6964 Contract_Executed.pdf
PDF 314 KB Posted
- Attached to
- OSP Boiler Plant Fire Escape
- Solicitation number
- S-29100-00012629
- Issued by
- Marion County, Oregon
About this file
This is a State of Oregon Public Improvement Agreement for the Oregon State Penitentiary (OSP) Boiler Plant Fire Escape project, involving the Department of Corrections and GR Smith Construction Corporation as the contractor. The contract (Number 6964) has a base bid of $116,200.00 for the project, with a project timeline of 10 days after Notice to Proceed for start date, 120 days for substantial completion, and 150 days for final completion. The project is governed by Invitation to Bid No. S-29100-00012629 and includes various exhibits and attachments such as pricing submittal forms, bond forms, general conditions, specifications, plans, and bidder qualification requirements.
The contract includes liquidated damages of $400.00 per calendar day for failing to meet substantial or final completion dates. The contractor (GR Smith Construction Corporation) is based in Salem, Oregon, with a Construction Contractors Board (CCB) license number 230172 valid until 02/26/2026. The agreement requires the contractor to comply with non-discrimination policies, workforce and outreach requirements, and includes provisions for preventing sexual harassment and discrimination. The contract represents the entire agreement between the parties and cannot be modified unless done so in writing and signed by both parties.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12629 OSP Boiler Plant Fire Escape_Plans.pdf | ||
| 12630_Att B_Technical Specs.pdf | ||
| ITB~9.pdf | ||
| 12629 OSP Control Room Fire Escape_SOW .pdf | ||
| 6964 NOITA.pdf | ||
| 12629 ADDENDA 2.pdf | ||
| 12629 Plan Holder list.pdf | ||
| 12629 ITB_GTC_SGC_SPECS.pdf | ||
| 12629 ADDENDA 1.pdf | ||
| 12629 Bid Tab.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Level 3 - Restricted a
Base Bid: $116,200.00; (As Detailed in Exhibit 1, Pricing Submittal Form)
STATE OF OREGON PUBLIC IMPROVEMENT AGREEMENT
for OSP
Boiler Plant Fire Escape Contract Number:6964
This Agreement for the OSP Boiler Plant Fire Escape (the "Agreement"), made by and between the State of Oregon, acting by and through the Department of Corrections, hereinafter called OWNER, and GR Smith Construction Corporation hereinafter called the CONTRACTOR (collectively the “Parties”), is effective on the date this Agreement has been signed by all the Parties and all required State of Oregon governmental approvals have been obtained. Unless otherwise defined in the Invitation to Bid or in this Agreement, the capitalized terms used herein are defined in Section A.1 of the State of Oregon General Conditions for Public Improvement
WITNESSETH:
1. Contract Price, Contract Documents and Work.
The CONTRACTOR, in consideration of the sum of $116,200.00 (the "Contract Price"), to be paid to the CONTRACTOR by OWNER in the manner and at the time hereinafter provided, and subject to the terms and conditions provided for in the Invitation to Bid, this Public Improvement Agreement and other Contract Documents, all of which are incorporated herein by reference, hereby agrees to perform all Work described and reasonably inferred from the Contract Documents.
The Contract Price includes the following items:
CONTRACTOR shall perform the Work for the Contract Price pursuant to Invitation to Bid No. S‐29100‐00012629d all Addenda thereto) and the following Exhibits and Attachments which are incorporated herein by this reference, whether or not physically attached to this Agreement:
EXHIBIT 1 PRICING SUBMITTAL FORM
EXHIBIT 2 [RESERVED]
EXHIBIT 3 PAYMENT BOND FORM
EXHIBIT 4 PERFORMANCE BOND FORM
EXHIBIT 5 [RESERVED]
EXHIBIT 6 GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS
EXHIBIT 7 SUPPLEMENTAL GENERAL CONDITIONS
ATTACHMENT B SPECIFICATIONS
ATTACHMENT C PLANS
ATTACHMENT D GENERAL REQUIREMENTS BIDDER'S QUALIFICATIONS
ATTACHMENT E SECURITY FORM (LEDS)
2. Representatives.
Unless otherwise specified in the Contract Documents, the OWNER designates Pete Belisle as its Authorized Representative in the administration of this Contract. The above‐named individual shall be the initial point of contact for matters related to performance, payment, authorization, and to carry out the responsibilities of the OWNER. CONTRACTOR has named Gary Smith as its Authorized Representative to act on its behalf.
3. Contract Dates.
PROJECT START DATE:
SUBSTANTIAL COMPLETION:
FINAL COMPLETION:
10 Days After Notice to Proceed 120 Days After Notice to Proceed 150 Days After Notice to Proceed
3.a Project substantial and final completion dates represent the BASE BID timelines only. Bid alternates, if selected, may allow additional substantial and final completion time as indicated on each respective bid alternate line item on Exhibit 1; Pricing Submittal Form.
4. Liquidated Damages.
Liquidated damages of $400.00 will apply to the contract resulting from this ITB. Failure to substantially complete the Project by the date of Substantial Completion, as specified in the Contract, will result in damage to the State of Oregon.
Moreover, failure to fully complete the Project by the date of Final Completion, as specified in the Contract, will also result in damage to the State of Oregon. Since actual damage will be difficult to determine, it is agreed that the Contractor shall pay to the State of Oregon, not as a penalty but as the State of Oregon, not as a penalty but as liquidated damages, $400.00 per calendar day elapsed in excess of the Substantial Completion date stated in Section 3 of this Agreement. Moreover, it is agreed that the Contractor shall pay to the State of Oregon, not as a penalty but as liquidated damages, $400.00 per calendar day elapsed in excess of the Final Completion date stated in Section 3 of this Agreement.
5. Certification ‐ Non‐Discrimination Contractor certifies, in accordance with House Bill 3060 (2017 Oregon Laws, chapter 212)(“HB 3060”), that it has in place a policy and practice of preventing sexual harassment, sexual assault, and discrimination against employees who are members of a "protected class," as that term is defined by subsection 2(1)(b) of HB 3060. As a material term and condition of this Agreement, Contractor must maintain, throughout the duration of this Agreement, a policy and practice that complies with HB 3060, including, but not limited to, giving employees written notice of the Contractor’s policy and practice.
6. Workforce and Outreach Requirements (ORS 279C.533) Contractor agrees to be bound by and comply with all applicable workforce and outreach requirements provided under ORS 279C.533 as prescribed in the Contract Documents (see Exhibit 7).
7. Integration THE CONTRACT DOCUMENTS CONSTITUTE THE ENTIRE AGREEMENT BETWEEN THE PARTIES. NO WAIVER, CONSENT, MODIFICATION OR CHANGE OF TERMS OF THIS CONTRACT SHALL BIND EITHER PARTY UNLESS IN WRITING AND SIGNED BY BOTH PARTIES. SUCH WAIVER, CONSENT, MODIFICATION OR CHANGE, IF MADE, SHALL BE EFFECTIVE ONLY IN THE SPECIFIC INSTANCE AND FOR THE SPECIFIC PURPOSE GIVEN. THERE ARE NO OTHER UNDERSTANDINGS, AGREEMENTS, OR
REPRESENTATIONS, ORAL OR WRITTEN, NOT SPECIFIED HEREIN REGARDING THIS CONTRACT.
CONTRACTOR, BY THE SIGNATURE BELOW OF ITS AUTHORIZED REPRESENTATIVE, HEREBY
ACKNOWLEDGES THAT IT HAS READ THIS CONTRACT, UNDERSTANDS IT, AND AGREES TO BE BOUND
BY ITS TERMS AND CONDITIONS.
In witness whereof, the STATE OF OREGON, acting by and through the Department of Corrections executes this Agreement and the CONTRACTOR does execute the same as of the day and year of this Agreement first above written.
CONTRACTOR DATA:
CONTRACTOR NAME: GR Smith Construction Corporation
CONTRACTOR ADDRESS: PO Box 13102
CONTRACTOR ADDRESS: Salem, OR 97309
CONTRACTOR EMAIL ADDRESS: gary@grsmithconstruction.com
CONTRACTOR'S CCB#: 230172
Expiration Date: 02/26/2026
SECRETARY OF STATE REGISTRATION: 1634161-92
CONTRACTOR'S SIGNATURE: Date
Reviewed by Facilities Administrator: Date
Date State of Oregon by and through its DEPARTMENT OF CORRECTIONS
4/23/25
4/16/2025
SCULATTD
Pencil
| STATE OF OREGON PUBLIC IMPROVEMENT AGREEMENT |
| WITNESSETH: |
| 1. Contract Price, Contract Documents and Work. |
| 2. Representatives. |
| 3. Contract Dates. |
| 4. Liquidated Damages. |
| $400.00 |
| 5. Certification ‐ Non‐Discrimination |
| 6. Workforce and Outreach Requirements (ORS 279C.533) |
| 7. Integration THE CONTRACT DOCUMENTS CONSTITUTE THE ENTIRE AGREEMENT BETWEEN THE PARTIES. NO WAIVER, CONSENT, MODIFICATION OR CHANGE OF TERMS OF THIS CONTRACT SHALL BIND EITHER PARTY UNLESS IN WRITING AND SIGNED BY BOTH PARTIES. SUCH WAIVER, CONSENT,... |
| 2025-04-23T11:16:32-0700 | |
| Steve Walborn |
| 2025-04-25T06:30:25-0700 | |
| Dustin Sculatti |
File details come from the government source that posted it. Updated .