1703883 QNA ARSR Scope of Work Repair Building Morales TX 2026 Sept 22.pdf
PDF 93 KB Posted
- Solicitation number
- 6973GH-27-R-00042
About this file
SCOPE OF WORK SUMMARY
This is a detailed Statement of Work (SOW) for repair and restoration services at an ARSR (Air Route Surveillance Radar) equipment building located in Morales, Texas, dated September 22, 2026 (JCN 1703883). The contractor must furnish all equipment, labor, materials, and tools to address water damage, prevent water intrusion, and repair building and exterior items.
Primary Scope Elements
Exterior Work: Power wash the entire building exterior at 1,200–3,500 psi depending on material type, clean CMU walls and concrete foundation by chemical and brush methods, and protect cable trays from damage during washing. Apply two coats of Foundation Armor SX5000 siloxane-silane blend water repellent to all exterior CMU and exposed concrete surfaces.
Sealing and Joint Work: Remove all old, dried, or compromised sealants throughout the building and replace with Sika WS-295 silicone sealant (ASTM C920). This includes eight vertical wall control joints (exterior CMU and interior 5/8" fire-retardant plywood), building-to-foundation joints, concrete door stoops, ductwork and pipe penetrations, soffit joints, siding and frieze board joints, and weatherhoods. For plywood walls, cut 3/8" vee grooves and fill with water-based DAP 3-in-1 Premium Wood Filler; for gypsum board, fill grooves with joint compound and mesh tape.
Door Hardware and Replacement: Replace all door hardware with lever handles and lockset cylinders complying with BHMA Grade 1 system accepting universal 7-pin removable cores. Add panic hardware to Emergency Generator and Equipment Room doors. Replace only the Equipment Room exterior doors and frames with 14-gauge steel, hollow core, label "B" fire-rated doors complying with FAA 1600.69D 4-3-13. For the main entrance double door (CDX-10 lock and Hoffman box), coordinate and pay for a GSA-certified locksmith to remove and reinstall the lock in the new door.
Interior Finishes: Replace all damaged and mold/mildew-stained acoustical ceiling tiles (24" x 48" pattern), maintaining existing pattern and providing six extra tiles to the Contracting Officer. Replace all accessible vinyl composition tile (VCT) flooring and bases with Armstrong Standard Excelon Imperial texture, 1/8" Fortress White, 12" x 12" (SKU 51839), maintaining 12" x 12" grid pattern and consistent texture direction. Replace 4" resilient base where new VCT is installed and elsewhere where accessible.
Painting: Prime and apply two coats of interior white latex paint to all interior plywood and gypsum board walls and ceilings, and interior CMU walls. Paint existing metal gable siding, roof edges, and metal roof overhang vertical faces matching existing colors. Paint all exterior single and double doors and frames inside and outside matching existing colors. For galvanized cable trays and structural supports, apply medium sand abrasion and three coats of Rust Grip® per Section 0991 13.42, with second and third coats applied before first coat fully cures.
Exhaust Fans and Weatherhoods: Replace two existing gable attic louver exhaust fans with Greenheck Sidewall Propeller Exhaust Fans (Product #SE1-16-428-A5X-QD) with compatible controls; install fan speed control model P266ACA-100C (Johnson Controls) set to activate at 90°F and deactivate below 90°F. Provide and install Greenheck wall housing (#H-16) for the 16-inch fans and add weatherhoods (two #WTHD-16-90 and one #WTHD-18-90) with 90-degree turn-down. Replace round wall fan UPS Room in kind (Greenheck P/N CW-099A). All new exhaust fan penetrations must be sealed. Ground all equipment per FAA-STD-19G and test for functionality.
Bollard and Site Work: Paint all existing steel pipe bollards (approximately 24, 6" diameter) with primer and two coats of exterior yellow paint. Provide new yellow high-density polyethylene ¼-inch heavy-duty bollard covers with two red 3/4" reflective stripes. Maintain a portable toilet on site for the duration of construction.
General Requirements: Protect ARSR equipment from damage by containing dust during ceiling work, shielding equipment during painting, and removing receptacle and switch covers temporarily. Move and return all furniture and shelving to original locations and provide sufficient storage boxes for temporary furniture storage. Clean all building floors thoroughly prior to final inspection. Provide specified manufacturer and contractor warranties upon completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JCN 1703883, QNA ARSR, Repair Building & Exterior Items, Correct Water Damage, Prevent Water Intrusion, Morales TX
September 22, 2026
BRIEF SCOPE OF WORK
Furnish the equipment, labor, materials, and tools necessary to:
1. Power wash the entire exterior of the building. Seal exterior CMU walls with water repellant.
2. Relace interior and exterior vertical wall control joint sealants. Replace interior gypsum board sheet ceiling and wall joints and plywood sheet wall joints.
3. Replace exterior all door hardware with lever handles, all lockset cylinders and add panic hardware on Emergency Generator and Equipment Room doors. They must comply with BHMA Grade 1 system that accepts a universal 7-pin removable and interchangeable core.
4. Only replace the Equipment Room exterior doors and frames with 14 gauge steel, label “B” fire rated doors to comply with FAA 1600.69D 4-3-13. Other existing doors and frames remain.
5. The main entrance double door holds a CDX-10 lock and a Hoffman box. The Contractor must coordinate and pay for a GSA-certified locksmith to remove it and reinstall it in the new door.
6. Replace all damaged and mold/mildew stained acoustical ceiling tiles.
7. Replace all accessible resilient vinyl composition tiles (VCT) floor tiles and bases with Contractor furnished material (CFM).
8. Paint interior walls and ceilings, exterior metal siding, exterior doors and frames, exterior cable trays, pipe bollards, and add bollard covers over painted bollards.
9. Replace the two existing gable attic exhaust fans and a round wall fan. Add wall housing for attic fans. Add three weatherhoods over gable louvers.
DETAILED SCOPE OF WORK
Furnish the equipment, labor, materials, and tools necessary to:
1. Power wash the entire exterior of the building including CMU walls, doors, soffits, fascia, discolored concrete foundation next to the building, gable metal siding. Power washing a building, the recommended pressure typically ranges between 1,200 to 3,500 psi depending on the building material, with softer materials like stucco or vinyl siding requiring lower pressure (around 1,200 psi) and tougher materials like brick or concrete handling higher pressure (up to 2,500 psi) and structural steel (up to 3,500 psi).
a. Clean exterior CMU walls, exposed foundation and concrete next to building by chemical, brush and rinse where they are discolored.
b. Power wash top and sides of metal cable trays and the steel supports. Protect the underside of the cable trays that may damage the cables.
2. Reseal the ARSR equipment building.
(See specification Sections 01 56 00, 07 92 00 and 09 21 16)
a. Remove all old dried, cracked or compromised sealant and replace with new for the entire building.
b. This includes inside and outside building vertical control joints, building to foundation joints, concrete door stoops, ductwork and pipe penetrations, soffit, siding and frieze board to wall joints and weatherhoods.
c. Clean out and reseal the building eight vertical wall control joints, outside CMU and inside 5/8” fire retardant plywood walls. Replace backer rods and reseal joints. Sika WS-295 silicone sealant meets ASTM C920.
d. Move furniture, shelves, et cetera, temporarily to perform the interior floor wall and ceiling joint repairs and painting then return it to the initial location when the work is completed. Protect the items attached to the walls not to be painted and equipment that cannot be moved from paint drips and damage, e.g. conduits, remove receptacle and switch covers temporarily for painting, shield ARSR equipment, et cetera.
e. Plywood Sheathing. Where the interior walls are covered with 5/8” 4’ x 8’ fire retardant plywood sheets, strip and clean off all of the accessible joint compound taped plywood panel joints, cut about a 3/8” deep vee groove in joints where sheets meet. Fill the vee grooved joints with water based DAP 3 in 1 Premium Wood Filler, Item no. 101513. Then sand for smooth surface for painting per item 6.a. below.
f. Gypsum Board Sheathing. Where the walls and suspended ceiling are gypsum board, clean off all the existing taped joints, cut about a 3/8” vee in joints where sheets meet. Fill the vee grooved joints with joint compound, cover joints with mesh tape (aka FIBA tape). Apply joint compound smoother out over the tape. Then sand surface for painting per item 6.a. below.
g. Seal bottom of metal panels at the sill plates at the top of the perimeter CMU walls.
h. Add or replace damaged or missing exterior doors items: exterior moldings Door Jamb
Adhesive-Backed Fire/Smoke Silicon Gasketing around all 8 door frames; Heavy Duty Aluminum
Brush Door Sweep for thresholds flush mounted on each of the 8 door leaves. Products to meet grade 1 ANSI/BHMA A156 standards as applicable.
3. Apply blended water-based silane/siloxane water repellent. (See specification Section 07 19 00).
a. Apply two coats of water repellant per manufacturer directions to all surfaces of the exterior
CMU block wall surfaces and exposed concrete foundation after they have been power washed, cleaned and dried properly. Protect adjacent surfaces and items from repellant drips and spray.
b. Use Foundation Armor SX5000 siloxane-silane blend.
4. Exterior Door Hardware and Cylinders.
(See specification Section 08 71 00).
a. Replace all door hardware with lever handles on single and double doors.
a. Replace all lockset cylinders on single and double doors. They must comply with BHMA Grade 1 system that accepts a universal 7-pin removable and interchangeable core.
b. Provide panic hardware on Emergency Generator Room and Equipment Room doors.
c. Only replace the exterior Equipment Room doors and frames with 14 gauge steel, hollow core, label “B” fire rated doors that will comply with FAA 1600.69D 4-3-13, Perimeter Doors and Door Locks requirements. Other existing exterior doors and frames remain.
d. The main entrance double door holds a CDX-10 lock and a Hoffman box. The Contractor must coordinate and pay for a GSA-certified locksmith to remove it and reinstall it in the new door.
5. Acoustical ceiling tiles.
(See specification Sections 01 56 00 and 09 51 00).
a. Replace all damaged and mold/mildew stained acoustical ceiling tiles. Maintain the existing ceiling tile pattern of 24 by 48 inch tiles. Field verify the number to be replaced prior to ordering and provide 6 extra tiles to the COR for the SSC future use.
b. Provide any additional suspended ceiling tile framing or wires to support the ceiling as needed.
c. Contain dust to protect ARSR equipment, shield the equipment, do not cover to prevent any equipment overheating damage.
6. Vinyl flooring tiles and base.
(See specification Section 09 65 00).
a. Replace all resilient vinyl composition tiles (VCT) floor tiles and bases with new Contractor Furnished Material (CFM) floor tiles and bases except for those areas specifically covered by the equipment. Provide Armstrong - Standard Excelon Imperial texture, 1/8” Fortress White 12" x12" SKU: 51839 (45 sf/box) or Contracting Officer approved equivalent or better. Cut the existing tiles along the edges next to where the equipment that remains in place meets the tile flooring.
Maintain the room tile floor 12” x12” grid pattern and run the tile texture pattern all in the same direction, not checkerboarded.
b. Move furniture to perform the new flooring installation and return it to the initial location when the work is completed. Provide enough storage boxes (aka Conex boxes) for temporary storage of furniture, shelving, et cetera on site to execute the project work until all stored items are returned to their initial locations inside of the building.
c. Replace all 4” resilient base where new VCT are installed except where equipment cannot be moved for access. Replace all 4” resilient base elsewhere in the building where it is accessible. Field verify quantity required prior to ordering materials.
d. Remove debris beforehand. Sweep from corners to the center of the rooms or vacuum. Wet mop the new VCT flooring applying cleaning solution per manufacturer’s instructions using only the amount needed. Rinse well to avoid sticky floors. When VCT flooring is dry, apply floor wax and buff.
e. Clean all of the building floors thoroughly prior to final inspection.
7. Prepare surfaces as required and repaint, prime, and two coats.
(See specification Section 09 90 00).
a. Reference notes 2.d. And 2.e. above: for all interior plywood and gypsum board walls and ceilings, interior CMU walls, prime and paint with two coats of interior white latex paint. Protect all wall attached items and equipment that is not to be painted, e.g. conduits, remove receptacle and switch covers temporarily for painting, shield ARSR equipment, et cetera.
b. Paint the existing metal gable siding, roof edges and vertical face of metal roof overhang matching existing color.
c. Paint soffit and metal siding above the top of exterior building CMU walls with paint matching existing color.
d. Paint all exterior single and double doors and frames inside and outside matching existing colors.
e. Following power washing of cable trays, reattach the underside loose cover. Galvanized cable trays from equipment building to tower and the structural supports and similar adjacent items shall be abraded, sand medium, clean, non-greasy, and uncontaminated from salt and other chemicals for paint coats to adhere better. Apply 3 coats of Rust Grip® per Section 0991 13.42 Miscellaneous Exterior Paint. Second and third coat must be applied before Rust Grip® first coat has fully cured to avoid adhesion issues. The surface must also be dry during application. Protect adjacent surfaces from the spray and dripping. Follow manufacturer instructions.
8. Gables, exhaust fans and weatherhoods.
a. Replace the two existing gable attic louver exhaust fans, controls, and provide grounding in accordance with FAA-STD-19G. After fan and control installation, test for functionality. Reference Sections D/A002, E/A002 and 3/A006 Wall Mounted Fan. The as-built drawings indicate the two attic existing exhaust fans are Greenheck Sidewall Propeller Exhaust Fans, Product #SE1-16-428- A5X-QD, 1666-3373 CFM. Field verify prior to ordering the new ones and verify with the manufacturer’s representative the related items ordered are all compatible. Existing wiring can be used for the new fan/control installation if not damaged or deteriorated.
b. Fan speed control: -40°F to 140°F, 0 psi to 754 psi, 208/240v ac, 8 output, 3R, item 40G352 mfr. Model P266ACA-100C, Johnson controls, and associated electrical wiring. Set the temperature controls to turn exhaust fans on when attic space is above 90 degrees F and turn off when the attic space is below 90 degrees F.
c. Provide and install Greenheck wall housing for the two new 16 inch sidewall propeller fans , product #H-16 for the two gable exhaust fans to be replaced.
d. Add and install 2 new weatherhoods, Greenheck weatherhood kits for the 16 inch sidewall propeller fan louvers, with 90 degree turn-down. Field verify the right size prior to ordering, two #WTHD-16-90 and one #WTHD-18-90. Weatherhoods are galvanized steel with wire mesh birdscreen.
e. Provide and install Greenheck weatherhood kit for the 18 by 18 inch gable louver, 90 degree turn-down, product #WTHD-18-90. Weatherhoods are galvanized steel with wire mesh birdscreen. Field verify the right size prior to ordering.
f. Replace round wall fan UPS Room wall in kind. Verify if it is a Greenheck P/N: CW-099A Exhaust Fan. Reference: 099-CUE/099-CW Series Direct Drive Greenheck Exhaust Fan, sidewall mounted. Field verify the exact make and model prior to ordering. Seal all around the new exhaust fan exterior CMU wall penetration.
9. Prepare surfaces, sand medium and clean for primer to adhere better. Paint all existing steel pipe bollards with primer and two coats of exterior yellow paint. Provide new yellow, high density polyethylene, ¼ inch heavy duty bollard covers with 2 red 3/4” reflective stripes by Bollards and Sleeves, LLC over each bollard. Field verify bollards are 6” pipe posts, height and the number required, about 24, prior to ordering bollard covers.
10. Provide and maintain a portable toilet on site for the duration for as long as the construction personnel are on site.
11. Provide specified manufacturer and contractor warranties.