000.00

AE West LLC 300.000 $196.75 $59,025.00 Engineer's Estimate 300.000 CUYD $310.00 $93,000.00

A0220 30101-0000 AGGREGATE BASE W. W. Clyde & Co. 27,500.000 $59.00 $1,622,500.00 McKenzie Construction & Site Development, LLC

27,500.000 $56.00 $1,540,000.00

Steve Manning Construction Inc 27,500.000 $42.00 $1,155,000.00

Las Vegas Paving Corporation 27,500.000 $36.60 $1,006,500.00

Hat Creek Construction & Materials, Inc.

27,500.000 $32.00 $880,000.00

AE West LLC 27,500.000 $29.55 $812,625.00 Amrize Southwest Inc 27,500.000 $28.90 $794,750.00 Road and Highway Builders 27,500.000 $20.00 $550,000.00

Engineer's Estimate 27,500.000 TON $75.00 $2,062,500.00

A0240 30401-5200 FULL DEPTH

RECLAMATION,

METHOD 2, 4-INCH

DEPTH

Steve Manning Construction Inc 11.000 $220,000.00 $2,420,000.00

McKenzie Construction & Site Development, LLC

11.000 $107,120.00 $1,178,320.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0240 30401-5200 FULL DEPTH

RECLAMATION,

METHOD 2, 4-INCH

DEPTH

Hat Creek Construction & Materials, Inc.

11.000 $105,000.00 $1,155,000.00

AE West LLC 11.000 $100,771.60 $1,108,487.60 Amrize Southwest Inc 11.000 $50,868.00 $559,548.00 W. W. Clyde & Co. 11.000 $37,659.00 $414,249.00 Road and Highway Builders 11.000 $30,000.00 $330,000.00

Las Vegas Paving Corporation 11.000 $18,500.00 $203,500.00

Engineer's Estimate 11.000 MILE $90,000.00 $990,000.00

A0250 30401-5500 FULL DEPTH

RECLAMATION,

METHOD 2, 8-INCH

DEPTH

Steve Manning Construction Inc 5.000 $240,000.00 $1,200,000.00

McKenzie Construction & Site Development, LLC

5.000 $215,270.00 $1,076,350.00

Hat Creek Construction & Materials, Inc.

5.000 $105,000.00 $525,000.00

AE West LLC 5.000 $86,524.66 $432,623.30 Road and Highway Builders 5.000 $60,000.00 $300,000.00

Amrize Southwest Inc 5.000 $56,882.00 $284,410.00 W. W. Clyde & Co. 5.000 $39,838.00 $199,190.00 Las Vegas Paving Corporation 5.000 $20,300.00 $101,500.00

Engineer's Estimate 5.000 MILE $130,000.00 $650,000.00

A0260 40101-5600 ASPHALT

CONCRETE

PAVEMENT,

GYRATORY MIX,

1/2-INCH OR 3/4-

INCH NOMINAL

MAXIMUM SIZE

AGGREGATE, 0.3

TO <3 MILLION

ESAL

AE West LLC 72,000.000 $208.17 $14,988,240.00 Steve Manning Construction Inc 72,000.000 $185.00 $13,320,000.00

McKenzie Construction & Site Development, LLC

72,000.000 $180.00 $12,960,000.00

W. W. Clyde & Co. 72,000.000 $141.13 $10,161,360.00 Amrize Southwest Inc 72,000.000 $135.80 $9,777,600.00 Hat Creek Construction & Materials, Inc.

72,000.000 $125.00 $9,000,000.00

Las Vegas Paving Corporation 72,000.000 $117.50 $8,460,000.00

Road and Highway Builders 72,000.000 $113.00 $8,136,000.00

Engineer's Estimate 72,000.000 TON $160.00 $11,520,000.00

A0280 40105-3000 ANTISTRIP

ADDITIVE, TYPE 3

Las Vegas Paving Corporation 720.000 $532.00 $383,040.00

AE West LLC 720.000 $517.50 $372,600.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0280 40105-3000 ANTISTRIP

ADDITIVE, TYPE 3

Steve Manning Construction Inc 720.000 $500.00 $360,000.00

McKenzie Construction & Site Development, LLC

720.000 $463.00 $333,360.00

Road and Highway Builders 720.000 $400.00 $288,000.00

W. W. Clyde & Co. 720.000 $356.00 $256,320.00 Amrize Southwest Inc 720.000 $1.10 $792.00 Hat Creek Construction & Materials, Inc.

720.000 $1.00 $720.00

Engineer's Estimate 720.000 TON $300.00 $216,000.00 A0300 40601-0000 FOG SEAL Steve Manning

Construction Inc 150.000 $1,500.00 $225,000.00

AE West LLC 150.000 $1,035.00 $155,250.00 W. W. Clyde & Co. 150.000 $1,035.00 $155,250.00 McKenzie Construction & Site Development, LLC

150.000 $1,004.00 $150,600.00

Amrize Southwest Inc 150.000 $809.40 $121,410.00 Hat Creek Construction & Materials, Inc.

150.000 $750.00 $112,500.00

Las Vegas Paving Corporation 150.000 $688.00 $103,200.00

Road and Highway Builders 150.000 $400.00 $60,000.00

Engineer's Estimate 150.000 TON $795.00 $119,250.00

A0310 41101-1000 PRIME COAT,

METHOD 1

Steve Manning Construction Inc 500.000 $1,500.00 $750,000.00

W. W. Clyde & Co. 500.000 $1,175.00 $587,500.00 AE West LLC 500.000 $948.75 $474,375.00 McKenzie Construction & Site Development, LLC

500.000 $916.00 $458,000.00

Amrize Southwest Inc 500.000 $611.00 $305,500.00 Las Vegas Paving Corporation 500.000 $552.00 $276,000.00

Hat Creek Construction & Materials, Inc.

500.000 $500.00 $250,000.00

Road and Highway Builders 500.000 $400.00 $200,000.00

Engineer's Estimate 500.000 TON $1,100.00 $550,000.00 A0320 41105-0000 BLOTTER Road and Highway

Builders 510.000 $400.00 $204,000.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0320 41105-0000 BLOTTER W. W. Clyde & Co. 510.000 $260.00 $132,600.00 AE West LLC 510.000 $142.60 $72,726.00 McKenzie Construction & Site Development, LLC

510.000 $127.00 $64,770.00

Steve Manning Construction Inc 510.000 $80.00 $40,800.00

Las Vegas Paving Corporation 510.000 $72.00 $36,720.00

Amrize Southwest Inc 510.000 $64.30 $32,793.00 Hat Creek Construction & Materials, Inc.

510.000 $50.00 $25,500.00

Engineer's Estimate 510.000 TON $80.00 $40,800.00 A0330 41201-0000 TACK COAT Steve Manning

Construction Inc 150.000 $1,500.00 $225,000.00

W. W. Clyde & Co. 150.000 $1,320.00 $198,000.00 AE West LLC 150.000 $822.25 $123,337.50 Amrize Southwest Inc 150.000 $809.40 $121,410.00 McKenzie Construction & Site Development, LLC

150.000 $787.00 $118,050.00

Hat Creek Construction & Materials, Inc.

150.000 $750.00 $112,500.00

Las Vegas Paving Corporation 150.000 $688.00 $103,200.00

Road and Highway Builders 150.000 $400.00 $60,000.00

Engineer's Estimate 150.000 TON $940.00 $141,000.00

A0340 50101-0600 MINOR CONCRETE

PAVEMENT,

REINFORCED, 6-

INCH DEPTH

McKenzie Construction & Site Development, LLC

1,620.000 $360.00 $583,200.00

Hat Creek Construction & Materials, Inc.

1,620.000 $250.00 $405,000.00

Amrize Southwest Inc 1,620.000 $244.40 $395,928.00 Las Vegas Paving Corporation 1,620.000 $235.00 $380,700.00

Steve Manning Construction Inc 1,620.000 $201.00 $325,620.00

W. W. Clyde & Co. 1,620.000 $181.00 $293,220.00 AE West LLC 1,620.000 $115.69 $187,417.80 Road and Highway Builders 1,620.000 $80.00 $129,600.00

Engineer's Estimate 1,620.000 SQYD $380.00 $615,600.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0350 55401-1000 REINFORCING

STEEL

McKenzie Construction & Site Development, LLC

3,500.000 $12.00 $42,000.00

Road and Highway Builders 3,500.000 $8.00 $28,000.00

Amrize Southwest Inc 3,500.000 $5.55 $19,425.00 Las Vegas Paving Corporation 3,500.000 $5.40 $18,900.00

Hat Creek Construction & Materials, Inc.

3,500.000 $5.00 $17,500.00

Steve Manning Construction Inc 3,500.000 $4.00 $14,000.00

AE West LLC 3,500.000 $3.73 $13,055.00 W. W. Clyde & Co. 3,500.000 $2.50 $8,750.00 Engineer's Estimate 3,500.000 LB $5.25 $18,375.00

A0360 60101-0000 CONCRETE McKenzie Construction & Site Development, LLC

45.000 $3,090.00 $139,050.00

Hat Creek Construction & Materials, Inc.

45.000 $2,500.00 $112,500.00

Steve Manning Construction Inc 45.000 $2,500.00 $112,500.00

Amrize Southwest Inc 45.000 $1,557.00 $70,065.00 Las Vegas Paving Corporation 45.000 $1,450.00 $65,250.00

W. W. Clyde & Co. 45.000 $1,319.00 $59,355.00 Road and Highway Builders 45.000 $1,000.00 $45,000.00

AE West LLC 45.000 $919.18 $41,363.10 Engineer's Estimate 45.000 CUYD $2,100.00 $94,500.00

A0370 60103-0140 CONCRETE,

HEADWALL FOR 24

-INCH PIPE

CULVERT

Amrize Southwest Inc 2.000 $32,570.00 $65,140.00 W. W. Clyde & Co. 2.000 $32,049.00 $64,098.00 Las Vegas Paving Corporation 2.000 $31,500.00 $63,000.00

Road and Highway Builders 2.000 $20,000.00 $40,000.00

Hat Creek Construction & Materials, Inc.

2.000 $15,000.00 $30,000.00

AE West LLC 2.000 $13,954.65 $27,909.30 Steve Manning Construction Inc 2.000 $12,000.00 $24,000.00

McKenzie Construction & Site Development, LLC

2.000 $2,476.00 $4,952.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0370 60103-0140 CONCRETE,

HEADWALL FOR 24

-INCH PIPE

CULVERT

Engineer's Estimate 2.000 EACH $5,000.00 $10,000.00

A0380 60103-0180 CONCRETE,

HEADWALL FOR 36

-INCH PIPE

CULVERT

Amrize Southwest Inc 2.000 $35,377.00 $70,754.00 W. W. Clyde & Co. 2.000 $34,812.00 $69,624.00 Las Vegas Paving Corporation 2.000 $34,000.00 $68,000.00

Road and Highway Builders 2.000 $30,000.00 $60,000.00

Hat Creek Construction & Materials, Inc.

2.000 $18,000.00 $36,000.00

AE West LLC 2.000 $17,591.43 $35,182.86 Steve Manning Construction Inc 2.000 $15,000.00 $30,000.00

McKenzie Construction & Site Development, LLC

2.000 $8,946.00 $17,892.00

Engineer's Estimate 2.000 EACH $10,000.00 $20,000.00

A0390 60103-0220 CONCRETE,

HEADWALL FOR 48

-INCH PIPE

CULVERT

Amrize Southwest Inc 8.000 $43,239.00 $345,912.00 W. W. Clyde & Co. 8.000 $42,548.00 $340,384.00 Las Vegas Paving Corporation 8.000 $42,000.00 $336,000.00

Road and Highway Builders 8.000 $35,000.00 $280,000.00

Steve Manning Construction Inc 8.000 $35,000.00 $280,000.00

Hat Creek Construction & Materials, Inc.

8.000 $32,000.00 $256,000.00

AE West LLC 8.000 $25,176.06 $201,408.48 McKenzie Construction & Site Development, LLC

8.000 $18,462.00 $147,696.00

Engineer's Estimate 8.000 EACH $25,000.00 $200,000.00

A0400 60103-0640 CONCRETE,

HEADWALL FOR

DOUBLE 30-INCH

PIPE CULVERT

Steve Manning Construction Inc 2.000 $50,000.00 $100,000.00

Amrize Southwest Inc 2.000 $41,779.00 $83,558.00 W. W. Clyde & Co. 2.000 $41,111.00 $82,222.00 Las Vegas Paving Corporation 2.000 $40,000.00 $80,000.00

Road and Highway Builders 2.000 $40,000.00 $80,000.00

AE West LLC 2.000 $28,103.70 $56,207.40

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0400 60103-0640 CONCRETE,

HEADWALL FOR

DOUBLE 30-INCH

PIPE CULVERT

McKenzie Construction & Site Development, LLC

2.000 $18,462.00 $36,924.00

Hat Creek Construction & Materials, Inc.

2.000 $18,000.00 $36,000.00

Engineer's Estimate 2.000 EACH $13,000.00 $26,000.00

A0410 60201-0400 12-INCH PIPE

CULVERT

Road and Highway Builders 185.000 $500.00 $92,500.00

Steve Manning Construction Inc 185.000 $250.00 $46,250.00

Hat Creek Construction & Materials, Inc.

185.000 $230.00 $42,550.00

AE West LLC 185.000 $227.40 $42,069.00 Amrize Southwest Inc 185.000 $157.20 $29,082.00 W. W. Clyde & Co. 185.000 $155.00 $28,675.00 Las Vegas Paving Corporation 185.000 $152.00 $28,120.00

McKenzie Construction & Site Development, LLC

185.000 $115.00 $21,275.00

Engineer's Estimate 185.000 LNFT $220.00 $40,700.00

A0420 60201-0600 18-INCH PIPE

CULVERT

Road and Highway Builders 280.000 $600.00 $168,000.00

Steve Manning Construction Inc 280.000 $300.00 $84,000.00

AE West LLC 280.000 $235.41 $65,914.80 Hat Creek Construction & Materials, Inc.

280.000 $230.00 $64,400.00

Amrize Southwest Inc 280.000 $185.30 $51,884.00 W. W. Clyde & Co. 280.000 $182.00 $50,960.00 Las Vegas Paving Corporation 280.000 $179.00 $50,120.00

McKenzie Construction & Site Development, LLC

280.000 $123.00 $34,440.00

Engineer's Estimate 280.000 LNFT $190.00 $53,200.00

A0430 60201-0800 24-INCH PIPE

CULVERT

Road and Highway Builders 1,210.000 $700.00 $847,000.00

Steve Manning Construction Inc 1,210.000 $350.00 $423,500.00

AE West LLC 1,210.000 $333.10 $403,051.00 Hat Creek Construction & Materials, Inc.

1,210.000 $230.00 $278,300.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0430 60201-0800 24-INCH PIPE

CULVERT

Amrize Southwest Inc 1,210.000 $212.30 $256,883.00 W. W. Clyde & Co. 1,210.000 $209.00 $252,890.00 Las Vegas Paving Corporation 1,210.000 $205.00 $248,050.00

McKenzie Construction & Site Development, LLC

1,210.000 $150.00 $181,500.00

Engineer's Estimate 1,210.000 LNFT $240.00 $290,400.00

A0440 60201-0900 30-INCH PIPE

CULVERT

Road and Highway Builders 200.000 $800.00 $160,000.00

Hat Creek Construction & Materials, Inc.

200.000 $475.00 $95,000.00

Steve Manning Construction Inc 200.000 $380.00 $76,000.00

AE West LLC 200.000 $331.05 $66,210.00 Amrize Southwest Inc 200.000 $258.30 $51,660.00 W. W. Clyde & Co. 200.000 $254.00 $50,800.00 Las Vegas Paving Corporation 200.000 $249.00 $49,800.00

McKenzie Construction & Site Development, LLC

200.000 $184.00 $36,800.00

Engineer's Estimate 200.000 LNFT $210.00 $42,000.00

A0450 60201-1000 36-INCH PIPE

CULVERT

Road and Highway Builders 385.000 $900.00 $346,500.00

Steve Manning Construction Inc 385.000 $580.00 $223,300.00

Hat Creek Construction & Materials, Inc.

385.000 $475.00 $182,875.00

AE West LLC 385.000 $407.35 $156,829.75 Amrize Southwest Inc 385.000 $266.20 $102,487.00 W. W. Clyde & Co. 385.000 $262.00 $100,870.00 Las Vegas Paving Corporation 385.000 $257.00 $98,945.00

McKenzie Construction & Site Development, LLC

385.000 $235.00 $90,475.00

Engineer's Estimate 385.000 LNFT $240.00 $92,400.00

A0460 60201-1200 48-INCH PIPE

CULVERT

Road and Highway Builders 270.000 $1,000.00 $270,000.00

Steve Manning Construction Inc 270.000 $650.00 $175,500.00

AE West LLC 270.000 $647.43 $174,806.10

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0460 60201-1200 48-INCH PIPE

CULVERT

Hat Creek Construction & Materials, Inc.

270.000 $500.00 $135,000.00

McKenzie Construction & Site Development, LLC

270.000 $364.00 $98,280.00

Amrize Southwest Inc 270.000 $360.50 $97,335.00 W. W. Clyde & Co. 270.000 $355.00 $95,850.00 Las Vegas Paving Corporation 270.000 $348.00 $93,960.00

Engineer's Estimate 270.000 LNFT $340.00 $91,800.00

A0470 60210-0400 END SECTION FOR

12-INCH PIPE

CULVERT

McKenzie Construction & Site Development, LLC

8.000 $2,340.00 $18,720.00

Amrize Southwest Inc 8.000 $1,089.00 $8,712.00 W. W. Clyde & Co. 8.000 $1,072.00 $8,576.00 Las Vegas Paving Corporation 8.000 $1,050.00 $8,400.00

AE West LLC 8.000 $579.08 $4,632.64 Road and Highway Builders 8.000 $400.00 $3,200.00

Steve Manning Construction Inc 8.000 $400.00 $3,200.00

Hat Creek Construction & Materials, Inc.

8.000 $100.00 $800.00

Engineer's Estimate 8.000 EACH $760.00 $6,080.00

A0480 60210-0600 END SECTION FOR

18-INCH PIPE

CULVERT

McKenzie Construction & Site Development, LLC

12.000 $2,340.00 $28,080.00

Amrize Southwest Inc 12.000 $1,221.00 $14,652.00 W. W. Clyde & Co. 12.000 $1,201.00 $14,412.00 Las Vegas Paving Corporation 12.000 $1,160.00 $13,920.00

Road and Highway Builders 12.000 $1,000.00 $12,000.00

Steve Manning Construction Inc 12.000 $800.00 $9,600.00

AE West LLC 12.000 $493.34 $5,920.08 Hat Creek Construction & Materials, Inc.

12.000 $150.00 $1,800.00

Engineer's Estimate 12.000 EACH $1,390.00 $16,680.00

A0490 60210-0800 END SECTION FOR

24-INCH PIPE

CULVERT

McKenzie Construction & Site Development, LLC

50.000 $2,476.00 $123,800.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0490 60210-0800 END SECTION FOR

24-INCH PIPE

CULVERT

Road and Highway Builders 50.000 $1,500.00 $75,000.00

Amrize Southwest Inc 50.000 $1,348.00 $67,400.00 W. W. Clyde & Co. 50.000 $1,326.00 $66,300.00 Las Vegas Paving Corporation 50.000 $1,300.00 $65,000.00

Steve Manning Construction Inc 50.000 $900.00 $45,000.00

AE West LLC 50.000 $746.47 $37,323.50 Hat Creek Construction & Materials, Inc.

50.000 $200.00 $10,000.00

Engineer's Estimate 50.000 EACH $1,100.00 $55,000.00

A0500 60210-0900 END SECTION FOR

30-INCH PIPE

CULVERT

McKenzie Construction & Site Development, LLC

4.000 $3,835.00 $15,340.00

Road and Highway Builders 4.000 $2,000.00 $8,000.00

Amrize Southwest Inc 4.000 $1,707.00 $6,828.00 W. W. Clyde & Co. 4.000 $1,680.00 $6,720.00 Las Vegas Paving Corporation 4.000 $1,650.00 $6,600.00

Steve Manning Construction Inc 4.000 $1,500.00 $6,000.00

AE West LLC 4.000 $1,065.50 $4,262.00 Hat Creek Construction & Materials, Inc.

4.000 $700.00 $2,800.00

Engineer's Estimate 4.000 EACH $1,900.00 $7,600.00

A0510 60210-1000 END SECTION FOR

36-INCH PIPE

CULVERT

McKenzie Construction & Site Development, LLC

14.000 $8,946.00 $125,244.00

Road and Highway Builders 14.000 $3,000.00 $42,000.00

Amrize Southwest Inc 14.000 $2,190.00 $30,660.00 W. W. Clyde & Co. 14.000 $2,155.00 $30,170.00 Las Vegas Paving Corporation 14.000 $2,100.00 $29,400.00

Steve Manning Construction Inc 14.000 $1,650.00 $23,100.00

AE West LLC 14.000 $1,382.22 $19,351.08 Hat Creek Construction & Materials, Inc.

14.000 $850.00 $11,900.00

Engineer's Estimate 14.000 EACH $1,500.00 $21,000.00

A0520 61901-3300 FENCE, TORTOISE

BARRIER

Steve Manning Construction Inc 3,000.000 $38.00 $114,000.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0520 61901-3300 FENCE, TORTOISE

BARRIER

Las Vegas Paving Corporation 3,000.000 $34.00 $102,000.00

AE West LLC 3,000.000 $23.26 $69,780.00 Amrize Southwest Inc 3,000.000 $20.20 $60,600.00 Hat Creek Construction & Materials, Inc.

3,000.000 $20.00 $60,000.00

McKenzie Construction & Site Development, LLC

3,000.000 $20.00 $60,000.00

W. W. Clyde & Co. 3,000.000 $20.00 $60,000.00 Road and Highway Builders 3,000.000 $10.00 $30,000.00

Engineer's Estimate 3,000.000 LNFT $14.50 $43,500.00

A0530 62201-0200 DUMP TRUCK, 8

CUBIC YARD

MINIMUM

CAPACITY

Steve Manning Construction Inc 120.000 $250.00 $30,000.00

W. W. Clyde & Co. 120.000 $233.00 $27,960.00 McKenzie Construction & Site Development, LLC

120.000 $216.00 $25,920.00

Road and Highway Builders 120.000 $200.00 $24,000.00

Amrize Southwest Inc 120.000 $181.60 $21,792.00 Hat Creek Construction & Materials, Inc.

120.000 $180.00 $21,600.00

AE West LLC 120.000 $162.15 $19,458.00 Las Vegas Paving Corporation 120.000 $150.00 $18,000.00

Engineer's Estimate 120.000 HOUR $185.00 $22,200.00

A0540 62201-0550 BACKHOE LOADER,

6 CUBIC FOOT

MINIMUM RATED

CAPACITY BUCKET,

24-INCH WIDTH

W. W. Clyde & Co. 100.000 $337.00 $33,700.00 McKenzie Construction & Site Development, LLC

100.000 $293.00 $29,300.00

Steve Manning Construction Inc 100.000 $250.00 $25,000.00

Amrize Southwest Inc 100.000 $205.60 $20,560.00 AE West LLC 100.000 $202.32 $20,232.00 Las Vegas Paving Corporation 100.000 $191.00 $19,100.00

Road and Highway Builders 100.000 $180.00 $18,000.00

Hat Creek Construction & Materials, Inc.

100.000 $170.00 $17,000.00

Engineer's Estimate 100.000 HOUR $170.00 $17,000.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0550 62201-0950 WHEEL LOADER, 3

CUBIC YARD

MINIMUM RATED

CAPACITY

W. W. Clyde & Co. 100.000 $344.00 $34,400.00 Hat Creek Construction & Materials, Inc.

100.000 $265.00 $26,500.00

Steve Manning Construction Inc 100.000 $250.00 $25,000.00

Amrize Southwest Inc 100.000 $249.60 $24,960.00 AE West LLC 100.000 $233.93 $23,393.00 McKenzie Construction & Site Development, LLC

100.000 $221.00 $22,100.00

Road and Highway Builders 100.000 $200.00 $20,000.00

Las Vegas Paving Corporation 100.000 $198.00 $19,800.00

Engineer's Estimate 100.000 HOUR $180.00 $18,000.00

A0560 62201-1450 BULLDOZER, 350HP

MINIMUM

FLYWHEEL POWER

W. W. Clyde & Co. 100.000 $558.00 $55,800.00 Steve Manning Construction Inc 100.000 $380.00 $38,000.00

Hat Creek Construction & Materials, Inc.

100.000 $350.00 $35,000.00

AE West LLC 100.000 $322.80 $32,280.00 McKenzie Construction & Site Development, LLC

100.000 $309.00 $30,900.00

Las Vegas Paving Corporation 100.000 $302.00 $30,200.00

Amrize Southwest Inc 100.000 $263.60 $26,360.00 Road and Highway Builders 100.000 $250.00 $25,000.00

Engineer's Estimate 100.000 HOUR $295.00 $29,500.00

A0570 62201-2850 MOTOR GRADER,

12 FOOT

MINIMUM BLADE

W. W. Clyde & Co. 100.000 $404.00 $40,400.00 Steve Manning Construction Inc 100.000 $350.00 $35,000.00

Amrize Southwest Inc 100.000 $297.30 $29,730.00 McKenzie Construction & Site Development, LLC

100.000 $293.00 $29,300.00

AE West LLC 100.000 $278.53 $27,853.00 Hat Creek Construction & Materials, Inc.

100.000 $265.00 $26,500.00

Las Vegas Paving Corporation 100.000 $251.00 $25,100.00

Road and Highway Builders 100.000 $200.00 $20,000.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0570 62201-2850 MOTOR GRADER,

12 FOOT

MINIMUM BLADE

Engineer's Estimate 100.000 HOUR $250.00 $25,000.00

A0580 62201-3350 HYDRAULIC

EXCAVATOR, 1

CUBIC YARD

MINIMUM

CAPACITY

W. W. Clyde & Co. 100.000 $343.00 $34,300.00 McKenzie Construction & Site Development, LLC

100.000 $309.00 $30,900.00

Steve Manning Construction Inc 100.000 $300.00 $30,000.00

Amrize Southwest Inc 100.000 $263.80 $26,380.00 Las Vegas Paving Corporation 100.000 $225.00 $22,500.00

Hat Creek Construction & Materials, Inc.

100.000 $220.00 $22,000.00

Road and Highway Builders 100.000 $200.00 $20,000.00

AE West LLC 100.000 $193.61 $19,361.00 Engineer's Estimate 100.000 HOUR $265.00 $26,500.00

A0590 62301-0000 GENERAL LABOR AE West LLC 60.000 $212.96 $12,777.60 W. W. Clyde & Co. 60.000 $180.00 $10,800.00 McKenzie Construction & Site Development, LLC

60.000 $139.00 $8,340.00

Steve Manning Construction Inc 60.000 $120.00 $7,200.00

Las Vegas Paving Corporation 60.000 $109.00 $6,540.00

Amrize Southwest Inc 60.000 $101.00 $6,060.00 Road and Highway Builders 60.000 $90.00 $5,400.00

Hat Creek Construction & Materials, Inc.

60.000 $85.00 $5,100.00

Engineer's Estimate 60.000 HOUR $100.00 $6,000.00

A0600 62302-1100 SPECIAL LABOR,

HIRED SURVEY

SERVICES

AE West LLC 60.000 $575.00 $34,500.00 Hat Creek Construction & Materials, Inc.

60.000 $460.00 $27,600.00

Steve Manning Construction Inc 60.000 $420.00 $25,200.00

McKenzie Construction & Site Development, LLC

60.000 $379.00 $22,740.00

Amrize Southwest Inc 60.000 $348.20 $20,892.00 Las Vegas Paving Corporation 60.000 $344.00 $20,640.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0600 62302-1100 SPECIAL LABOR,

HIRED SURVEY

SERVICES

Road and Highway Builders 60.000 $200.00 $12,000.00

W. W. Clyde & Co. 60.000 $193.00 $11,580.00 Engineer's Estimate 60.000 HOUR $200.00 $12,000.00

A0610 62303-1000 SPECIAL LABOR,

HIRED TECHNICAL

SERVICES (ADTB)

AE West LLC $805,000.70 W. W. Clyde & Co. $668,607.00 Las Vegas Paving Corporation $654,000.00

Steve Manning Construction Inc $565,000.00

Amrize Southwest Inc $518,755.00 McKenzie Construction & Site Development, LLC

$503,958.00

Hat Creek Construction & Materials, Inc.

$50,000.00

Road and Highway Builders $50,000.00

Engineer's Estimate ALL LPSM LPSM $72,000.00

A0620 62406-0100 PLACING

CONSERVED

TOPSOIL, 2-INCH

DEPTH

Steve Manning Construction Inc 40.000 $22,000.00 $880,000.00

AE West LLC 40.000 $9,644.25 $385,770.00 W. W. Clyde & Co. 40.000 $7,478.00 $299,120.00 McKenzie Construction & Site Development, LLC

40.000 $5,150.00 $206,000.00

Las Vegas Paving Corporation 40.000 $4,668.00 $186,720.00

Hat Creek Construction & Materials, Inc.

40.000 $4,100.00 $164,000.00

Amrize Southwest Inc 40.000 $3,905.00 $156,200.00 Road and Highway Builders 40.000 $1,500.00 $60,000.00

Engineer's Estimate 40.000 ACRE $3,500.00 $140,000.00

A0630 62510-2000 SEEDING,

HYDRAULIC

METHOD

Las Vegas Paving Corporation 40.000 $5,600.00 $224,000.00

Amrize Southwest Inc 40.000 $4,043.00 $161,720.00 W. W. Clyde & Co. 40.000 $3,978.00 $159,120.00 AE West LLC 40.000 $3,451.48 $138,059.20 Hat Creek Construction & Materials, Inc.

40.000 $2,000.00 $80,000.00

Steve Manning Construction Inc 40.000 $2,000.00 $80,000.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0630 62510-2000 SEEDING,

HYDRAULIC

METHOD

McKenzie Construction & Site Development, LLC

40.000 $1,153.00 $46,120.00

Road and Highway Builders 40.000 $800.00 $32,000.00

Engineer's Estimate 40.000 ACRE $2,900.00 $116,000.00

A0635 62515-2000 MULCHING,

HYDRAULIC

METHOD

AE West LLC 40.000 $8,656.25 $346,250.00 Amrize Southwest Inc 40.000 $6,177.00 $247,080.00 W. W. Clyde & Co. 40.000 $6,078.00 $243,120.00 Las Vegas Paving Corporation 40.000 $6,000.00 $240,000.00

Steve Manning Construction Inc 40.000 $5,000.00 $200,000.00

McKenzie Construction & Site Development, LLC

40.000 $4,614.00 $184,560.00

Hat Creek Construction & Materials, Inc.

40.000 $1,565.00 $62,600.00

Road and Highway Builders 40.000 $800.00 $32,000.00

Engineer's Estimate 40.000 ACRE $3,000.00 $120,000.00 A0640 63301-0000 SIGN SYSTEM W. W. Clyde & Co. 64.000 $1,934.00 $123,776.00

Road and Highway Builders 64.000 $1,500.00 $96,000.00

AE West LLC 64.000 $700.53 $44,833.92 Hat Creek Construction & Materials, Inc.

64.000 $600.00 $38,400.00

Steve Manning Construction Inc 64.000 $500.00 $32,000.00

McKenzie Construction & Site Development, LLC

64.000 $463.00 $29,632.00

Amrize Southwest Inc 64.000 $426.80 $27,315.20 Las Vegas Paving Corporation 64.000 $412.00 $26,368.00

Engineer's Estimate 64.000 EACH $660.00 $42,240.00

A0650 63301-0000 SIGN SYSTEM

(WITH FLASHING

BEACON)

McKenzie Construction & Site Development, LLC

8.000 $13,518.00 $108,144.00

Steve Manning Construction Inc 8.000 $13,500.00 $108,000.00

AE West LLC 8.000 $4,140.00 $33,120.00 Amrize Southwest Inc 8.000 $3,706.00 $29,648.00 Las Vegas Paving Corporation 8.000 $3,600.00 $28,800.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0650 63301-0000 SIGN SYSTEM

(WITH FLASHING

BEACON)

Road and Highway Builders 8.000 $3,000.00 $24,000.00

W. W. Clyde & Co. 8.000 $2,763.00 $22,104.00 Hat Creek Construction & Materials, Inc.

8.000 $2,500.00 $20,000.00

Engineer's Estimate 8.000 EACH $1,200.00 $9,600.00

A0660 63306-0400 POST, STEEL, 2-

INCH X 2-INCH

Road and Highway Builders 44.000 $500.00 $22,000.00

Hat Creek Construction & Materials, Inc.

44.000 $400.00 $17,600.00

AE West LLC 44.000 $345.00 $15,180.00 W. W. Clyde & Co. 44.000 $276.00 $12,144.00 Amrize Southwest Inc 44.000 $252.70 $11,118.80 Steve Manning Construction Inc 44.000 $250.00 $11,000.00

Las Vegas Paving Corporation 44.000 $244.00 $10,736.00

McKenzie Construction & Site Development, LLC

44.000 $231.00 $10,164.00

Engineer's Estimate 44.000 EACH $330.00 $14,520.00

A0670 63308-2000 OBJECT MARKER,

TYPE 2

AE West LLC 48.000 $230.00 $11,040.00 Road and Highway Builders 48.000 $200.00 $9,600.00

Amrize Southwest Inc 48.000 $157.20 $7,545.60 Las Vegas Paving Corporation 48.000 $152.00 $7,296.00

Steve Manning Construction Inc 48.000 $135.00 $6,480.00

McKenzie Construction & Site Development, LLC

48.000 $128.00 $6,144.00

Hat Creek Construction & Materials, Inc.

48.000 $95.00 $4,560.00

W. W. Clyde & Co. 48.000 $17.00 $816.00 Engineer's Estimate 48.000 EACH $110.00 $5,280.00

A0680 63309-0200 DELINEATOR, TYPE

AE West LLC 970.000 $143.75 $139,437.50 Road and Highway Builders 970.000 $120.00 $116,400.00

Steve Manning Construction Inc 970.000 $90.00 $87,300.00

Amrize Southwest Inc 970.000 $85.90 $83,323.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0680 63309-0200 DELINEATOR, TYPE

McKenzie Construction & Site Development, LLC

970.000 $84.00 $81,480.00

Las Vegas Paving Corporation 970.000 $83.00 $80,510.00

Hat Creek Construction & Materials, Inc.

970.000 $80.00 $77,600.00

W. W. Clyde & Co. 970.000 $28.00 $27,160.00 Engineer's Estimate 970.000 EACH $95.00 $92,150.00

A0690 63314-0000 RUMBLE STRIP McKenzie Construction & Site Development, LLC

1.700 $10,300.00 $17,510.00

Amrize Southwest Inc 1.700 $8,942.00 $15,201.40 Hat Creek Construction & Materials, Inc.

1.700 $7,700.00 $13,090.00

Las Vegas Paving Corporation 1.700 $4,425.00 $7,522.50

AE West LLC 1.700 $4,140.00 $7,038.00 Road and Highway Builders 1.700 $4,000.00 $6,800.00

W. W. Clyde & Co. 1.700 $1,220.00 $2,074.00 Steve Manning Construction Inc 1.700 $750.00 $1,275.00

Engineer's Estimate 1.700 MILE $4,600.00 $7,820.00

A0700 63316-1000 REMOVE AND

RESET SIGN (PANEL

ONLY)

Road and Highway Builders 44.000 $1,000.00 $44,000.00

W. W. Clyde & Co. 44.000 $553.00 $24,332.00 AE West LLC 44.000 $230.00 $10,120.00 Steve Manning Construction Inc 44.000 $135.00 $5,940.00

McKenzie Construction & Site Development, LLC

44.000 $128.00 $5,632.00

Amrize Southwest Inc 44.000 $112.30 $4,941.20 Las Vegas Paving Corporation 44.000 $109.00 $4,796.00

Hat Creek Construction & Materials, Inc.

44.000 $60.00 $2,640.00

Engineer's Estimate 44.000 EACH $220.00 $9,680.00

A0710 63401-0300 PAVEMENT

MARKINGS, TYPE B,

SOLID

W. W. Clyde & Co. 2,250.000 $22.00 $49,500.00 Road and Highway Builders 2,250.000 $6.00 $13,500.00

AE West LLC 2,250.000 $3.45 $7,762.50 Amrize Southwest Inc 2,250.000 $2.25 $5,062.50

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0710 63401-0300 PAVEMENT

MARKINGS, TYPE B,

SOLID

Steve Manning Construction Inc 2,250.000 $2.20 $4,950.00

Las Vegas Paving Corporation 2,250.000 $2.15 $4,837.50

Hat Creek Construction & Materials, Inc.

2,250.000 $2.00 $4,500.00

McKenzie Construction & Site Development, LLC

2,250.000 $2.00 $4,500.00

Engineer's Estimate 2,250.000 LNFT $4.30 $9,675.00

A0720 63402-0300 PAVEMENT

MARKINGS, TYPE B,

SOLID

McKenzie Construction & Site Development, LLC

47.000 $4,120.00 $193,640.00

W. W. Clyde & Co. 47.000 $1,823.00 $85,681.00 Steve Manning Construction Inc 47.000 $1,450.00 $68,150.00

Hat Creek Construction & Materials, Inc.

47.000 $1,435.00 $67,445.00

AE West LLC 47.000 $1,380.00 $64,860.00 Amrize Southwest Inc 47.000 $1,011.00 $47,517.00 Road and Highway Builders 47.000 $1,000.00 $47,000.00

Las Vegas Paving Corporation 47.000 $977.00 $45,919.00

Engineer's Estimate 47.000 MILE $1,500.00 $70,500.00

A0730 63402-0400 PAVEMENT

MARKINGS, TYPE B,

BROKEN

McKenzie Construction & Site Development, LLC

22.000 $4,532.00 $99,704.00

W. W. Clyde & Co. 22.000 $1,823.00 $40,106.00 Steve Manning Construction Inc 22.000 $1,000.00 $22,000.00

Hat Creek Construction & Materials, Inc.

22.000 $895.00 $19,690.00

Road and Highway Builders 22.000 $800.00 $17,600.00

AE West LLC 22.000 $402.50 $8,855.00 Amrize Southwest Inc 22.000 $252.70 $5,559.40 Las Vegas Paving Corporation 22.000 $244.00 $5,368.00

Engineer's Estimate 22.000 MILE $980.00 $21,560.00

A0740 63406-0100 RAISED PAVEMENT

MARKER, NON-

REFLECTIVE

W. W. Clyde & Co. 320.000 $28.00 $8,960.00 Road and Highway Builders 320.000 $20.00 $6,400.00

Steve Manning Construction Inc 320.000 $12.00 $3,840.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0740 63406-0100 RAISED PAVEMENT

MARKER, NON-

REFLECTIVE

Hat Creek Construction & Materials, Inc.

320.000 $10.00 $3,200.00

McKenzie Construction & Site Development, LLC

320.000 $10.00 $3,200.00

AE West LLC 320.000 $9.20 $2,944.00 Amrize Southwest Inc 320.000 $8.40 $2,688.00 Las Vegas Paving Corporation 320.000 $8.15 $2,608.00

Engineer's Estimate 320.000 EACH $14.00 $4,480.00

A0745 63501-0000 TEMPORARY

TRAFFIC CONTROL

AE West LLC $4,750,350.84 Hat Creek Construction & Materials, Inc.

$2,500,000.00

Las Vegas Paving Corporation $2,402,000.00

Steve Manning Construction Inc $1,700,000.00

Road and Highway Builders $1,600,000.00

W. W. Clyde & Co. $1,259,767.00 Amrize Southwest Inc $1,169,355.00 McKenzie Construction & Site Development, LLC

$1,071,200.00

Engineer's Estimate ALL LPSM LPSM $988,300.00 A0830 63701-0000 FIELD OFFICE Las Vegas Paving

Corporation 1.000 $385,900.00 $385,900.00

Road and Highway Builders 1.000 $150,000.00 $150,000.00

AE West LLC 1.000 $89,700.08 $89,700.08 W. W. Clyde & Co. 1.000 $83,811.00 $83,811.00 Hat Creek Construction & Materials, Inc.

1.000 $65,000.00 $65,000.00

McKenzie Construction & Site Development, LLC

1.000 $46,036.00 $46,036.00

Amrize Southwest Inc 1.000 $45,750.00 $45,750.00 Steve Manning Construction Inc 1.000 $30,000.00 $30,000.00

Engineer's Estimate 1.000 EACH $50,000.00 $50,000.00

A0840 64620-0400 REMOVE AND

RESET MAILBOX

W. W. Clyde & Co. 19.000 $2,960.00 $56,240.00 McKenzie Construction & Site Development, LLC

19.000 $2,060.00 $39,140.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

A0840 64620-0400 REMOVE AND

RESET MAILBOX

Road and Highway Builders 19.000 $1,500.00 $28,500.00

Amrize Southwest Inc 19.000 $1,123.00 $21,337.00 Las Vegas Paving Corporation 19.000 $1,100.00 $20,900.00

Hat Creek Construction & Materials, Inc.

19.000 $1,000.00 $19,000.00

AE West LLC 19.000 $901.97 $17,137.43 Steve Manning Construction Inc 19.000 $600.00 $11,400.00

Engineer's Estimate 19.000 EACH $410.00 $7,790.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

Project No. : NV FLAP NYE 10(1) Project Name: BOB RUUD MEM

HWY & BELL VISTA

AVE

Division: Central Federal Lands

Schedule: B Schedule Type: Base Lead Designer:

Solicitation No. : 6982AF26B000003 Opened at: Lakewood, CO Opened by: Ryan Phillips State: NV County: Nye Federal Land: Ash Meadows NWR Bid Open Date and Time: 06/10/2026

Contract Awarded to: Award Date:

Contractor Comment Bid Amount Responsive Steve Manning Construction Inc, 5211 Churn Creek Road, Redding, CA, 96002

$44,852,360.00

McKenzie Construction & Site Development, LLC, 2301 Calvert St NW, Washington, DC, 20008

$43,992,094.96

AE West LLC, 3112 Spring Hollow Court, Ann Arbor, MI, 48105

$41,527,409.68

W. W. Clyde & Co., 869 N 1500 W, Orem, UT, 84057

$31,429,324.60

Road and Highway Builders $30,555,555.00 Hat Creek Construction & Materials, Inc., 24339 Highway 89 N, Burney, CA, 96013

$29,994,499.00

I certify that this Bid Tabulation reflects the offers received for this solicitation

Signed:

Title:

Date:

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

Generated by : Denise Martinez

Contract Specialist

Las Vegas Paving Corporation, 4420 S. Decatur Blvd, Las Vegas, NV, 89103

$27,591,000.00

Amrize Southwest Inc, 4675 WEST TECO #140, LAS VEGAS, NV, 89118

$26,528,454.90

Engineer's Estimate $32,897,260.00

Project No. : NV FLAP NYE 10(1) Project Name: BOB RUUD MEM HWY & BELL VISTA

AVE

Schedule: B Schedule Type: Base

Line Item Number

Pay Item Number Description Contractor Quantity Unit Unit Price Amount

B0010 15101-0000 MOBILIZATION McKenzie Construction & Site Development, LLC

$7,016,026.46

Steve Manning Construction Inc $4,300,000.00

Road and Highway Builders $3,002,335.00

Hat Creek Construction & Materials, Inc.

$2,980,000.00

W. W. Clyde & Co. $2,765,689.00 AE West LLC $2,472,961.94 Las Vegas Paving Corporation $912,211.00

Amrize Southwest Inc $746,975.00 Engineer's Estimate ALL LPSM LPSM $2,891,952.80

B0020 15215-1000 SURVEY AND

STAKING,

APPROACH ROAD

Steve Manning Construction Inc 33.000 $3,000.00 $99,000.00

Las Vegas Paving Corporation 33.000 $2,800.00 $92,400.00

W. W. Clyde & Co. 33.000 $1,818.00 $59,994.00 AE West LLC 33.000 $1,725.00 $56,925.00 McKenzie Construction & Site Development, LLC

33.000 $1,621.00 $53,493.00

Road and Highway Builders 33.000 $1,000.00 $33,000.00

Amrize Southwest Inc 33.000 $805.80 $26,591.40 Hat Creek Construction & Materials, Inc.

33.000 $400.00 $13,200.00

Engineer's Estimate 33.000 EACH $710.00 $23,430.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

B0030 15215-3000 SURVEY AND

STAKING,

DRAINAGE

STRUCTURE

Las Vegas Paving Corporation 80.000 $2,800.00 $224,000.00

AE West LLC 80.000 $2,300.00 $184,000.00 McKenzie Construction & Site Development, LLC

80.000 $2,212.00 $176,960.00

Steve Manning Construction Inc 80.000 $2,000.00 $160,000.00

Hat Creek Construction & Materials, Inc.

80.000 $1,200.00 $96,000.00

Road and Highway Builders 80.000 $1,000.00 $80,000.00

Amrize Southwest Inc 80.000 $785.70 $62,856.00 W. W. Clyde & Co. 80.000 $448.00 $35,840.00 Engineer's Estimate 80.000 EACH $1,300.00 $104,000.00

B0040 15225-0000 SLOPE, REFERENCE,

AND CLEARING

AND GRUBBING

CONTROL

Amrize Southwest Inc 20.500 $28,388.00 $581,954.00 Steve Manning Construction Inc 20.500 $16,000.00 $328,000.00

Las Vegas Paving Corporation 20.500 $14,100.00 $289,050.00

McKenzie Construction & Site Development, LLC

20.500 $7,997.00 $163,938.50

Hat Creek Construction & Materials, Inc.

20.500 $5,400.00 $110,700.00

W. W. Clyde & Co. 20.500 $4,505.00 $92,352.50 AE West LLC 20.500 $2,300.00 $47,150.00 Road and Highway Builders 20.500 $1,000.00 $20,500.00

Engineer's Estimate 20.500 MILE $8,400.00 $172,200.00

B0050 15236-2000 SURVEY CONTROL,

GRADE FINISHING

McKenzie Construction & Site Development, LLC

41.000 $29,533.00 $1,210,853.00

Las Vegas Paving Corporation 41.000 $14,100.00 $578,100.00

Amrize Southwest Inc 41.000 $10,377.00 $425,457.00 W. W. Clyde & Co. 41.000 $7,508.00 $307,828.00 Steve Manning Construction Inc 41.000 $6,000.00 $246,000.00

Hat Creek Construction & Materials, Inc.

41.000 $4,200.00 $172,200.00

AE West LLC 41.000 $3,680.00 $150,880.00 Road and Highway Builders 41.000 $1,000.00 $41,000.00

Report Generated on 06/23/2026 12:41 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]

B0050 15236-2000 SURVEY CONTROL,

GRADE FINISHING Engineer's Estimate 41.000 MILE $5,800.00 $237,800.00

B0060 15301-0000 CONTRACTOR

QUALITY CONTROL

Road and Highway Builders $1,400,000.00

Hat Creek Construction & Materials, Inc.

$1,000,000.00

Steve Manning Construction Inc $760,000.00

Amrize Southwest Inc $729,730.00 Las Vegas Paving Corporation $616,000.00

W. W. Clyde & Co. $579,926.55 AE West LLC $461,773.33 McKenzie Construction & Site Development, LLC

$324,926.00

Engineer's Estimate ALL LPSM LPSM $730,000.00

B0070 15401-0000 CONTRACTOR

TESTING

Hat Creek Construction & Materials, Inc.

$1,450,081.00

Road and Highway Builders $1,200,000.00

W. W. Clyde & Co. $1,094,877.28 McKenzie Construction & Site Development, LLC

$824,063.00

Steve Manning Construction Inc $650,000.00

AE West…