This document is a Bid Opening Results file for the Natchez Trace Parkway project (Solicitation No. 693C73-25-B-000007). The project involves resurfacing approximately 9.5 miles of the Natchez Trace Parkway from MP 354.3 to 363.7, including work on ramps, bridges, parking areas, pavement patching, overlay, signing, and pavement markings. The project is divided into multiple schedules (A, B, C, D) with varying performance periods ranging from 30 to 110 calendar days depending on the combination of schedules awarded.
Seven construction companies submitted bids, with total combined schedule prices ranging from $4,631,728 (GC Works Inc.) to $5,682,420.46 (McKenzie Construction and Site Development, LLC). The Engineer's Estimate was $4,042,800.00. The solicitation is specifically for Small Business Concerns, with the total project cost expected to fall between $2,000,000 and $5,000,000. The bid opening took place on April 8, 2025, at 2:00 p.m. in Ashburn, VA, under the Federal Highway Administration's Eastern Federal Lands Highway Division.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Bid Opening for
Natchez Trace Parkway
PROJECT: TN NP NATR 1H11 1J16
SOLICITATION NO. 693C73-25-B-000007
April 8, 2025, at 2:00 p.m.
Ashburn, VA
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-25-B-000007
Project: TN NP NATR 1H11 1J16
April 8, 2025, 2:00 p.m. local time
If the Government awards the contract as Schedules A + B + C + D, the performance period to complete all the contract work will be
110 calendar days. If the Government awards the contract as Schedules A + B + C, the performance period to complete all the contract work will be 95 calendar days. If the Government awards the contract as Schedules A + D, the performance period to complete all the contract work will be 70 calendar days. If awarded separately, Schedule A will be 60 calendar days, Schedule B will be 30 calendar days, Schedule C will be 35 calendar days. If Schedule D is not awarded with Schedule A, it will not be exercised.
BIDDER SCHEDULE TOTAL TOTAL PRICE
Central Southern Construction
Corp.
SCHEDULE A
$2,5440,682.00
SCHEDULE B (GOVERNMENT OPTION 1)
$850,182.00
SCHEDULE C (GOVERNMENT OPTION 2)
$1,110,982.00
SCHEDULE D (GOVERNMENT OPTION 3)
$355,682.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$4,861,528.00
Eclipse Co., LLC SCHEDULE A
$2,159,998.00
SCHEDULE B (GOVERNMENT OPTION 1)
$991,553.00
SCHEDULE C (GOVERNMENT OPTION 2)
$1,144,381.00
SCHEDULE D (GOVERNMENT OPTION 3)
$876,167.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$5,172,099.00
GC Works Inc. SCHEDULE A
$2,264,882.00
SCHEDULE B (GOVERNMENT OPTION 1)
$870,182.00
SCHEDULE C (GOVERNMENT OPTION 2)
$1,130,982.00
SCHEDULE D (GOVERNMENT OPTION 3)
$365,682.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$4,631,728.00
BID OPENING for SOLICITATION NO. 693C73-25-B-000007
Project: TN NP NATR 1H11 1J16
April 8, 2025, 2:00 p.m. local time
If the Government awards the contract as Schedules A + B + C + D, the performance period to complete all the contract work will be
110 calendar days. If the Government awards the contract as Schedules A + B + C, the performance period to complete all the contract work will be 95 calendar days. If the Government awards the contract as Schedules A + D, the performance period to complete all the contract work will be 70 calendar days. If awarded separately, Schedule A will be 60 calendar days, Schedule B will be 30 calendar days, Schedule C will be 35 calendar days. If Schedule D is not awarded with Schedule A, it will not be exercised.
BIDDER SCHEDULE TOTAL TOTAL PRICE
McKenzie Construction and
Site Development, LLC
SCHEDULE A
$2,764,134.44
SCHEDULE B (GOVERNMENT OPTION 1)
$1,078,156.59
SCHEDULE C (GOVERNMENT OPTION 2)
$1,378,423.65
SCHEDULE D (GOVERNMENT OPTION 3)
$461,705.78
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$5,682,420.46
Riley Bridge Co., Inc. SCHEDULE A
$2,370,808.98
SCHEDULE B (GOVERNMENT OPTION 1)
$928,153.08
SCHEDULE C (GOVERNMENT OPTION 2)
$1,181,317.43
SCHEDULE D (GOVERNMENT OPTION 3)
$404,694.38
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$4,884,973.87
Steel Factor Enterprises, LLC. SCHEDULE A
$2,484,072.94
SCHEDULE B (GOVERNMENT OPTION 1)
$1,056,945.60
SCHEDULE C (GOVERNMENT OPTION 2)
$1,346,643.10
SCHEDULE D (GOVERNMENT OPTION 3)
$423,758.90
$5,311,420.54
BID OPENING for SOLICITATION NO. 693C73-25-B-000007
Project: TN NP NATR 1H11 1J16
April 8, 2025, 2:00 p.m. local time
If the Government awards the contract as Schedules A + B + C + D, the performance period to complete all the contract work will be
110 calendar days. If the Government awards the contract as Schedules A + B + C, the performance period to complete all the contract work will be 95 calendar days. If the Government awards the contract as Schedules A + D, the performance period to complete all the contract work will be 70 calendar days. If awarded separately, Schedule A will be 60 calendar days, Schedule B will be 30 calendar days, Schedule C will be 35 calendar days. If Schedule D is not awarded with Schedule A, it will not be exercised.
BIDDER SCHEDULE TOTAL TOTAL PRICE
Yorkshire Industries SCHEDULE A
$2,226,453.83
SCHEDULE B (GOVERNMENT OPTION 1)
$869,546.36
SCHEDULE C (GOVERNMENT OPTION 2)
$1,161,440.12
SCHEDULE D (GOVERNMENT OPTION 3)
$400,680.93
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$4,658,121.24
Engineer’s Estimate SCHEDULE A
$1,742,800.00
SCHEDULE B (GOVERNMENT OPTION 1)
$710,000.00
SCHEDULE C (GOVERNMENT OPTION 2)
$890,000.00
SCHEDULE D (GOVERNMENT OPTION 3)
$700,000.00
$4,042,800.00
| Slide 1 |
| Slide 2: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-25-B-000007 Project: TN NP NATR 1H11 1J16 April 8, 2025, 2:00 p.m. local time If the Government awards the contract as Schedules A + B + |
| Slide 3: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-25-B-000007 Project: TN NP NATR 1H11 1J16 April 8, 2025, 2:00 p.m. local time If the Government awards the contract as Schedules A + B + |