This document is a set of Questions and Answers related to the federal contract opportunity for the WY FLAP JOH 14(1) North Fork Crazy Woman Creek Bridge project.
The key details are:
- The project scope includes replacing an existing bridge structure on Crazy Woman Canyon Road/Route 33, reconstructing the roadway approaches, installing object markers, and improving a pullout area.
- The new bridge will be a 14-foot wide, 51-foot long single span structure, with rolled girders, structural steel decking, and a gravel surface.
- The project has a bid date listed on the Invitation for Bid, and no ground disturbing activities can begin prior to May 1, 2025, with a contract completion date of September 26, 2025.
- The existing bridge has load ratings for various vehicle types.
- The agency involved is the Department of Transportation Federal Highway Administration.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for WY FLAP JOH 14(1) North Fork Crazy Woman Creek Bridge
August 30, 2024
Questions Answers 1 Ref. Sheet S9 Typical Section; At the Typical Section, the thrie-beam bridge railing is called-out as weathering steel. Special Provision article 555.03A(e) specifies galvanized guardrail. Please clarify.
Use weathering steel for the thrie-beam bridge railing. Please refer to Amendment A001.
September 3, 2024
Questions Answers 2 Do you have the anticipated bid date and construction timeframe for this project?
Bid date can be found on sheet A-1 of the invitation for bid.
Per SCR’s Subsection 108.01: No ground disturbing activities can begin prior to May 1, 2025, and the contract completion date is September 26, 2025.