Questions and Answers as of 10.15.2025.pdf
PDF 236 KB Posted
- Attached to
- SAV TOWB Parking Lot Refurbishment
- Solicitation number
- 6973GH-26-C-00010
About this file
This document is a Questions and Answers (Q&A) file for Solicitation 6973GH-26-R-00010, titled SAV TOWB Parking Lot Replacement. The Q&A covers three key clarification points about a lift replacement project, dated 10/14/2025 and 10/15/2025. The first question seeks dimensions for dumpster doors, though no specific dimensions are provided in the response. The second question addresses potential concrete pad demolition, with guidance to coordinate modifications with the new lift manufacturer's installation recommendations. The third question confirms that existing power supply conduit may be utilized for the replacement lift. An accompanying image shows a green dumpster gate with dimensions of 19'11" wide, with noted height measurements of 8'2.5" and a comment indicating the ground is not level.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
6973GH-26-R-00010
SAV TOWB Parking Lot Replacement
RFI 10/14/2025
1. Q: Under the SOW - Section i, it talks about the dumpster doors. What are the dimensions of the gate - height, width, and opening?
A.
RFI 10/15/2025
2. Q; Will a complete demolition of the concrete pad around the existing lift designated for replacement be needed or will the contractor have to remain within the existing concrete footprint for lift replacement A. Coordinate the need for concrete modifications with new lift manufacturer’s written instructions and recommendations to ensure final installation is compliant with warranty conditions.
3. Q: Can the existing power supply conduit to the existing lift be utilized for the replacement lift, or will the SOW require a new path for power / hydraulic/ air supply for the new lift?
A. Existing conduit may be utilized.