QnA 11-4-21.pdf
PDF 90 KB Posted
- Attached to
- AZ FLAP SR88(1) Apache Trail Federal contract opportunity
- Solicitation number
- 6982AF21B000027
About this file
This document provides details for a federal contract opportunity to repair and resurface approximately 11 miles of Arizona State Route 88 between Roosevelt Dam and Apache Lake Marina in Maricopa County, Arizona. The scope of work includes roadway excavation, riprap, chip sealing, asphalt paving, concrete work, pipe culverts, reinforced concrete box culverts, drainage repairs, erosion control, and revegetation. The project aims to provide a hardened driving surface along the route and improve sight distance at select locations. It was advertised in late October with bid opening anticipated in early December and award by late December. Construction is scheduled from winter 2022 through fall 2022. The estimated cost range for the project is between $12-16 million. The opportunity is funded by the Federal Highway Administration and administered by the Arizona Department of Transportation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Opening Summary Apache.pdf | ||
| QnA AZ FLAP SR 88(1) Apache Trail 11.23.21.pdf | ||
| 11-17-21 Q and A SI and A Sheet Str 00031 Pine Creek Bridge SR88.pdf | ||
| Amendment A001 Page A-1 AZ FLAP SR88(1) Apache Trail .pdf | ||
| Amendment A001.pdf | ||
| AZ_SR88(1)_Apache Trail_Final Hydraulics Report.pdf | ||
| AZ FLAP SR88(1) Apache Trail - Final Plans-Updated.pdf | ||
| FP-14_Eng.pdf | ||
| Road Cut Excavation Recommendations Apache Trail AZ FLAP SR88(1).pdf | ||
| AZ FLAP SR88(1) Final Pavement Recommendations.pdf | ||
| AZ FLAP SR88(1) Apache Trail IFB.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for AZ FLAP SR88(1) Apache Trail
November 4, 2021
Questions Answers 1 Who will be the Construction Operations Engineer? To be determined.
2 Who will be the Project Engineer? To be determined.
3 Are there cross-sections available? No. Cross-sections were not developed for this project.
4 Please provide an Earthwork Summary (including embankment). Refer to excavation summary on plan sheet B8. Embankment is not a pay item for this project.