This document appears to be a Questions and Answers (Q&A) document related to a federal contract opportunity for the WY FLAP JOH 14(1) North Fork Crazy Woman Creek Bridge project.
The key details are as follows: The project involves the replacement of an existing bridge structure on Crazy Woman Canyon Road/Route 33 in Johnson County, Wyoming. The new single-span prefabricated bridge will be 14 feet wide and 51 feet long, with rolled girders, structural steel decking, and a gravel deck surface. New concrete abutments and wingwalls supported by micropile foundations will be constructed, and no additional scour protection is required. The existing bridge is load-rated for 2-3 Axles: 11T, 4-5 Axles: 12T, 6+ Axles: 13T, Semi-Truck: 20T, and Tandem: 21T. The Q&A document clarifies that weathering steel should be used for the thrie-beam bridge railing, not galvanized guardrail as previously specified. The project is being managed by the Central Federal Lands Highway Division (CFLHD) of the Federal Highway Administration (FHWA), in cooperation with the U.S. Forest Service (USFS) and Johnson County, Wyoming.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for WY FLAP JOH 14(1) North Fork Crazy Woman Creek Bridge
August 30, 2024
Questions Answers 1 Ref. Sheet S9 Typical Section; At the Typical Section, the thrie-beam bridge railing is called-out as weathering steel. Special Provision article 555.03A(e) specifies galvanized guardrail. Please clarify.
Use weathering steel for the thrie-beam bridge railing. Please refer to Amendment A001.