UT ERFO 70014(2)_Pre-Bid Meeting Presentation.pdf
PDF 7 MB Posted
- Attached to
- UT ERFO 70014(2) Santaquin Canyon Road
- Solicitation number
- 6982AF23B000001
About this file
This presentation outlines details for a federal construction contract to repair flood damage on Santaquin Canyon Road in Utah. The project scope includes embankment construction, retaining wall construction, concrete box culvert installation, aggregate placement, and asphalt paving across seven sites. Construction is anticipated to begin in early July 2023 and be complete by July 2024, with a winter shutdown from December 2023 to May 2024. The contract has a total estimated cost range of $5-10 million and incorporates principal work items such as mechanically stabilized earth walls, roadway aggregate, asphalt, and reinforced concrete box culverts. Questions regarding the solicitation are due by June 7th and bids will open on June 14th, with the intent to award both the initial schedule and option year completion dates.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UT ERFO 70014(2)
Santaquin Canyon Road
Pre-Bid Meeting May 30, 2023
Presentation Outline
• Project Partners
• Project Introduction
• Project Photo Log
• Project Scope Details
• Contract Requirements & Solicitation Notes
• Questions
• Retaining Wall Design
Project Partners
Design Engineer;
Construction Contract
Administration
Owner
Roles & Responsibilities
Project Introduction Project Location
Project Introduction Project Location – Sites within 2.0 mile portion of road
Project Photo Log Site 2 – Guardrail, Aggregate, Paving
Site 3 – Retaining Wall, Guardrail, Aggregate, Paving
Site 3A - Retaining Wall, Guardrail, Aggregate, Paving
Site 4 – Box Culvert (17’ x 8’), Aggregate, Paving
Site 4A – Rock Embankment, Aggregate, Paving
Site 5 – Box Culvert (12’ x 4’), Riprap, Aggregate, Paving
Site 5 – Box Culvert (12’ x 4’), Riprap, Aggregate, Paving
Site 5A – Retaining Wall, Guardrail, Aggregate, Paving
Site 6 - Box Culvert (15’ x 8’), Aggregate, Paving
Site 6A – Special Rock Embankment
Site 7 – Rock Embankment, Aggregate, Paving, Plantings
Site 7A - Box Culvert (14’ x 8’), Aggregate, Paving
Project Scope Details
Contract Requirements
• Comply with 401, 404, and Stream Alteration Permit
• Contractor Developed SWPPP and erosion control measures
• Vegetation Clearing (little to none anticipated) and Migratory Birds
Impacts – Nest Survey
• Best Management Practices
• Schedule A Contract Completion Date of November 30, 2023
• Option X Contract Completion Date of October 11, 2024
• Winter Shutdown Anticipated between December 1, 2023 and May 15, Solicitation Notes
• Full and Open Advertisement
• Intent is to award both Schedule A and Option X
• Bid opening scheduled for June 14, 2023 at 2:00pm MDT.
• Submit all questions in writing to CFLContracts@dot.gov. Deadline for submitting technical questions is June 7, 2023 at 4:00pm MDT.
mailto:CFLContracts@dot.gov
Questions
Thank you for your interest in this project
Retaining Wall Design
Retaining Wall SCRs
• Section 254 – Precast Concrete Block Retaining Walls
• Use of gravity wall systems preferred
• If wall heights preclude use of gravity system, use MSE wall system with concrete block facing units, per Sections 255 and 257
• Intent is for expeditious and economical design and block fabrication
(utilization of “stock” concrete blocks)
• Wall Design
• Use established LRFD procedures for internal and external stability
• Wall Submittal – based on recent ground survey
• Design Calculations
• Wall Details and Drawings
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
| Slide Number 16 |
| Slide Number 17 |
| Slide Number 18 |
| Slide Number 19 |
| Slide Number 20 |
| Slide Number 21 |
| Slide Number 22 |
| Slide Number 23 |
| Slide Number 24 |
| Slide Number 25 |
File details come from the government source that posted it. Updated .