This is an Engineering Change Directive (ECD) for Amendment 1 to a construction contract for the QNA ARSR facility in Morales, Texas, addressing refurbishment and resealing of building and exterior items to correct water damage and prevent water intrusion.
The directive modifies contract specifications and drawings to comply with FAA security requirements per FAA 1600.69D 4-3-13, Perimeter Doors and Door Locks. Key changes include: (1) replacement of the Equipment Room exterior doors—specifically one front double door and one back single door—with new 14-gauge steel, label "B" fire-rated doors and frames complying with FAA standards; (2) addition of a peephole to one front double door; (3) replacement of all door hardware with BHMA Grade 1 lever handles that accept universal 7-pin removable and interchangeable cores on single and double doors; (4) replacement of all lockset cylinders on exterior doors; (5) provision of panic hardware on Emergency Generator Room and Equipment Room doors; (6) removal and reinstallation of the main entrance CDX-10 lock and Hoffman box by a GSA-certified locksmith, with the contractor bearing coordination and payment costs; and (7) replacement of existing vinyl composition tile (VCT) flooring and bases with new contractor-furnished Armstrong Standard Excelon Imperial texture tiles (Fortress White, 12"x12", SKU 51839) except where existing equipment remains in place. The directive affects drawings QNA-1708338-A002 and specifications Sections 01 11 00, 08 71 00, and 09 65 00. The estimated cost impact is $15,000 with no schedule impact, as the contract has not yet been awarded. Implementation requires incorporation of this directive into project documentation for construction contract advertisement and award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QNA ARSR, Refurbish & Reseal Building and Exterior Items to Correct Water Damage, Prevent Water Intrusion, Morales TX
Contract No. xxxxxx
Amendment 1
ENGINEERING CHANGE DIRECTIVE (ECD)
Project: QNA ARSR, Refurbish & Reseal Building and Exterior Items to Correct Water Damage, Prevent Water Intrusion
JCN: 1703883
Revisions to the notes on the drawings and the specifications.
Drawing Affected:
QNA-1708338-A002 – Scope of Work Notes – Add Note 9. Exterior Door Hardware and Cylinders
In 2. Description of Changes below.
Specifications Affected:
Section 01 11 00 — Part 1: General, 1.2. Work Covered by Contract Documents Paragraph C.4.
page 01 11 00 – 3, Item 4 Exterior Door Hardware and Cylinders:
Replace 4.d and add 4.e as in 2. Description of Changes below.
Section 08 71 00 Door Hardware, - Part 1 – General 1.01 Summary, Paragraph A, Replace Paragraph A as In 2. Description of Changes below.
Section 08 71 00 Door Hardware, - Part 3 – Execution, 3.07 Hardware Schedule, Paragraph A, Add B. and C. as in 2. Description of Changes below.
Section 09 65 00 Resilient Tile Flooring — Part 1: General, 1.02. Related Requirements by Contract Documents Paragraph B. page 09 65 00 – 1.
1. PURPOSE
a. This Engineering Change Directive (ECD) provides clarification regarding Contractor responsibility for repair building and exterior items to correct water damage, prevent water intrusion.
b. In drawing and specifications add replace the front double doors and back exterior door of the Equipment Room with new steel 14 gauge steel, label “B” fire rated doors and frames to comply with FAA 1600.69D 4-3-13, Perimeter Doors and Door Locks security requirements. Add a peephole to one of the front double doors.
c. Remove and reinstall the main entrance double door CDX-10 lock and Hoffman box. The contractor must coordinate and pay for a GSA-certified locksmith to remove it and reinstall it in the new door.
d. In specifications add to replace 08 71 00 Door Hardware notes in 1.01 Summary A. And in
3.07 Execution add notes B. and C. to ensure the Contractor field verifies the existing door hardware. Replace existing with hardware BHMA Grade 1 that accepts a universal 7-pin removable and interchangeable core. Emphasize the hardware group tables for single and double doors are only guidelines.
2. DESCRIPTION OF CHANGES
a. On Drawing QNA-1708338-A002 – Scope of Work Notes, added note 9 as follow:
9. Exterior Door Hardware and Cylinders.
(See specification Section 08 71 00).
a. Replace all door hardware with lever handles on single and double doors. They must comply with BHMA Grade 1 system that accepts a universal 7-pin removable and interchangeable core.
b. Replace all lockset cylinders on single and double doors.
c. Provide panic hardware on Emergency Generator Room and Equipment Room doors.
d. The main entrance double door holds a CDX-10 lock and a Hoffman box. The Contractor must coordinate and pay for a GSA-certified locksmith to remove it and reinstall it in the new door.
e. Only replace the exterior Equipment Room doors (this includes 1 double door in the front, and one single door in the back) and frames with 14 gauge steel, label “B” fire rated doors that comply with FAA 1600.69D 4-3-13, Perimeter Doors and Door Locks requirements. Other existing exterior doors and frames remain.
b. Section 01 11 00 — Part 1: General, 1.2. Work Covered by Contract Documents Paragraph C.4.
page 01 11 00 – 3, Item 4. Exterior Door Hardware and Cylinders:
Replace 4.d and add 4.e as follows:
d. Only replace the exterior Equipment Room doors and frames with 14 gauge steel, label “B” fire rated doors that will comply with FAA 1600.69D 4-3-13, Perimeter Doors and Door Locks requirements. Other existing doors and frames remain.
e. The main entrance double door holds a CDX-10 lock and a Hoffman Box. The Contractor must coordinate and pay for a GSA-certified locksmith to remove it and reinstall it in the new door.
c. Section 08 71 00 Door Hardware, - Part 1 – General 1.01 Summary, Paragraph A, replace it as follows:
1.01 SUMMARY
A. Section includes the supply and installation of the Finish Hardware.
1. Contractor shall include field verification of all existing exterior doors condition that are to remain and take note of hardware to be replaced. Replace existing door hardware with BHMA Grade 1 system that accepts a universal 7-pin removable and interchangeable core.
2. Provide new lever handles, hardware and replace lockset cylinders on exterior doors.
Provide new rim cylinders, mortise cylinders, SFIC cores, gasketing, door sweeps, thresholds.
3. Provide the appropriate keying system and coordinate it with RE/COR and SSCM unless instructed otherwise by Project Engineer/Contracting Officer.
4. Provide panic hardware on the Equipment Room and Generator Room steel hollow metal exterior doors.
5. Only the Equipment Room exterior front double door and back single door are to be replaced with 14 gauge steel, label “B” fire rated doors that comply with FAA 1600.69D 4-3-13. Perimeter Doors and Door Locks requirements herein. The other existing exterior doors and frames remain.
6. The main entrance double doors to the Equipment Room has a CDX-10 lock and a Hoffman box. The Contractor must include their bid the cost to coordinate and pay for a GSA-certified locksmith to remove it and reinstall it in the new door.
a. Door Requirements.
(1) Perimeter doors and critical operational area doors must be equipped with latch guards or be designed to protect the latching hardware from tampering. Perimeter double doors must be equipped with full-length astragals or other mechanism (e.g., rim latch hardware, interior mullion) to prevent defeat of the locking hardware.
(2) Exterior perimeter doors and controlled area doors will be kept closed and always locked unless there are personnel providing access control. Doors of facility outbuildings that the SSE determines do not house critical equipment, do not lead to critical areas, do not protect valuable or easily pilfered government equipment and supplies, and are within a properly fenced perimeter are excluded from this requirement.
b. Locking Systems. All exterior perimeter doors and those interior doors through which the FM restricts access will be fitted with any BHMA Grade 1 system that accepts a universal 7-pin removable and interchangeable core that can be changed without disassembling the entire core or BHMA Grade 1 equivalent electronic lock cylinders and programmable smart key systems. Electronic/programmable systems are recommended in circumstances where they are more cost-effective than traditional cores and keys. Keys and access cards must be numbered to facilitate inventory control (see paragraph 4-3-14b).
(1) For FAA-leased facilities, the lessor will furnish FAA standard BHMA Grade 1 locking hardware except for lock cores and keys, which will be provided by the FAA. The FAA will maintain its own key system.
(2) Mechanical push-button keypads or hard-coded electronic keypads may be used in addition to FAA standard locks on any FSL 1 or FSL 1A facility perimeter door; perimeter doors of facility outbuildings that do not house critical equipment or lead to critical areas and are within a fenced perimeter; any internal door not otherwise protected with PACS;
and pedestrian gates at FSL 2 and 1 facilities.
d. Section 08 71 00 Door Hardware, - Part 3 – Execution, 3.07 Hardware Schedule, page 08 71 00- 14, Paragraph A, add B. and C. as follows:
B. Contractor shall field verify existing hardware and replace them with new BHMA Grade 1 system that accepts a universal 7-pin removable and interchangeable cores.
C. Provide any missing items as noted in the hardware group schedule guideline tables below.
e. Section 09 65 00 Resilient Tile Flooring — Part 1: General, 1.02. Related Requirements by Contract
Documents Paragraph B. page 09 65 00 – 1. As follows:
B. Replace all existing resilient floor vinyl composition tiles (VCT) and bases with new Contractor Furnished Material (CFM) floor VCT tiles and bases except for those area specifically covered by the equipment. Provide Armstrong - Standard Excelon Imperial texture, 1/8” Fortress White 12" x12" SKU: 51839 (45 sf/box) or Contracting Officer approved equivalent or better. Cut existing tiles along the edges next to where the equipment that remains in place meets the tile flooring. Maintain the tile floor 12” x 12” grid layout pattern and run the tile texture pattern all in the same direction, not checkerboarded. See 00 11 00 Summary of Work, Part 1, 1.2.C.6.
REASON FOR CHANGE
To comply with ARSR security requirements per FAA 1600.69D 4-3-13, Perimeter Doors and Door
Locks.
Replace Equipment Room exterior doors to protect classified equipment in the room.
And add drawing and specification door hardware notes for clarification of the project scope of work.
Revise Government Furnished Material (GRM) from to Contractor Furnished Material (CFM) for replacing the existing Vinyl Composite Tile (VCT) flooring.
The building drawings with building dimensions, elevations, door schedules, etcetera, are from the
1995 as-built drawings are to show Contractors what is there for their information for estimating, etc.
f. IMPACT ASSESSMENT
Cost Impact: $15,000 estimated.
Schedule Impact: None: not awarded yet.
Functional Impact: Clarifies additional work to comply with FAA security requirements.
g. IMPLEMENTATION
This directive shall be incorporated into the project documentation and used for construction contract advertisement and award.