This document contains the questions and answers from a pre-bid meeting for a federal construction contract. The contract will provide repairs to damaged sites along the Santaquin Canyon Road within the Uinta-Wasatch-Cache National Forest in Utah. Repairs include embankment construction, retaining wall construction using mechanically stabilized earth and reinforced concrete box culverts, aggregate placement, and asphalt paving. The work must be completed between early July 2023 and October 2024 to restore safe passage. Eligible offerors include large businesses that can submit a small business subcontracting plan if awarded the contract. The solicitation is estimated to cost between $5-10 million and is being issued by the Department of Transportation Federal Highway Administration.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5/30/2023

UT ERFO 70014(2) Santaquin Canyon Road Pre-Bid Teams Meeting Questions & Answers (Q&A)

Question Answer

1. What are the Small Business Requirements?

This procurement is Full and Open. Large Business concerns will be required to submit a Small Business Subcontracting Plan if they are the apparent low bidder. See Appendix C of the Solicitation for the Sample Small Business Subcontracting Plan.

2. Is the road/area open to the public?

The area and road are open to the Trumboldt Picnic Area, which is between Sites 2 and 3. Upstream of the Trumboldt Picnic Area, the road and area is closed by Forest Service Order and will remain closed through construction. There is no administrative access requirement for Forest Service vehicles upstream of the Trumboldt Picnic Area. Essentially, the contractor will be working behind a closed gate.

3. Are there any cultural clearances?

There are no cultural resources impacted by this project.

4. Have you looked into supply times for the culverts?

Concrete box culvert lead times may be significant due to the size of the proposed structures. It is expected that fabrication will occur over the upcoming fall and winter, in preparation for placement during the 2024 construction season.

5. Is the intent for retaining walls to match the previously constructed retaining wall in the canyon.

Yes, the walls need to be similar texture and color to the existing wall.

6. Is salt used to deice the road? No salt is used; the area is closed in the winter.

7. Will local concrete mix design be accepted for the retaining wall blocks?

Yes, locally used concrete mix designs will be evaluated and accepted for the retaining wall blocks.

8. Have you reviewed fabrication lead times for retaining walls.

The Government will rely on the contractor to offer the most economical and streamlined design.

Contractors are expected to take fabrication lead time into consideration and use off the shelf items as much as possible.

9. Will the Government fast track the submittal approvals.

Expect 3 to 5 days turnaround.

10. Have fabrication lead times been accounted for in development of contract completion dates.

Yes, estimated lead times for fabrication of site-specific materials have been included in the construction schedule developed during design.

5/30/2023

11. Can portions of the retaining wall at Site 3 with a shorter height be designed as a gravity wall, instead of using MSE wall for the entire length of the wall?

Yes, portions of retaining walls that meet the design criteria for internal stability as gravity structures, can be designed as such. In this case, shorter portions of a wall can be designed as a gravity wall system, while taller portions of the same wall can be designed as a MSE wall system.

12. Is final engineering of the retaining walls to be based on the contractor’s survey of the wall sites, as well as the contractor’s investigation into the depth of intact bedrock? Any estimates by the contractor regarding the needed retaining wall square footage, block sizes, geogrid quantities, etc. will just be estimates at this point?

Final engineering of the retaining walls will be based on the contractor’s survey of wall sites, to confirm the most accurate representation of the site and necessary wall quantity to repair the site. The final pay quantity for retaining walls will be adjusted to match the as-constructed pay quantity. The depth to intact bedrock is not expected to affect the final engineering of the retaining walls. The depth of grouted riprap curtainwalls may be reduced if intact bedrock is encountered in excavation of the curtainwall trench.

13. Can we assume the submittals (concrete blocks, geogrid, etc.)

can be approved by the engineer who provided the design?

The retaining wall will be evaluated as a system. The wall system will be approved, provided the system meets minimum requirements for internal wall stability, using standard design methodologies.

14. Can you clarify the actual contract completion date?

The Government intends to award both Schedule A and Option X, which will extend the contact completion date to October 11, 2024.