Bid Tabs WY FLAP JOH 14(1).pdf

PDF 658 KB Posted

Attached to
WY FLAP JOH 14(1) North Fork Crazy Woman Creek Bridge
Solicitation number
6982AF24B000023
Issued by

About this file

This document is a Tabulation of Bids Report for the WY FLAP JOH 14(1) North Fork Crazy Woman Creek Bridge project. The project involves replacing an existing bridge structure on Route 33/Crazy Woman Canyon Road, including reconstruction of the roadway approaches and pullout improvements. The proposed structure is a 14-foot wide, 51-foot long single span prefabricated steel bridge with a gravel deck surface.

The solicitation number is 6982AF24B000023, with bids opened on 10/01/24. The engineer's estimate for the project was $1,370,000. The low bid was submitted by Battle Ridge Builders LLC at $1,085,125, followed by MC2 Engineering and Construction ($1,393,024), TCA Group Inc. ($1,444,110), and Harrison Western Construction Corporation ($1,999,220). Key bid items include mobilization, construction surveying, quality control, micropile foundations, and temporary traffic control. The contract was awarded, but the award date is not specified in the document.

View the file

Other files

File Type Posted
Bid Opening Summary Sched A WY FLAP JOH 14(1).pdf PDF
QnA 09.25.24.pdf PDF
QnA 09.20.24.pdf PDF
QnA 09.19.24.pdf PDF
A002.pdf PDF
QnA 09.17.24.pdf PDF
QnA 09.10.24.pdf PDF
Pre-Bid Site Visit Sign In Sheet.pdf PDF
WY FLAP JOH 14(1)_Prebid presentation.pdf PDF
QnA 09.03.24.pdf PDF
A001.pdf PDF
QnA 08.30.24.pdf PDF
FP-14.pdf PDF
6982AF24B000023.pdf PDF
HYD Report WY FLAP JOH 14(1).pdf PDF
GEO Report Addendum WY FLAP JOH 14(1).pdf PDF
GEO Report WY FLAP JOH 14(1).pdf PDF
WY FLAP JOH 14(1) Plans Flattened.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 10/03/24

1 out of 9

Project No: WY FLAP JOH 14(1)

Project Name: North Fork Crazy Woman Creek Bridge

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF24B000023

Division: Central Federal Lands

State: WY County: Johnson

Federal Land: USFS Bighorn National Forest Opened at: Lakewood, Colorado

Opened by: Leslie Karsten

Date: 10/01/24

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Battle Ridge Builders LLC $1,085,125.00 354 Countryside LN Belgrade, MT 59714

MC2 Engineering and Construction, PC $1,393,023.96 850 North Main Street Sheridan, WY 82801

TCA Group Inc. $1,444,110.00 2223 Montana Avenue, Suite Billings, MT 59101

HARRISON WESTERN CONSTRUCTION CORPO $1,999,220.00

1208 Quail Street Lakewood, CO 80215

Engineer's Estimate $1,370,000.00

Contract Specialist 10/03/2024

2 out of 9

Project No: WY FLAP JOH 14(1)

Project Name: North Fork Crazy Woman Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0100 15101-0000 MOBILIZATION

Battle Ridge Builders LLC Lump Sum $271,000.00 MC2 Engineering and Construction, PC Lump Sum $38,560.00 TCA Group Inc. Lump Sum $240,000.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $260,000.00 Engineer's Estimate ALL LPSM Lump Sum $188,773.75

A0120 15201-0000 CONSTRUCTION SURVEY AND STAKING

Battle Ridge Builders LLC Lump Sum $9,000.00 MC2 Engineering and Construction, PC Lump Sum $12,050.00 TCA Group Inc. Lump Sum $7,500.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $1,050.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0140 15214-1000 SURVEY AND STAKING, BRIDGE

Battle Ridge Builders LLC Lump Sum $18,000.00 MC2 Engineering and Construction, PC Lump Sum $23,109.62 TCA Group Inc. Lump Sum $7,500.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $1,050.00 Engineer's Estimate ALL LPSM Lump Sum $12,000.00

A0160 15301-0000 CONTRACTOR QUALITY CONTROL

Battle Ridge Builders LLC Lump Sum $16,000.00 MC2 Engineering and Construction, PC Lump Sum $38,703.08 TCA Group Inc. Lump Sum $110,000.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $109,000.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00

A0180 15401-0000 CONTRACTOR TESTING

Battle Ridge Builders LLC Lump Sum $14,000.00 MC2 Engineering and Construction, PC Lump Sum $23,101.66 TCA Group Inc. Lump Sum $45,000.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $15,600.00 Engineer's Estimate ALL LPSM Lump Sum $35,000.00

A0200 15501-0000 CONSTRUCTION SCHEDULE

Battle Ridge Builders LLC Lump Sum $16,000.00 MC2 Engineering and Construction, PC Lump Sum $24,493.16 TCA Group Inc. Lump Sum $11,000.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $4,950.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

3 out of 9

Project No: WY FLAP JOH 14(1)

Project Name: North Fork Crazy Woman Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0220 15701-0000 SOIL EROSION CONTROL

Battle Ridge Builders LLC Lump Sum $18,000.00 MC2 Engineering and Construction, PC Lump Sum $25,378.66 TCA Group Inc. Lump Sum $18,000.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $55,900.00 Engineer's Estimate ALL LPSM Lump Sum $35,000.00

A0240 15802-0000 WATERING FOR DUST CONTROL

Battle Ridge Builders LLC Lump Sum $6,000.00 MC2 Engineering and Construction, PC Lump Sum $25,188.91 TCA Group Inc. Lump Sum $5,500.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $6,700.00 Engineer's Estimate ALL LPSM Lump Sum $55,000.00

A0260 20103-0000 CLEARING AND GRUBBING

Battle Ridge Builders LLC $40.00 $25,200.00 MC2 Engineering and Construction, PC $42.41 $26,718.30 TCA Group Inc. $32.00 $20,160.00

HARRISON WESTERN CONSTRUCTION CORPO $38.00 $23,940.00

Engineer's Estimate 630 SQYD $3.00 $1,890.00

A0280 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS

Battle Ridge Builders LLC Lump Sum $24,000.00 MC2 Engineering and Construction, PC Lump Sum $28,541.16 TCA Group Inc. Lump Sum $80,000.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $60,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

A0300 20304-2000 REMOVAL OF BRIDGE

Battle Ridge Builders LLC Lump Sum $64,000.00 MC2 Engineering and Construction, PC Lump Sum $61,431.16 TCA Group Inc. Lump Sum $68,000.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $62,000.00 Engineer's Estimate ALL LPSM Lump Sum $70,000.00

A0320 20420-0000 EMBANKMENT CONSTRUCTION

Battle Ridge Builders LLC $200.00 $13,000.00 MC2 Engineering and Construction, PC $580.19 $37,712.35 TCA Group Inc. $85.00 $5,525.00

HARRISON WESTERN CONSTRUCTION CORPO $620.00 $40,300.00

Engineer's Estimate 65 CUYD $175.00 $11,375.00

4 out of 9

Project No: WY FLAP JOH 14(1)

Project Name: North Fork Crazy Woman Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0340 20466-0000 CONSERVE AND STOCKPILE TOPSOIL

Battle Ridge Builders LLC $100.00 $1,500.00 MC2 Engineering and Construction, PC $1,776.24 $26,643.60 TCA Group Inc. $105.00 $1,575.00

HARRISON WESTERN CONSTRUCTION CORPO $800.00 $12,000.00

Engineer's Estimate 15 CUYD $15.00 $225.00

A0360 20801-0000 STRUCTURE EXCAVATION

Battle Ridge Builders LLC $200.00 $14,000.00 MC2 Engineering and Construction, PC $434.84 $30,438.80 TCA Group Inc. $65.00 $4,550.00

HARRISON WESTERN CONSTRUCTION CORPO $680.00 $47,600.00

Engineer's Estimate 70 CUYD $200.00 $14,000.00

A0380 20803-0000 STRUCTURAL BACKFILL

Battle Ridge Builders LLC $110.00 $2,200.00 MC2 Engineering and Construction, PC $959.61 $19,192.20 TCA Group Inc. $75.00 $1,500.00

HARRISON WESTERN CONSTRUCTION CORPO $690.00 $13,800.00

Engineer's Estimate 20 CUYD $300.00 $6,000.00

A0400 30202-2100 ROADWAY AGGREGATE, METHOD 2, SURFACE COURSE

Battle Ridge Builders LLC $80.00 $9,600.00 MC2 Engineering and Construction, PC $189.45 $22,734.00 TCA Group Inc. $95.00 $11,400.00

HARRISON WESTERN CONSTRUCTION CORPO $260.00 $31,200.00

Engineer's Estimate 120 TON $160.00 $19,200.00

A0420 30303-2000 AGGREGATE SURFACE RECONDITIONING

Battle Ridge Builders LLC $20.00 $2,500.00 MC2 Engineering and Construction, PC $263.75 $32,968.75 TCA Group Inc. $45.00 $5,625.00

HARRISON WESTERN CONSTRUCTION CORPO $190.00 $23,750.00

Engineer's Estimate 125 SQYD $15.00 $1,875.00

A0440 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Battle Ridge Builders LLC $4,000.00 $80,000.00 MC2 Engineering and Construction, PC $2,540.86 $50,817.20 TCA Group Inc. $1,600.00 $32,000.00

HARRISON WESTERN CONSTRUCTION CORPO $11,900.00 $238,000.00

Engineer's Estimate 20 CUYD $3,300.00 $66,000.00

5 out of 9

Project No: WY FLAP JOH 14(1)

Project Name: North Fork Crazy Woman Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0460 55401-1000 REINFORCING STEEL

Battle Ridge Builders LLC $5.00 $11,000.00 MC2 Engineering and Construction, PC $14.70 $32,340.00 TCA Group Inc. $10.00 $22,000.00

HARRISON WESTERN CONSTRUCTION CORPO $17.50 $38,500.00

Engineer's Estimate 2,200 LB $5.00 $11,000.00

A0480 55504-0000 PRE-FABRICATED STEEL BRIDGE (14'x49')

Battle Ridge Builders LLC Lump Sum $190,000.00 MC2 Engineering and Construction, PC Lump Sum $254,278.80 TCA Group Inc. Lump Sum $235,000.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $370,000.00 Engineer's Estimate ALL LPSM Lump Sum $270,000.00

A0500 56320-0000 CONTAINMENT SYSTEM AND WORKER PROTECTION PLAN

Battle Ridge Builders LLC Lump Sum $10,000.00 MC2 Engineering and Construction, PC Lump Sum $36,131.16 TCA Group Inc. Lump Sum $5,000.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $13,400.00 Engineer's Estimate ALL LPSM Lump Sum $105,000.00

A0520 56701-0000 MICROPILE (9" dia)

Battle Ridge Builders LLC $475.00 $152,000.00 MC2 Engineering and Construction, PC $622.86 $199,315.20 TCA Group Inc. $800.00 $256,000.00

HARRISON WESTERN CONSTRUCTION CORPO $500.00 $160,000.00

Engineer's Estimate 320 LNFT $600.00 $192,000.00

A0540 56705-0000 MICROPILE LOAD VERIFICATION TEST

Battle Ridge Builders LLC $39,000.00 $39,000.00 MC2 Engineering and Construction, PC $65,503.08 $65,503.08 TCA Group Inc. $65,000.00 $65,000.00

HARRISON WESTERN CONSTRUCTION CORPO $85,700.00 $85,700.00

Engineer's Estimate 1 EACH $20,000.00 $20,000.00

A0560 56706-0000 MICROPILE PROOF LOAD TEST

Battle Ridge Builders LLC $6,500.00 $13,000.00 MC2 Engineering and Construction, PC $29,257.02 $58,514.04 TCA Group Inc. $31,500.00 $63,000.00

HARRISON WESTERN CONSTRUCTION CORPO $6,350.00 $12,700.00

Engineer's Estimate 2 EACH $7,000.00 $14,000.00

6 out of 9

Project No: WY FLAP JOH 14(1)

Project Name: North Fork Crazy Woman Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0580 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY

Battle Ridge Builders LLC $130.00 $2,600.00 MC2 Engineering and Construction, PC $395.20 $7,904.00 TCA Group Inc. $245.00 $4,900.00

HARRISON WESTERN CONSTRUCTION CORPO $250.00 $5,000.00

Engineer's Estimate 20 HOUR $200.00 $4,000.00

A0600 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH

Battle Ridge Builders LLC $100.00 $4,000.00 MC2 Engineering and Construction, PC $180.75 $7,230.00 TCA Group Inc. $245.00 $9,800.00

HARRISON WESTERN CONSTRUCTION CORPO $150.00 $6,000.00

Engineer's Estimate 40 HOUR $180.00 $7,200.00

A0620 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Battle Ridge Builders LLC $140.00 $2,800.00 MC2 Engineering and Construction, PC $210.88 $4,217.60 TCA Group Inc. $225.00 $4,500.00

HARRISON WESTERN CONSTRUCTION CORPO $350.00 $7,000.00

Engineer's Estimate 20 HOUR $240.00 $4,800.00

A0640 62201-1300 BULLDOZER, 160HP MINIMUM FLYWHEEL POWER

Battle Ridge Builders LLC $140.00 $2,800.00 MC2 Engineering and Construction, PC $271.13 $5,422.60 TCA Group Inc. $245.00 $4,900.00

HARRISON WESTERN CONSTRUCTION CORPO $630.00 $12,600.00

Engineer's Estimate 20 HOUR $280.00 $5,600.00

A0660 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE

Battle Ridge Builders LLC $140.00 $2,800.00 MC2 Engineering and Construction, PC $301.25 $6,025.00 TCA Group Inc. $225.00 $4,500.00

HARRISON WESTERN CONSTRUCTION CORPO $650.00 $13,000.00

Engineer's Estimate 20 HOUR $270.00 $5,400.00

A0680 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY

Battle Ridge Builders LLC $140.00 $2,800.00 MC2 Engineering and Construction, PC $361.50 $7,230.00 TCA Group Inc. $245.00 $4,900.00

HARRISON WESTERN CONSTRUCTION CORPO $140.00 $2,800.00

Engineer's Estimate 20 HOUR $280.00 $5,600.00

7 out of 9

Project No: WY FLAP JOH 14(1)

Project Name: North Fork Crazy Woman Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0700 62301-0000 GENERAL LABOR

Battle Ridge Builders LLC $80.00 $4,000.00 MC2 Engineering and Construction, PC $84.35 $4,217.50 TCA Group Inc. $85.00 $4,250.00

HARRISON WESTERN CONSTRUCTION CORPO $90.00 $4,500.00

Engineer's Estimate 50 HOUR $100.00 $5,000.00

A0720 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Battle Ridge Builders LLC $125.00 $1,250.00 MC2 Engineering and Construction, PC $108.45 $1,084.50 TCA Group Inc. $205.00 $2,050.00

HARRISON WESTERN CONSTRUCTION CORPO $320.00 $3,200.00

Engineer's Estimate 10 HOUR $250.00 $2,500.00

A0740 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Battle Ridge Builders LLC $165.00 $3,300.00 MC2 Engineering and Construction, PC $331.38 $6,627.60 TCA Group Inc. $230.00 $4,600.00

HARRISON WESTERN CONSTRUCTION CORPO $250.00 $5,000.00

Engineer's Estimate 20 HOUR $250.00 $5,000.00

A0760 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGIST)

Battle Ridge Builders LLC Lump Sum $5,000.00 MC2 Engineering and Construction, PC Lump Sum $10,242.50 TCA Group Inc. Lump Sum $3,625.00 HARRISON WESTERN CONSTRUCTION CORPO Lump Sum $4,550.00 Engineer's Estimate ALL LPSM Lump Sum $6,000.00

A0780 62405-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH

Battle Ridge Builders LLC $45.00 $6,075.00 MC2 Engineering and Construction, PC $60.25 $8,133.75 TCA Group Inc. $45.00 $6,075.00

HARRISON WESTERN CONSTRUCTION CORPO $74.00 $9,990.00

Engineer's Estimate 135 SQYD $40.00 $5,400.00

A0800 62511-1000 SEEDING, DRY METHOD

Battle Ridge Builders LLC $18.00 $5,310.00 MC2 Engineering and Construction, PC $37.31 $11,006.45 TCA Group Inc. $30.00 $8,850.00

HARRISON WESTERN CONSTRUCTION CORPO $23.00 $6,785.00

Engineer's Estimate 295 SQYD $6.00 $1,770.00

8 out of 9

Project No: WY FLAP JOH 14(1)

Project Name: North Fork Crazy Woman Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0820 62516-1000 MULCHING, DRY METHOD

Battle Ridge Builders LLC $12.00 $3,540.00 MC2 Engineering and Construction, PC $46.16 $13,617.20 TCA Group Inc. $25.00 $7,375.00

HARRISON WESTERN CONSTRUCTION CORPO $23.00 $6,785.00

Engineer's Estimate 295 SQYD $4.75 $1,401.25

A0840 63301-0000 SIGN SYSTEM

Battle Ridge Builders LLC $1,400.00 $1,400.00 MC2 Engineering and Construction, PC $32,182.29 $32,182.29 TCA Group Inc. $6,000.00 $6,000.00

HARRISON WESTERN CONSTRUCTION CORPO $2,700.00 $2,700.00

Engineer's Estimate 1 EACH $1,300.00 $1,300.00

A0860 63308-3000 OBJECT MARKER, TYPE 3

Battle Ridge Builders LLC $350.00 $1,400.00 MC2 Engineering and Construction, PC $2,147.51 $8,590.04 TCA Group Inc. $2,000.00 $8,000.00

HARRISON WESTERN CONSTRUCTION CORPO $740.00 $2,960.00

Engineer's Estimate 4 EACH $420.00 $1,680.00

A0880 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE

Battle Ridge Builders LLC $5.00 $650.00 MC2 Engineering and Construction, PC $140.52 $18,267.60 TCA Group Inc. $15.00 $1,950.00

HARRISON WESTERN CONSTRUCTION CORPO $17.00 $2,210.00

Engineer's Estimate 130 LNFT $17.00 $2,210.00

A0900 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Battle Ridge Builders LLC $60.00 $8,400.00 MC2 Engineering and Construction, PC $125.51 $17,571.40 TCA Group Inc. $150.00 $21,000.00

HARRISON WESTERN CONSTRUCTION CORPO $250.00 $35,000.00

Engineer's Estimate 140 SQFT $120.00 $16,800.00

A0920 63701-0000 FIELD OFFICE

Battle Ridge Builders LLC $8,000.00 $8,000.00 MC2 Engineering and Construction, PC $29,589.04 $29,589.04 TCA Group Inc. $16,000.00 $16,000.00

HARRISON WESTERN CONSTRUCTION CORPO $182,000.00 $182,000.00

Engineer's Estimate 1 EACH $35,000.00 $35,000.00

9 out of 9

Project No: WY FLAP JOH 14(1)

Project Name: North Fork Crazy Woman Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Total Schedule - All Items

Battle Ridge Builders LLC $1,085,125.00 MC2 Engineering and Construction, PC $1,393,023.96 TCA Group Inc. $1,444,110.00

HARRISON WESTERN CONSTRUCTION CORPO $1,999,220.00

Engineer's Estimate $1,370,000.00

File details come from the government source that posted it. Updated .