1703883 QNA ARSR Specifications Combined Repair Building Morales TX 2026 Sept 22.pdf
PDF 5 MB Posted
- Solicitation number
- 6973GH-27-R-00042
About this file
This file is a Questions and Answers (Q&A) document related to specifications and repair requirements for the Morales, Texas ARSR facility.
The document addresses the Air Force Radar Site Replacement (ARSR) repair project (JCN 1703883) located approximately 12 miles south of Hallettsville, Texas (coordinates 29.341420, -96.871910). The project scope involves repair and replacement of building and exterior items to correct water damage and prevent water intrusion at the facility. The Q&A format indicates this document contains clarifications on the technical specifications and construction requirements that contractors must follow, though specific questions and answers are not detailed in the provided reference materials. Contractors are required to provide all plant, labor, materials, and equipment necessary to fully comply with the Summary of Work, Construction Specifications, Construction Drawings, and all other contract documents. This procurement is issued by the Department of Transportation Federal Aviation Administration through Franchise Acquisition Services under solicitation number 6973GH-27-R-00042.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOR OFFICIAL USE ONLY
Property of the United States Government
Copying, Dissemination or Distribution of These Documents to Unauthorized Personnel is Prohibited
Public availability to be determined under 5 USC 552
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION
CENTRAL SERVICE AREA
ENGINEERING SERVICES AJW-2C18D
FORT WORTH, TEXAS
PROJECT SPECIFICATIONS FOR
Repair/Replace Building and Exterior Items to Correct Water Damage, Prevent Water Intrusion
JCN 1703883
QNA ARSR
Morales, TX
Coordinates:
29°20'28.71"N, 96°52'19.69"W
Or 29.341420, -96.871910
Site 12 miles South of Hallettsville, TX
2nd Gate on left pass bridge off of CR-12
September 22, 2026
JCN 1703883 Repair Building & Exterior Items to Correct Water Damage, Prevent Water Intrusion, Morales TX
FOR OFFICIAL USE ONLY
Property of the United States Government
Copying, Dissemination or Distribution of These Documents to Unauthorized Personnel is Prohibited
Public availability to be determined under 5 USC 552
THIS PAGE INTENTIONALLY LEFT BLANK
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
INTRODUCTION 00 01 00 -1
SECTION 00 01 00
INTRODUCTION
The Following specifications and advisements constitute the working portion of the contract between the contractor and the Federal Aviation Administration, an Agency of the United States Government.
The Contracting Officer assigned to this contract shall be the only individual with authority to speak for and contractually bind the FAA. All communications, authorizations, approvals, changes, modifications, etc., involving this contract shall be through the Contracting Officer. Any action not approved by the Contracting Officer shall not bind the FAA.
END OF SECTION
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
TABLE OF CONTENTS 00 02 00 - 1
SECTION 00 02 00
TABLE OF CONTENTS
DIVISION
NUMBER SECTION NAME
00 00 00 COVERSHEET
00 01 00 INTRODUCTION
00 02 00 TABLE OF CONTENTS
DIVISION 1 – GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 12 00 PHOTOGRAPHS OF WORK EXAMPLES
01 14 16 OCCUPANCY
01 31 00 PROJECT MANAGEMENT & COORDINATION
01 32 00 CONSTRUCTION PROJECT DOCUMENTATION
01 33 00 SUBMITTAL PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 45 00 QUALITY CONTROL
01 56 00 DUST CONTROL
01 63 00 SUBSTITUTION AND PRODUCT OPTIONS
01 63 50 MATERIAL SHIPMENTS
01 71 00 CLEANING
01 73 00 EXECUTION
01 77 00 CLOSEOUT PROCEDURES
01 78 10 PROJECT RECORD DOCUMENTS
01 78 20 OPERATION & MAINTENANCE DATA
DIVISION 2 – EXISTING CONDITIONS
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
TABLE OF CONTENTS 00 02 00 - 2
02 41 00 DEMOLITION
02 42 00 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
07 19 00 WATER REPELLENTS
07 92 00 JOINT SEALANTS
07 92 01 WEATHERPROOFING SEALANTS
DIVISION 8 – OPENINGS
08 71 00 DOOR HARDWARE
DIVISION 9 – FINISHES
09 21 16 GYPSUM BOARD ASSEMBLIES
09 29 00 GYPSUM BOARD
09 05 61 COMMON WORK RESULTS FOR FLOORING PREPARATION
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT TILE FLOORING
09 90 00 PAINTING AND COATINGS
09 91 13.42 MISCELLANEOUS EXTERIOR PAINTING
ATTACHMENTS
ATTACHMENT A PROJECT DRAWINGS
--End of Section--
JCN 1703883, QNA ARSR, Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SUMMARY OF WORK 0101 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Contractor shall provide all plant, labor, materials and equipment necessary to fully meet all requirements of this Summary of Work, Construction Specifications, Construction Drawings and all other Contract Documents related to and/or titled: JCN 1703883. QNA ARSR. Repair Building and Exterior Items, Correct Water Damage and Prevent Water Intrusion, Morales (Hallettsville)
TX.
B. This Section includes the following:
1. Work covered by the Contract Documents.
2. Use of premises.
3. Work restrictions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identification: JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX.
a. Project Location: about 12 miles south of Hallettsville TX.
b. Access road through 2nd gate on left pass bridge off CR-12.
c. Coordinates are 29°20'28.71"N, 96°52'19.69"W or 29.341420, -96.871910
2. FAA's Representative: FAA Resident Engineer/Contracting Officers Representative (RE/COR)
a. All work performed and all materials and equipment used are subject to approval by the “Contracting Officer and/or Resident Engineer/Contracting Officer’s Representative
(RE/COR)”.
B. Designers: Engineering Services, AJW-2C18D.
C. The Work includes (but not limited to):
Note: Where these specifications specify certain products, equivalent or better is acceptable per Section 01 63 00 provided product substitutions are approved by the Project Engineer and/or Contracting Officer. Please note that if other items herein the contract documents are not applicable, then they are for reference only.
1. Power wash the entire exterior of the building including CMU walls, doors, soffits, fascia, discolored concrete foundation next to the building, gable metal siding. Power washing a building, the recommended pressure typically ranges between 1,200 to 3,500 psi depending on the building material, with softer materials like stucco or vinyl siding requiring lower pressure (around 1,200 psi) and tougher materials like brick or concrete handling higher pressure (up to 2,500 psi) and structural steel (up to 3,500 psi).
JCN 1703883, QNA ARSR, Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SUMMARY OF WORK 0101 11 00 - 2
a. Clean exterior CMU walls, exposed foundation and concrete next to building by chemical, brush and rinse where they are discolored.
b. Power wash top and sides of metal cable trays and the steel supports. Protect the underside of the cable trays that may damage the cables.
2. Reseal the ARSR equipment building.
(See specification Sections 01 56 00, 07 92 00 and 09 21 16)
a. Remove all old dried, cracked or compromised sealant and replace with new for the entire building.
b. This includes inside and outside building vertical control joints, building to foundation joints, concrete door stoops, ductwork and pipe penetrations, soffit, siding and frieze board to wall joints and weatherhoods.
c. Clean out and reseal the building eight vertical wall control joints, outside CMU and inside 5/8” fire retardant plywood walls. Replace backer rods and reseal joints.
Sika WS-295 silicone sealant meets ASTM C920.
d. Move furniture, shelves, et cetera, temporarily to perform the interior floor wall and ceiling joint repairs and painting then return it to the initial location when the work is completed. Protect the items attached to the walls not to be painted and equipment that cannot be moved from paint drips and damage, e.g. conduits, remove receptacle and switch covers temporarily for painting, shield ARSR equipment, et cetera.
e. Plywood Sheathing. Where the interior walls are covered with 5/8” 4’ x 8’ fire retardant plywood sheets, strip and clean off all of the accessible joint compound taped plywood panel joints, cut about a 3/8” deep vee groove in joints where sheets meet. Fill the vee grooved joints with water based DAP 3 in 1 Premium
Wood Filler, Item no. 101513. Then sand for surface smooth for painting per item
6.a. below.
f. Gypsum Board Sheathing. Where the walls and suspended ceiling are gypsum board, clean off all the existing taped joints, cut about a 3/8” vee in joints where sheets meet. Fill the vee grooved joints with joint compound, cover joints with mesh tape (aka FIBA tape). Apply joint compound smoother out over the tape.
Then sand surface for painting per item 6.a. below.
g. Seal bottom of metal panels at the sill plates at the top of the perimeter CMU walls.
h. Add or replace damaged or missing exterior doors items: exterior moldings Door
Jamb Adhesive-Backed Fire/Smoke Silicon Gasketing around all 8 door frames;
Heavy Duty Aluminum Brush Door Sweep for thresholds flush mounted on each of the 8 door leaf’s. Products to meet grade 1 ANSI/BHMA A156 standards as applicable.
3. Apply blended water-based silane/siloxane water repellent.
(See specification Section 07 19 00).
JCN 1703883, QNA ARSR, Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SUMMARY OF WORK 0101 11 00 - 3
a. Apply two coats of water repellant per manufacturer directions to all surfaces of the exterior CMU block wall surfaces and exposed concrete foundation after they have been power washed, cleaned and dried properly. Protect adjacent surfaces and items from repellant drips and spray.
b. Use Foundation Armor SX5000 siloxane-silane blend.
4. Exterior Door Hardware and Cylinders.
(See specification Section 08 71 00).
a. Contractor shall include field verification of all existing exterior doors that are to remain and take note of hardware to be replaced. Replace existing door hardware with BHMA Grade 1 system that accepts a universal 7-pin removable and interchangeable core.
b. Provide new lever handles, hardware and replace lockset cylinders on exterior doors.
Provide new rim cylinders, mortise cylinders, SFIC cores, gasketing, door sweeps, thresholds.
c. Provide the appropriate keying system and coordinate it with RE/COR and SSCM unless instructed otherwise by Project Engineer/Contracting Officer.
d. Provide panic hardware on Emergency Generator Room and Equipment Room steel hollow metal exterior doors.
e. Only replace the exterior Equipment Room doors and frames with 14 gauge steel, label “B” fire rated doors that will comply with FAA 1600.69D 4-3-13, Perimeter
Doors and Door Locks requirements. The other existing exterior doors remain.
f. The main entrance double doors to the Equipment Room has a CDX-10 lock and a
Hoffman box. Contractor must include their bid cost to coordinate and pay for a
GSA-certified locksmith to remove it and reinstall it in the new door.
5. Acoustical ceiling tiles.
(See specification Sections 01 56 00 and 09 51 00).
a. Replace all damaged and mold/mildew stained acoustical ceiling tiles. Maintain the existing ceiling tile pattern of 24 by 48 inch tiles. Field verify the number to be replaced prior to ordering and provide 6 extra tiles to the COR for the SSC future use.
b. Provide any additional suspended ceiling tile framing or wires to support the ceiling as needed.
c. Contain dust to protect ARSR equipment, shield the equipment, do not cover to prevent any equipment overheating damage.
6. Vinyl flooring tiles and base.
(See specification Section 09 65 00).
a. Replace all vinyl composition tiles (VCT) floor tiles and bases with new Contractor Furnished Material (CFM) floor tiles except for those areas specifically covered by the
JCN 1703883, QNA ARSR, Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SUMMARY OF WORK 0101 11 00 - 4
equipment. Provide Armstrong - Standard Excelon Imperial texture, 1/8” Fortress White 12" x12" SKU: 51839 (45 sf/box) or Contracting Officer approved equivalent or better. Cut the existing tiles along the edges next to where the equipment that remains in place meets the tile flooring. Maintain the tile floor 12” x 12” grid layout pattern and run the tile texture pattern all in the same direction, not checkerboarded.
b. Move furniture to perform the new flooring installation and return it to the initial location when the work is completed. Provide enough storage boxes (aka Conex boxes) for temporary storage of furniture, shelving, et cetera on site to execute the project work until all stored items are returned to their initial locations inside of the building.
c. Replace all 4” resilient base where new VCT are installed except where equipment cannot be moved for access. Replace all 4” resilient base elsewhere in the building where it is accessible. Field verify quantity required prior to ordering materials.
d. Remove debris beforehand. Sweep from corners to the center of the rooms or vacuum. Wet mop the new VCT flooring applying cleaning solution per manufacturer’s instructions using only the amount needed. Rinse well to avoid sticky floors. When VCT flooring is dry, apply floor wax and buff.
e. Clean all of the building floors thoroughly prior to final inspection.
7. Prepare surfaces as required and repaint, prime, and two coats.
(See specification Section 09 90 00).
a. Reference notes 2.d. And 2.e. above: for all interior plywood and gypsum board walls and ceilings, and interior CMU walls, prime and paint with two coats of interior white latex paint. Protect all wall attached items and equipment that is not to be painted, e.g. conduits, remove receptacle and switch covers temporarily for painting, shield ARSR equipment, et cetera.
b. Paint the existing metal gable siding, roof edges and vertical face of metal roof overhang matching existing color.
c. Paint soffit and metal siding above the top of exterior building CMU walls with paint matching existing color.
d. Paint all exterior single and double doors and frames inside and outside matching existing colors.
e. Following power washing of cable trays, reattach the underside loose cover.
Galvanized cable trays from equipment building to tower and the structural supports and similar adjacent items shall be abraded, sand medium, clean, non-greasy, and uncontaminated from salt and other chemicals for paint coats to adhere better. Apply 3 coats of Rust Grip® per Section 0991 13.42 Miscellaneous Exterior Paint. Second and third coat must be applied before Rust Grip® first coat has fully cured to avoid adhesion issues. The surface must also be dry during application. Protect adjacent surfaces from the spray and dripping. Follow manufacturer instructions.
8. Gables, exhaust fans and weatherhoods.
JCN 1703883, QNA ARSR, Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SUMMARY OF WORK 0101 11 00 - 5
a. Replace the two existing gable attic louver exhaust fans, controls, and provide grounding in accordance with FAA-STD-19G. After fan and control installation, test for functionality. Reference Sections D/A002, E/A002 and 3/A006 Wall Mounted Fan. The as-built drawings indicate the two attic existing exhaust fans are Greenheck Sidewall Propeller Exhaust Fans, Product #SE1-16-428-A5X-QD, 1666- 3373 CFM. Field verify prior to ordering the new ones and verify with the manufacturer’s representative the related items ordered are all compatible.
Existing wiring can be used for the new fan/control installation if not damaged or deteriorated.
b. Fan speed control: -40°F to 140°F, 0 psi to 754 psi, 208/240v ac, 8A output, 3R, item 40G352 mfr. Model P266ACA-100C, Johnson controls, and associated electrical wiring. Set the temperature controls to turn exhaust fans on when attic space is above 90 degrees F and turn off when the attic space is below 90 degrees F.
c. Provide and install Greenheck wall housing for the two new 16 inch sidewall propeller fans , product #H-16 for the two gable exhaust fans to be replaced.
d. Add and install 2 new weatherhoods, Greenheck weatherhood kits for the 16 inch sidewall propeller fan louvers, with 90 degree turn-down. Field verify the right size prior to ordering, two #WTHD-16-90 and one #WTHD-18-90. Weatherhoods are galvanized steel with wire mesh birdscreen.
e. Provide and install Greenheck weatherhood kit for the 18 by 18 inch gable louver, 90 degree turn-down, product #WTHD-18-90. Weatherhoods are galvanized steel with wire mesh birdscreen. Field verify the right size prior to ordering.
f. Replace round wall fan UPS Room wall in kind. Verify if it is a Greenheck P/N: CW- 099A Exhaust Fan. Reference: 099-CUE/099-CW Series Direct Drive Greenheck Exhaust Fan, sidewall mounted. Field verify the exact make and model prior to ordering. Seal all around the new exhaust fan exterior CMU wall penetration.
9. Prepare surfaces, sand medium and clean for primer to adhere better. Paint all existing steel pipe bollards with primer and two coats of exterior yellow paint. Provide new yellow, high density polyethylene, ¼ inch heavy duty bollard covers with 2 red 3/4” reflective stripes by Bollards and Sleeves, LLC over each bollard. Field verify bollards are 6” pipe posts, height and the number required, about 24, prior to ordering bollard covers.
10. Provide and maintain a portable toilet on site for the duration for as long as the construction personnel are on site.
11. Provide specified manufacturer and contractor warranties.
D. Drawing Convention – All drawings dimensions, equipment, utility piping/cabling, and location presented on the drawing are for informational purposes only and must be field verified by the Contractor.
JCN 1703883, QNA ARSR, Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SUMMARY OF WORK 0101 11 00 - 6
E. Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work, but shall be performed as if fully and correctly set forth and described in the drawings and specifications.
F. Where conflicts between the drawings and specifications occur, specifications shall govern in accordance with FAR 52.236-21.
1.3 PROTECTION:
A. Upon beginning work on the existing facility, Contractor shall protect existing buildings, equipment, pavement, sidewalks, fencing, gates, and landscaping as required.
B. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
C. Repair or replace portions of existing work, which have been altered during construction operations to match existing or adjoining work, as approved by the Project Engineer and/or Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
D. Contractor shall protect all Government property against damage, to include but not limited to dust, fumes, impact, scratching, water, paint, joint compound, power failure, power surges, weather, heavy equipment, et cetera. Especially protect sensitive equipment from dust or damage, see Section 01 56 00. All damages caused by the Contractor, whether to equipment, furniture, roads, landscaping, building components or any other type of Government property encountered at or near the project site shall be repaired or replaced to match existing to the satisfaction of the RE/COR at no cost to the Government.
1.4 USE OF PREMISES
A. General: Contractor shall have limited and restricted use of the premises for construction operations as indicated by RE/COR in coordination with facility operations personnel. Any potential impacts are to be brought to the attention of the RE/COR immediately.
1.5 OWNER'S OCCUPANCY REQUIREMENTS
A. Full FAA Access: FAA will access site and building during entire construction period. Cooperate with FAA during construction operations to minimize conflicts and facilitate FAA usage. Perform the Work so as not to interfere with FAA's day-to-day operations. Maintain existing exits, unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from FAA and authorities having jurisdiction.
2. Provide not less than 72 hours advance notice in writing to RE/COR of activities that will affect FAA's operations.
1.6 WORK RESTRICTIONS
JCN 1703883, QNA ARSR, Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SUMMARY OF WORK 0101 11 00 - 7
A. Contractor shall complete this project, including final clean-up of the premises and storage and equipment areas within the duration approved in the contract schedule. This shall include operational testing of new exhaust fans and controls systems.
B. Work Hours:
Regular Work Hours: Monday – Friday from 0700 – 1600 hours.
*SSC FAA employees with the required clearance to escort contractor workers in the Equipment Room with classified equipment may work four 10 hour days per week. The Contractor shall coordinate when SSC FAA escorts are available and may be limited to four days to perform work in secure areas.
Notify the RE/COR 48 hours in advance of any changes in work hours, shift changes, or anticipated overtime work.
C. Holiday Work Hours: The Contractor shall observe all federal holidays and weekends. No work shall be planned for these days unless approved in writing by the Contracting Officer.
D. No Work Moratoriums: There shall be no work done during the FAA Moratoriums unless a waiver has been granted. Coordinate with local SSC, RE/COR for dates/times of moratoriums.
E. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by FAA or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify the RE/COR 72 Hours prior to proposed utility interruptions or outage.
2. Do not proceed with utility interruptions without the RE/COR written permission.
1.7 SECURITY REQUIREMENTS
A. Site Access and Security:
1. Access to the site shall be determined by the RE/COR through coordination with SSC personnel and will be given to the Contractor at the Pre-Construction Meeting. The Contractor shall maintain the security integrity. SSC personnel with the required security clearance are required to escort the RE/COR and Contractor personnel for access inside of the ARSR building.
B. PERSONNEL LIST:
1. Contractor shall provide the facility FAA SSC and RE/COR with a list of contractor’s personnel who will require access to the site. The list shall be kept current during project work.
C. SECURITY INVESTIGATION:
JCN 1703883, QNA ARSR, Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SUMMARY OF WORK 0101 11 00 - 8
1. Contractor’s personnel may have a security investigation by the FAA. Upon request by the RE/COR, the contractor shall promptly complete all security forms provided the by RE/COR.
D. Weather Delay:
1. The Contractor shall obtain the approval of the RE/COR each day prior to beginning the next day’s work activity. The RE/COR may suspend all work activity in the event that outdoor weather conditions pose a threat of damage to the site work, the equipment or the building.
E. Construction Safety:
1. The Contractor is responsible for providing a safe work environment for all construction and inspection personal working on site. The Contractor shall follow all national, state, and local safety procedures mandated by FAA, OSHA, law, and local ordinance.
F. RIGHT TO SEARCH:
1. Current procedures at FAA facilities include the “right to search.” If in the judgment of the FAA, a reason to search a vehicle or person exists, such search will be made.
--END OF SECTION--
PHOTOGRAPHS OF WORK EXAMPLES - 1
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SECTION 0 12 00
SECTION 01 12 00
PHOTOGRAPHS OF WORK EXAMPLES
*NOTES AND PHOTOGRAPHS HEREIN INCLUDES WORK AND DETAILS THAT ARE PART OF THIS CONTRACT.
1. GABLE ROOF END WALL AT TELCO ROOM.
2. HVAC DUCTS OUTSIDE OF TELCO ROOM.
PREPARE METAL SURFACES AS REQUIRED.
REPAINT, PRIME, APPLY TWO COATS TO ALL METAL
GABLE SIDING, METAL ROOF EDGES, AND
VERTICAL FACE AND UNDERSIDE OF METAL ROOF
OVERHANGS, AND SOFFITS MATCHING EXISTING
EXTERIOR PAINT COLORS.
POWER WASH THE ENTIRE EXTERIOR OF THE
BUILDING INCLUDING GABLE METAL SIDING,
DISCOLORED CMU WALLS, CONCRETE
FOUNDATION.
APPLY TWO COATS OF BLENDED WATER-BASED
SILANE/SILOXANE WATER REPELLENT TO CMU
BLOCK WALLS AND ALL EXPOSED PERIMETER
CONCRETE BUILDING FOUNDATION.
PHOTOGRAPHS OF WORK EXAMPLES - 2
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
3. TELCOM FRONT DOOR.
TELCOM FRONT DOOR.
POWER WASH THE ENTIRE EXTERIOR OF THE
BUILDING INCLUDING CMU WALLS, CONCRETE
FOUNDATION, DISCOLORED CONCRETE DOOR
STOOPS, SIDEWALKS NEXT TO THE BUILDING.
APPLY TWO COATS OF BLENDED WATER-BASED
SILANE/SILOXANE WATER REPELLENT TO CMU
BLOCK WALLS AND ALL EXPOSED PERIMETER
CONCRETE BUILDING FOUNDATION.
POWER WASH THE ENTIRE EXTERIOR OF THE
BUILDING INCLUDING CMU WALLS, CONCRETE
FOUNDATION, DISCOLORED CONCRETE DOOR
STOOPS, SIDEWALKS NEXT TO THE BUILDING.
APPLY TWO COATS OF BLENDED WATER-BASED
SILANE/SILOXANE WATER REPELLENT TO CMU
CONCRETE BUILDING FOUNDATION.
PHOTOGRAPHS OF WORK EXAMPLES - 3
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
4. FRONT WALL. ATTENNA ON WALL.
5. EQUIPMENT ROOM FRONT DOOR.
BUILDING INCLUDING DISCOLORED CMU WALLS,
CONCRETE FOUNDATION, CONCRETE DOOR
STOOPS, SIDEWALKS NEXT TO THE BUILDING.
REMOVE AND REPLACE ALL EIGHT EXTERIOR
VERTICAL CMU WALL CONTROL JOINTS
MATERIALS COMPRISED OF BACKER ROD, AND
JOINT SEALANT.
APPLY TWO COATS OF BLENDED WATER-BASED
SILANE/SILOXANE WATER REPELLENT TO CMU
BLOCK WALLS AND ALL EXPOSED PERIMETER
CONCRETE BUILDING FOUNDATION.
REMOVE AND RESEAL ALL EXTERIOR JOINT
SEALANTS FOR METAL SIDING JOINTS, AROUND
LOUVERS, HVAC DUCTS, WEATHERHOODS, DOOR
AND WINDOW FRAMES TO RESEAL THE ENTIRE
BUILDING.
PHOTOGRAPHS OF WORK EXAMPLES - 4
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
6. EQUIPMENT ROOM FRONT DOOR.
6. UPS ROOM FRONT DOOR.
REMOVE AND REPLACE ALL EIGHT EXTERIOR
VERTICAL CMU WALL CONTROL JOINTS
MATERIALS COMPRISED OF BACKER ROD, AND
JOINT SEALANT.
POWER WASH THE ENTIRE EXTERIOR OF THE BUILDING
INCLUDING DISCOLORED CMU WALLS, CONCRETE
FOUNDATION, CONCRETE DOOR STOOPS, SIDEWALKS NEXT TO
THE BUILDING.
APPLY TWO COATS OF BLENDED WATER-BASED
SILANE/SILOXANE WATER REPELLENT TO CMU BLOCK WALLS
AND ALL EXPOSED PERIMETER CONCRETE BUILDING
FOUNDATION.
PAINT ALL EXTERIOR SINGLE AND DOUBLE DOORS AND
FRAMES INSIDE AND OUTSIDE MATCHING EXISTING COLORS.
REPLACE ALL DOOR HARDWARE WITH LEVER HANDLES ON
SINGLE AND DOUBLE DOORS. REPLACE ALL LOCKSET
CYLINDERS ON SINGLE AND DOUBLE DOORS. PROVIDE PANIC
HARDWARE ON EMERGENCY GENERATOR ROOM AND
EQUIPMENT ROOM DOORS.
PHOTOGRAPHS OF WORK EXAMPLES - 5
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
7. EMERGENCY GENERATOR (E/G) ROOM FRONT DOOR.
8. DOOR STOOP IN FRONT OF BUILDING.
8. GABLE END WALL OUTSIDE OF E/G ROOM
PROVIDE AND INSTALL GREENHECK
WEATHERHOOD KITS FOR THE TWO HERE GABLE
AND ONE ON THE OTHER GABLE SIDEWALL
LOUVERS, 90 DEGREE TURN-DOWN, PRODUCT
#WTHD-16-90 AND/OR #WTHD-18-90.
WEATHERHOODS ARE GALVANIZED STEEL WITH
WIRE MESH BIRDSCREEN. FIELD VERIFY THE
RIGHT SIZE PRIOR TO ORDERING. (TYPICAL)
REMOVE AND RESEAL ALL EXTERIOR JOINT
SEALANTS FOR METAL SIDING JOINTS, AROUND
LOUVERS, WEATHERHOODS, RESEAL THE ENTIRE
BUILDING. (TYPICAL)
c. PREPARE METAL SURFACES AS REQUIRED: SAND
MEDIUM, PRIME, REPAINT, APPLY TWO COATS TO
ALL METAL GABLE SIDING, METAL ROOF EDGES,
AND VERTICAL FACE AND UNDERSIDE OF METAL
ROOF OVERHANGS, AND SOFFITS MATCHING
EXISTING EXTERIOR PAINT COLORS. (TYPICAL)
POWER WASH THE ENTIRE EXTERIOR OF THE
BUILDING INCLUDING DISCOLORED CMU WALLS,
CONCRETE FOUNDATION, CONCRETE DOOR
STOOPS, SIDEWALKS NEXT TO THE BUILDING.
PAINT ALL EXTERIOR SINGLE AND DOUBLE DOORS
AND FRAMES INSIDE AND OUTSIDE MATCHING
EXISTING COLORS.
REPLACE ALL DOOR HARDWARE WITH LEVER
HANDLES ON SINGLE AND DOUBLE DOORS.
REPLACE ALL LOCKSET CYLINDERS ON SINGLE AND
DOUBLE DOORS. PROVIDE PANIC HARDWARE ON
EMERGENCY GENERATOR ROOM AND EQUIPMENT
ROOM DOORS.
PHOTOGRAPHS OF WORK EXAMPLES - 6
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
9. REAR WALL.
10. REAR WALL AT FAUCET.
11. REAR WALL.
BUILDING INCLUDING DISCOLORED CMU WALLS,
CONCRETE FOUNDATION. (TYPICAL)
REMOVE AND REPLACE ALL EIGHT EXTERIOR
VERTICAL CMU WALL CONTROL JOINTS
MATERIALS COMPRISED OF BACKER ROD, AND
JOINT SEALANT. (TYPICAL)
APPLY TWO COATS OF BLENDED WATER-BASED
SILANE/SILOXANE WATER REPELLENT TO CMU
BLOCK WALLS AND ALL EXPOSED PERIMETER
CONCRETE BUILDING FOUNDATION. (TYPICAL)
TYPICAL ITEMS EXTERIOR ITEMS TO WORK
AROUND AND PROTECT, ESPECIALLY WHEN
P0WER WASHING, PAINTING ROOF EDGES AND
SOFFITS, CABLE TRAYS, AND APPLYING CMU WALL
WEATHERPROOFING.
PHOTOGRAPHS OF WORK EXAMPLES - 7
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
12. REAR WALL.
13. REAR WALL. CMU CONTROL JOINT.
14. REAR WALL. EQUIPMENT ROOM BACK DOOR & CABLE TRAY
BUILDING INCLUDING EXTERIOR DISCOLORED
CMU WALLS, CONCRETE FOUNDATION, CONCRETE
DOOR STOOPS. (TYPICAL)
REMOVE AND REPLACE ALL EIGHT EXTERIOR
VERTICAL CMU WALL CONTROL JOINTS
MATERIALS COMPRISED OF BACKER ROD, AND
JOINT SEALANT. (TYPICAL)
APPLY TWO COATS OF BLENDED WATER-BASED
SILANE/SILOXANE WATER REPELLENT TO CMU
BLOCK WALLS AND ALL EXPOSED PERIMETER
CONCRETE BUILDING FOUNDATION. (TYPICAL)
POWER WASH THE TOP AND SIDES OF THE
GALVANIZED CABLE TRAYS AND FOUNDATIONAL
SUPPORT. AVOID DAMAGING THE CABLES IN
THE TRAY FROM THE BOTTOM WHEN POWER
WASHING. (TYPICAL)
SEE SECTION 01 11 00 SUMMARY OF WORK
1.2.C.1 FOR WASHING PRESURERS.
PREPARE METAL SURFACES FOR PAINTING: WIRE
BRUSH, SAND LIGHTLY, RINSE, AND WHEN DRY
APPLY THREE COATS OF RUST GRIP®. (TYPICAL)
POWER WASH THE ENTIRE EXTERIOR OF THE
BUILDING INCLUDING ROOD EDGES AND SOFFITS,
EXTERIOR DISCOLORED CMU WALLS, CONCRETE
FOUNDATION, CONCRETE DOOR STOOPS.
(TYPICAL)
REMOVE AND REPLACE ALL EIGHT EXTERIOR
VERTICAL CMU WALL CONTROL JOINTS
MATERIALS COMPRISED OF BACKER ROD, AND
JOINT SEALANT. (TYPICAL)
APPLY TWO COATS OF BLENDED WATER-BASED
SILANE/SILOXANE WATER REPELLENT TO CMU
CONCRETE BUILDING FOUNDATION. (TYPICAL)
PHOTOGRAPHS OF WORK EXAMPLES - 8
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
15. CABLE TRAY TO TOWER.
16. CABLE TRAY UNDERSIDE.
POWER WASH TOP AND SIDES OF THE
GALVANIZED CABLE TRAY AND FOUNDATIONAL
SUPPORT. AVOID DAMAGING THE CABLES IN
THE TRAY FROM THE BOTTOM WHEN POWER
WASHING. (TYPICAL)
APPLY THREE COATS OF RUST GRIP®. (TYPICAL)
AVOID DAMAGING THE CABLES IN THE TRAY
FROM THE BOTTOM WHEN POWER WASHING.
PREPARE METAL SURFACES FOR PAINTING: WIRE
APPLY THREE COATS OF RUST GRIP®. (TYPICAL)
PHOTOGRAPHS OF WORK EXAMPLES - 9
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
17. CABLE TRAY.
18. CABLE TRAY TO BUILDING.
POWER WASH TOP AND SIDES OF THE
GALVANIZED CABLE TRAY AND FOUNDATIONAL
SUPPORT. AVOID DAMAGING THE CABLES IN
APPLY THREE COATS OF RUST GRIP®. (TYPICAL)
POWER WASH TOP AND SIDES OF THE
GALVANIZED CABLE TRAY AND FOUNDATIONAL
SUPPORT. AVOID DAMAGING THE CABLES IN
APPLY THREE COATS OF RUST GRIP®. (TYPICAL)
PHOTOGRAPHS OF WORK EXAMPLES - 10
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
19. GABLE WALL CORNER OUTSIDE EQUIPMENT ROOM BY HVAC UNITS.
20. EQUIPMENT ROOM WALL.
REPAIR ALL WALL AND CEILING DAMAGED 5/8”
FIRE RETARDANT PLYWOOD WALL BOARDS.
DAMAGED INTERIOR 5/8” FIRE RETARDANT
PLYWOOD WALL AND CEILING JOINTS, FILL
WITH WOOD FILLER DAP 3 IN 1 PREMIUM
WOOD FILLER AND SAND TO SMOOTH THE
FINISH SURFACE. (TYPICAL)
REPAINT ALL 5/8” FIRE RETARDANT PLYWOOD
WALLS AND CEILINGS WITH PRIMER AND TWO
COATS OF INTERIOR WHITE LATEX PAINT.
(TYPICAL)
PROVIDE AND INSTALL GREENHECK
WEATHERHOOD KITS FOR THE ONE HERE GABLE
AND TWO ON THE OTHER GABLE WALL LOUVERS,
90 DEGREE TURN-DOWN, PRODUCT #WTHD-16-
90 AND/OR #WTHD-18-90. WEATHERHOODS ARE
GALVANIZED STEEL WITH WIRE MESH
BIRDSCREEN. FIELD VERIFY THE RIGHT SIZE PRIOR
TO ORDERING.
REMOVE AND RESEAL ALL EXTERIOR JOINT
SEALANTS FOR METAL SIDING JOINTS AT TOP OF
CMU WALL, AROUND LOUVERS, HVAC DUCTS,
WEATHERHOODS, RESEAL THE ENTIRE BUILDING.
(TYPICAL)
c. PREPARE METAL SURFACES AS REQUIRED. REPAINT, PRIME PLUS APPLY TWO COATS OF EXTERIOR
PAINT TO ALL METAL GABLE SIDING, METAL ROOF
EDGES, AND VERTICAL FACE AND UNDERSIDE OF
METAL ROOF OVERHANGS, AND SOFFITS
MATCHING EXISTING EXTERIOR PAINT COLORS.
(TYPICAL)
PHOTOGRAPHS OF WORK EXAMPLES - 11
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
21. EQUIPMENT ROOM WALL & CEILING AT HVAC GABLE END.
22. EQUIPMENT ROOM ACOUSTIC TILE CEILING.
REPLACE ALL DAMAGED AND
MOLD/MILDEW STAINED ACOUSTICAL
CEILING TILES. MAINTAIN THE EXISTING
CEILING TILE PATTERN OF 24 BY 48-INCH
TILES. OTHER CEILING TILES REMAIN.
PROVIDE ANY ADDITIONAL SUSPENDED
CEILING TILE FRAMING OR WIRES TO
SUPPORT THE CEILING IF NEEDED.
CLEAN THE MOLD/MILDEW OFF THE
CEILING HVAC DUCT CEILING VENTS.
REPLACE ALL DAMAGED AND
MOLD/MILDEW STAINED ACOUSTICAL
CEILING TILES. MAINTAIN THE EXISTING
CEILING TILE PATTERN OF 24 BY 48-INCH
TILES. OTHER CEILING TILES REMAIN.
PROVIDE ANY ADDITIONAL SUSPENDED
CEILING TILE FRAMING OR WIRES TO
SUPPORT THE CEILING IF NEEDED.
CLEAN THE MOLD/MILDEW OFF THE
CEILING HVAC DUCT CEILING VENTS.
PHOTOGRAPHS OF WORK EXAMPLES - 12
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
23. EQUIPMENT ROOM ACOUSTIC TILE CEILING.
24. EQUIPMENT ROOM ACOUSTIC TILE CEILING AT VENT.
REPLACE ALL DAMAGED AND MOLD/MILDEW
STAINED ACOUSTICAL CEILING TILES. MAINTAIN
THE EXISTING CEILING TILE PATTERN OF 24 BY
48-INCH TILES. OTHER CEILING TILES REMAIN.
(TYPICAL)
PROVIDE ANY ADDITIONAL SUSPENDED CEILING
TILE FRAMING OR WIRES TO SUPPORT THE
CEILING IF NEEDED.
CLEAN THE MOLD/MILDEW OFF THE CEILING
HVAC DUCT CEILING VENTS. (TYPICAL)
PHOTOGRAPHS OF WORK EXAMPLES - 13
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
25. EQUIPMENT ROOM CEILING AND CABLE TRAYS.
26. TOILET.
REPLACE ALL BUILDING VINYL COMPOSITION
TILES (VCT) FLOOR TILES WITH NEW
GOVERNMENT FURNISHED MATERIAL (GFM)
FLOOR TILES EXCEPT FOR THOSE AREAS
SPECIFICALLY COVERED BY THE EQUIPMENT.
CUT THE EXISTING TILES ALONG THE EDGES
NEXT TO WHERE THE EQUIPMENT THAT
REMAINS IN PLACE MEETS THE TILE FLOORING.
MAINTAIN THE ROOM TILE FLOOR PATTERN.
(TYPICAL)
REPLACE ALL BUILDING 4” RESILIENT BASE
WHERE NEW VCT ARE INSTALLED EXCEPT
WHERE EQUIPMENT CANNOT BE MOVED FOR
ACCESS. REPLACE ALL 4” RESILIENT BASE
ELSEWHERE IN THE BUILDING WHERE IT IS
ACCESSIBLE. FIELD VERIFY QUANTITY
REQUIRED PRIOR TO ORDERING MATERIALS.
(TYPICAL)
REPLACE ALL DAMAGED AND MOLD/MILDEW
STAINED ACOUSTICAL CEILING TILES. MAINTAIN
THE EXISTING CEILING TILE PATTERN OF 24 BY
48-INCH TILES. OTHER CEILING TILES REMAIN.
(TYPICAL)
PROVIDE ANY ADDITIONAL SUSPENDED CEILING
TILE FRAMING OR WIRES TO SUPPORT THE
CEILING IF NEEDED.
CLEAN THE MOLD/MILDEW OFF THE CEILING
HVAC DUCT CEILING VENTS. (TYPICAL)
PHOTOGRAPHS OF WORK EXAMPLES - 14
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
27. EMERGENCY GENERATOR ROOM.
28. EMERGENCY GENERATOR ROOM.
29. EMERGENCY GENERATOR ROOM.
PROVIDE ENOUGH STORAGE BOXES (AKA
CONEX BOXES) FOR TEMPORARY STORAGE
OF FURNITURE, SHELVING, ET CETERA ON
SITE IN PERFORMANCE OF PROJECT WORK
UNTIL ALL STORED ITEMS ARE RETURNED
TO THEIR INITIAL LOCATIONS INSIDE OF
THE BUILDING.
TYPICAL ITEMS ATTACHED TO THE WALLS
AND CEILINGS TO WORK AROUND AND
PROTECT, ESPECIALLY WHEN PAINTING.
PHOTOGRAPHS OF WORK EXAMPLES - 15
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
30. EMERGENCY GENERATOR ROOM.
31. EMERGENCY GENERATOR ROOM.
AND CEILINGS TO WORK AROUND AND
PROTECT, ESPECIALLY WHEN PAINTING.
PROVIDE ENOUGH STORAGE BOXES (AKA
CONEX BOXES) FOR TEMPORARY STORAGE
OF FURNITURE, SHELVING, ET CETERA ON
SITE IN PERFORMANCE OF PROJECT WORK
UNTIL ALL STORED ITEMS ARE RETURNED
TO THEIR INITIAL LOCATIONS INSIDE OF THE
BUILDING
CLEAN ALL OF THE BUILDING FLOORS
THOROUGHLY PRIOR TO FINAL INSPECTION.
PHOTOGRAPHS OF WORK EXAMPLES - 16
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
32.
33. UPS ROOM.
TYPICAL ITEMS ATTACHED TO THE WALLS TO
WORK AROUND AND PROTECT, ESPECIALLY
WHEN PAINTING.
PROVIDE ENOUGH STORAGE BOXES (AKA
CONEX BOXES) FOR TEMPORARY STORAGE
OF FURNITURE, SHELVING, ET CETERA ON
SITE IN PERFORMANCE OF PROJECT WORK
UNTIL ALL STORED ITEMS ARE RETURNED TO
THEIR INITIAL LOCATIONS INSIDE OF THE
BUILDING.
TYPICAL ITEMS ATTACHED TO THE WALLS TO
WORK AROUND AND PROTECT, ESPECIALLY
WHEN PAINTING.
PROVIDE ENOUGH STORAGE BOXES (AKA
CONEX BOXES) FOR TEMPORARY STORAGE
OF FURNITURE, SHELVING, ET CETERA ON
SITE IN PERFORMANCE OF PROJECT WORK
UNTIL ALL STORED ITEMS ARE RETURNED TO
THEIR INITIAL LOCATIONS INSIDE OF THE
BUILDING.
PAINT ALL EXTERIOR SINGLE AND DOUBLE
DOORS AND FRAMES INSIDE AND OUTSIDE
MATCHING EXISTING COLORS.
REPLACE ALL DOOR HARDWARE WITH LEVER
HANDLES ON SINGLE AND DOUBLE DOORS.
REPLACE ALL LOCKSET CYLINDERS ON SINGLE
AND DOUBLE DOORS. PROVIDE PANIC
HARDWARE ON EMERGENCY GENERATOR
ROOM AND EQUIPMENT ROOM DOORS.
PHOTOGRAPHS OF WORK EXAMPLES - 17
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
34. UPS ROOM.
35. UPS ROOM.
36. UPS ROOM WALL.
TO WORK AROUND AND PROTECT,
ESPECIALLY WHEN PAINTING.
TYPICAL ITEMS ATTACHED TO THE WALLS TO
WORK AROUND AND PROTECT, ESPECIALLY
WHEN PAINTING.
PROVIDE ENOUGH STORAGE BOXES (AKA
CONEX BOXES) FOR TEMPORARY STORAGE
OF FURNITURE, SHELVING, ET CETERA ON
SITE IN PERFORMANCE OF PROJECT WORK
UNTIL ALL STORED ITEMS ARE RETURNED TO
THEIR INITIAL LOCATIONS INSIDE OF THE
BUILDING.
PHOTOGRAPHS OF WORK EXAMPLES - 18
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
37. UPS ROOM.
38. DUST CONTROL EXAMPLE.
PHOTOGRAPH FROM A SIMILAR PROJECT
AS AN EXAMPLE OF DUST CONTAINMENT
TO PROTECT THE ARSR EQUIPMENT.
THIS IS TO EMPHASIZE HOW IMPORTANT
DUST CONTROL IS TO AVOID DAMAGE TO
ARSR EQUIPMENT.
CONTRACTOR SHALL PROTECT ALL
GOVERNMENT PROPERTY AGAINST
DAMAGE, TO INCLUDE BUT NOT LIMITED
TO DUST, FUMES, IMPACT, SCRATCHING,
WATER, PAINT, JOINT COMPOUND, POWER
FAILURE, POWER SURGES, WEATHER,
HEAVY EQUIPMENT, ET CETERA.
ESPECIALLY PROTECT SENSITIVE
EQUIPMENT FROM DUST OR DAMAGE,
SEE SECTION 01 56 00.
PHOTOGRAPHS OF WORK EXAMPLES - 19
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
39. ATTIC EXHAUST FAN EXAMPLE.
40. BOLLARD EXAMPLE.
THIS PHOTO IS FROM ANOTHER SIMILAR
ARSR PROJECT TO REPRESENT THE ATTIC
FAN AND TEMPERATURE SENSOR TO BE
REPLACED.
REPLACE THE TWO EXISTING GABLE ATTIC
LOUVER EXHAUST FANS, WIRING,
CONTROLS, GROUNDING AND ENSURE THEY
WORK PROPERLY. SEE SUMMARY OF WORK
FOR DETAILS.
SET THE TEMPERATURE CONTROLS TO TURN
EXHAUST FANS ON WHEN ATTIC SPACE IS
ABOVE 90 DEGREES F AND TURN OFF WHEN
THE ATTIC SPACE IS BELOW 90 DEGREES F.
THIS PHOTO IS FROM ANOTHER SIMILAR ARSR PROJECT
TO REPRESENT MORALES ARSR EXISTING BOLLARDS.
PAINT ALL EXISTING STEEL PIPE BOLLARDS: SAND
MEDIUM, APPLY PRIMER AND TWO COATS OF EXTERIOR
YELLOW PAINT. (TYPICAL)
PROVIDE NEW YELLOW, HIGH DENSITY POLYETHYLENE,
¼ INCH HEAVY DUTY BOLLARD COVERS WITH 2 RED
3/4” REFLECTIVE STRIPES BY “BOLLARDS AND SLEEVES,
LLC” OVER ALL BOLLARDS. (TYPICAL)
FIELD VERIFY BOLLARDS ARE 6” STD PIPE POSTS,
HEIGHT, AND NUMBER (ABOUT 24) PRIOR TO
ORDERING BOLLARD COVERS.
OCCUPANCY 01 14 16 - 1
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SECTION 01 14 16
OCCUPANCY
PART 1 - GENERAL
1.01 OCCUPANCY
A. Facilities designated for work under this contract will be partially occupied during construction. The Equipment Room area shall remain fully operational to include power, data, lighting, and HVAC until such time that all areas are fully operational, occupiable, and secure and functions of are operationally transferred to FAA. All other areas of the building shall be unoccupied for the duration of the construction.
B. Contractor shall relocate occupant’s furniture and equipment to a temporary location designated by the Government prior to beginning work. Any furniture or equipment directed by the Government to be left in the building shall be properly disposed of by the Contractor off site. Any furniture or equipment directed by the Government to be reused shall be stored by the Contractor and reinstalled as directed by the Government.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
CONSTRUCTION PROJECT DOCUMENTATION 01 32 00 - 1
SECTION 01 32 00
CONSTRUCTION PROJECT DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Submittals Schedule.
2. Preliminary Construction Schedule.
3. Contractor's Construction Schedule.
B. Related Sections include the following:
1. Division 01 Section "Project Management and Coordination" for submitting and distributing meeting and conference minutes.
2. Division 01 Section "Submittal Procedures" for submitting schedules and reports.
1.3 SUBMITTALS
A. Submittals Schedule: Submit three (3) copies of schedule. Arrange the following information in a tabular format:
3. Scheduled date for first submittal.
4. Specification Section number and title.
5. Submittal category (action or informational).
6. Name of subcontractor.
7. Description of the Work covered.
8. Scheduled date for the Contracting Office (CO)'s final release or approval.
C. Preliminary Construction Schedule: Submit three (3) copies.
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
CONSTRUCTION PROJECT DOCUMENTATION 01 32 00 - 2
1. Approval of cost-loaded preliminary construction schedule will not constitute approval of Schedule of Values for cost-loaded activities.
D. Contractor's Construction Schedule: Submit one (1) copy of schedule in electronic format for the Project Engineer and RE/COR and submit three (3) hard copies of initial schedule, large enough to show entire schedule for entire construction period. Prepare construction schedule utilizing Microsoft Project indicating the Critical Path and any long lead items.
Update schedule and resubmit with each and every pay application request as a minimum.
1.2 COORDINATION
A. Coordinate requirements in this Article with Part 2 "Submittals Schedule" Article. If a submittal review sequence policy governs, revise this Article to comply with requirements.
See Evaluations for discussion on submittal review sequence policies.
B. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
C. Coordinate Contractor's Construction Schedule with the schedule of values, list of subcontracts, submittals schedule, progress reports, payment requests, and all other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.1 SUBMITTALS SCHEDULE
A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule.
2. If a Preliminary Construction Schedule is not required, delete subparagraph below or revise to require initial submittal within 14 days of date established for commencement of the Work.
3. Initial Submittal: Submit concurrently with preliminary bar-chart schedule. Include submittals required at Notice to Proceed. List those required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
CONSTRUCTION PROJECT DOCUMENTATION 01 32 00 - 3
4. Revise subparagraph below if schedule must be continuously updated to reflect current status and changes in timing for submittals.
5. Final Submittal: Submit concurrently with the first complete submittal of Contractor's Construction Schedule.
2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Manual referenced in first paragraph below contains basic recommendations for CPM procedures and methods.
B. Procedures: Comply with procedures contained in AGC’s "Construction Planning & Scheduling."
C. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order from the Contracting Officer.
D. Activities: Treat each separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
1. Activity Duration: Define activities so no activity is longer than 3 days, unless specifically allowed by the CO.
2. Submittal Review Time: Include review and resubmittal times indicated in Section 013300 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.
3. Substantial Completion: Indicate completion in advance of date established for Substantial Completion and allow time for engineering's administrative procedures necessary for certification of Substantial Completion.
E. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule and show how the sequence of the Work is affected.
1. Phasing: Arrange list of activities on schedule by phase.
2. Products Ordered in Advance: Include a separate activity for each product. Include delivery date indicated in Section 011000 “Summary." Delivery dates indicated stipulate the earliest possible delivery date.
3. Work Restrictions: Show the effect of the following items on the schedule:
a. Limitations of continued occupancies.
b. Uninterruptible services.
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
CONSTRUCTION PROJECT DOCUMENTATION 01 32 00 - 4
c. Use of premises restrictions.
d. Seasonal variations.
e. Weather (requiring a stop work e.g. severe weather)
F. Milestones: Include major milestones indicated in the Contract Documents schedule, including, but not limited to, the Notice to Proceed, Phases begin and end dates, Substantial Completion, and Final Completion.
2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)
A. Gantt-chart schedule in this Article is adequate for many projects. Delete this Article if Project size and complexity justify CPM construction schedule. Time in first paragraph below usually needs extending for multiple contracts.
B. Gantt-Chart Schedule: Within 5 calendar days of contract award, the contractor shall submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule. A Notice to Proceed will not be issued until the schedule is approved.
PART 3 EXECUTION
3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Contractor's Construction Schedule Updating: At weekly intervals, update schedule to reflect actual construction progress and activities. Issue schedule at the regularly scheduled progress meeting. (Proposed vs. Actual)
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate Actual Completion percentage for each activity.
B. Distribution: Distribute copies of approved schedule to the CO, RE/COR, Project Engineer, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
END OF SECTION 01 32 00
SUBMITTAL PROCEDURES 01 33 00 - 1
JCN 1703883 QNA ARSR Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.01 SUBMITTALS
A. Catalog cut sheets, brochures, shop drawings and/or samples shall be clearly marked/indicated by the Contractor and submitted to the Project Engineer for the items on the schedule, drawings and other sections of the specifications.
B. All salient features of materials required to be submitted shall be easily found in the submittal package for each item and not require research on the part of the Government to determine compliance with Contract requirements.
C. Related items such as mechanical/electrical components shall be submitted at one time for coordination purposes.
D. Color coordinated items such as paint, vinyl composition tile, and so forth shall be submitted at one time to facilitate color comparison/selection by the RE/COR. Different categories of submittal items are not to be grouped on the same form.
E. All related submittals have to be submitted all together in one package. Submit the following items for approval after contract award.
1. Paint manufacturer’s technical data sheet including instructions for its applications and use of the interior/exterior primer and interior/exterior paint.
2. Construction…
This is the start of the file's text. The full file is on GovTribe.