UT ERFO 70014(2)_Pre-Bid Meeting Presentation.pdf

PDF 7 MB Posted

Attached to
UT ERFO 70014(2) Santaquin Canyon Road
Solicitation number
6982AF23B000001
Issued by

About this file

This presentation outlines details for a federal construction contract to repair flood damage on Santaquin Canyon Road in Utah. The project scope includes embankment construction, retaining wall construction, concrete box culvert installation, aggregate placement, and asphalt paving across seven sites. Construction is anticipated to begin in early July 2023 and be complete by July 2024, with a winter shutdown from December 2023 to May 2024. The contract has a total estimated cost range of $5-10 million and incorporates principal work items such as mechanically stabilized earth walls, roadway aggregate, asphalt, and reinforced concrete box culverts. Questions regarding the solicitation are due by June 7th and bids will open on June 14th, with the intent to award both the initial schedule and option year completion dates.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UT ERFO 70014(2)

Santaquin Canyon Road

Pre-Bid Meeting May 30, 2023

Presentation Outline

• Project Partners

• Project Introduction

• Project Photo Log

• Project Scope Details

• Contract Requirements & Solicitation Notes

• Questions

• Retaining Wall Design

Project Partners

Design Engineer;

Construction Contract

Administration

Owner

Roles & Responsibilities

Project Introduction Project Location

Project Introduction Project Location – Sites within 2.0 mile portion of road

Project Photo Log Site 2 – Guardrail, Aggregate, Paving

Site 3 – Retaining Wall, Guardrail, Aggregate, Paving

Site 3A - Retaining Wall, Guardrail, Aggregate, Paving

Site 4 – Box Culvert (17’ x 8’), Aggregate, Paving

Site 4A – Rock Embankment, Aggregate, Paving

Site 5 – Box Culvert (12’ x 4’), Riprap, Aggregate, Paving

Site 5 – Box Culvert (12’ x 4’), Riprap, Aggregate, Paving

Site 5A – Retaining Wall, Guardrail, Aggregate, Paving

Site 6 - Box Culvert (15’ x 8’), Aggregate, Paving

Site 6A – Special Rock Embankment

Site 7 – Rock Embankment, Aggregate, Paving, Plantings

Site 7A - Box Culvert (14’ x 8’), Aggregate, Paving

Project Scope Details

Contract Requirements

• Comply with 401, 404, and Stream Alteration Permit

• Contractor Developed SWPPP and erosion control measures

• Vegetation Clearing (little to none anticipated) and Migratory Birds

Impacts – Nest Survey

• Best Management Practices

• Schedule A Contract Completion Date of November 30, 2023

• Option X Contract Completion Date of October 11, 2024

• Winter Shutdown Anticipated between December 1, 2023 and May 15, Solicitation Notes

• Full and Open Advertisement

• Intent is to award both Schedule A and Option X

• Bid opening scheduled for June 14, 2023 at 2:00pm MDT.

• Submit all questions in writing to CFLContracts@dot.gov. Deadline for submitting technical questions is June 7, 2023 at 4:00pm MDT.

mailto:CFLContracts@dot.gov

Questions

Thank you for your interest in this project

Retaining Wall Design

Retaining Wall SCRs

• Section 254 – Precast Concrete Block Retaining Walls

• Use of gravity wall systems preferred

• If wall heights preclude use of gravity system, use MSE wall system with concrete block facing units, per Sections 255 and 257

• Intent is for expeditious and economical design and block fabrication

(utilization of “stock” concrete blocks)

• Wall Design

• Use established LRFD procedures for internal and external stability

• Wall Submittal – based on recent ground survey

• Design Calculations

• Wall Details and Drawings

Slide Number 1
Slide Number 2
Slide Number 3
Slide Number 4
Slide Number 5
Slide Number 6
Slide Number 7
Slide Number 8
Slide Number 9
Slide Number 10
Slide Number 11
Slide Number 12
Slide Number 13
Slide Number 14
Slide Number 15
Slide Number 16
Slide Number 17
Slide Number 18
Slide Number 19
Slide Number 20
Slide Number 21
Slide Number 22
Slide Number 23
Slide Number 24
Slide Number 25

File details come from the government source that posted it. Updated .