This is a summary of a federal contract opportunity for pavement preservation work on the Blue Ridge Parkway in North Carolina. The solicitation is for certified Small Business Concerns only to submit proposals for Solicitation Number 693C73-20-R-000003. The project consists of pavement preservation along approximately 25.67 miles of the parkway and includes one of the following pavement preservation treatment methods: stress-absorbing membrane interlayer or ultra-thin bonded wearing course. In addition to the selected pavement preservation method, the work includes asphalt concrete patching, pavement markings, and other miscellaneous tasks. The project will be split into multiple work schedules with the total cost expected to be between $1-5 million. Construction must be completed by December 11, 2020. Bid documents are scheduled for issue on November 18, 2019 with the bid due date and location specified on the SF 1442 form. Offerors must submit qualifications related to their experience with one of the pavement preservation methods. The solicitation will provide further requirements.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STRUCTURE SUMMARY STRUCTURE NO. 5140-119P
U.S. ROUTE 74A BRIDGE INSPECTION DATE: 7/13/17
BRIDGE IDENTIFICATION AND DESCRIPTION
MAIN SPAN MATERIAL: ....... CONCRETE CONTINUOUS NO. OF MAIN SPANS:
MAIN SPAN TYPE: ............... BOX GIRDER - SINGLE or SPREAD NO. OF APPR. SPANS:
# OF BEAMS, MAIN SPAN: .. 1 STRUCT. TOTAL LENGTH: .. 340.0 FT (103.6 M)
DECK TYPE: ......................... CONCRETE CAST-IN-PLACE MAX. SPAN LENGTH: .......... 102.0 FT (31.1 M)
WEARING SURFACE: .......... MONOLITHIC CONCRETE DECK WIDTH: ...................... 36.0 FT (11.0 M)
ABUT. FOUNDATIONS: ........ SPREAD FTG ON BEARING MAT'L CURB TO CURB WIDTH: ..... 28.0 FT (8.5 M)
PIER FOUNDATION(S): ........ UNKNOWN YEAR BUILT:
ABUTMENT / PIER MAT'L: ... CONCRETE YEAR RECONSTRUCTED: .. N/A
PROJ./PLAN REF. NO: ......... 2R1 / NONE SKEW ANGLE: ..................... 29 °
NPS ROAD CLASS: .............. 1 - PRINCIPAL PARK ROAD FRACTURE CRITICAL: ........ NO
STRUCTURE HISTORY: ...... 1981-JOINT REPAIR.
LOCATION
BLUE RIDGE PARKWAY MILE POINT: ..................... 384.75 (KM PT 618.78)
STATE: ................................. NORTH CAROLINA LOCATION: 1.2 MILES TO INTERSTATE 40
FACILITY CARRIED: ............ BLUE RIDGE PARKWAY
FEATURE INTERSECTED: .. U.S. ROUTE 74A
STRUCTURE EVALUATION SUMMARY
This concrete box girder bridge is in fair condition overall. Problems include significant transverse cracking in the deck surface over the piers and scaling of the deck surface, which has led to excessive aggregate exposure due to the loss of cement matrix. This condition gives greater potential for vehicles to slide during sudden stops, thus a non-skid surfacing material should be applied to the deck or transverse grooves/tines cut into surface. Other problems include a spall in the bearing seat at the south abutment, exposed rebar on the underside of the deck overhang and box girder, an erosion hole on the west side of the south pier, and debris accumulation in the abutment expansion joints.
Corrective action should be taken as outlined in this report to prevent the possible development of more serious or costly problems in the future.
INSPECTION TEAM: J. TRIPLETT (SEH), B. ROBIN (GEOCAL)
CONDITION ASSESSMENT:
JASON D. TRIPLETT, P.E., FIELD TEAM LEADER
REPORT REVIEW:
MARCUS MILLER, P.E., BRIDGE INSPECTION ENGINEER 703-404-6252
REPORT APPROVAL: DATE: 12/6/17
JORGOMAI CEESAY, PH.D., P.E., BIP SUPERVISORY ENGINEER 703-404-6244
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5140-119P
A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.
B (Major) - Structure exhibits severe deterioration, presents a safety hazard, or is designated a high priority due to age and/or condition.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
C226 PRIORITY OF IMPROVEMENT
ITEM
NO.
MAINTENANCE RECOMMENDATIONS
(GENERALLY NOT FLHP ELIGIBLE)
QTY. UNIT COST
UNIT
ESTIMATE
COST
PRELIM.
58.2 CLEAN SOIL AND DEBRIS FROM EXPANSION JOINTS AT ABUTMENTS. 1 LS
58.7 CLEAN DEBRIS OUT OF DECK DRAINS. 1 LS
PRELIM. MAINTENANCE TOTAL :
ITEM
NO.
REHABILITATION/RECONSTRUCTION
(TYPICALLY NEEDED WITHIN 5 YEARS)
QTY. UNIT
UNIT
COST ESTIMATES
PRELIM. COST
REHAB. RECONSTR.
58.1 CLEAN AND SEAL DECK SURFACE. 1 LS
60.3 REPAIR SPALLED BEARING SEAT AT SOUTH ABUTMENT. 1 LS
58.1, 59.2 CLEAN EXPOSED REBAR IN DECK AND BOX GIRDER UNDERSIDE AS
NECESSARY, AND SEAL ALL WITH AN APPROVED PROTECTIVE
COATING.
1 LS
60.17 FILL AND STABILIZE EROSION HOLE ON WEST SIDE OF SOUTH
PIER.
1 LS
59 CONTRACT COSTS FOR MOBILIZATION, TRAFFIC CONTROL, AND
DESIGN/CONSTRUCTION ENGINEERING.
1 LS
PRELIM. REHABILITATION/RECONSTRUCTION TOTAL :
PRELIMINARY ESTIMATE TOTAL* :
(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)
REMARKS: Access hatch at Span #2 is rusted shut with broken bolts present; hatches at Spans #3 and #4 are grouted shut.
Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.
FIELD INSPECTION REPORT STRUCTURE NO. 5140-119P
G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)
CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS
SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.
Fatigue cracks in steel or shear cracks in concrete may be present.
CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.
“IMMINENT” FAILURE CONDITION - major deterioration or sec ion loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability. Structure is closed to traffic but corrective action may return structure to light service.
FAILED CONDITION - out of service; beyond corrective action.
CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223
NOT APPLICABLE
EXCELLENT CONDITION
VERY GOOD CONDITION - no problems noted.
GOOD CONDITION - some minor problems.
SATISFACTORY CONDITION - structural elements show some minor deterioration.
FAIR CONDITION - all primary structural elements are sound but may have minor section loss, cracking, spalling, or scour.
POOR CONDITION - advanced section loss, deterioration, spalling, or scour.
N
58. DECK ITEM REFERENCE AND REMARKS
OTHER
ALIGNMENT
DEFLECTION AND/OR VIBRATION
FASCIA(E)
DIAPHRAGMS AND BRACING
TRUSSES
FLOOR BEAMS AND STRINGERS
ARCH(ES) OR SLAB(S)
GIRDERS OR BEAMS
BEARING DEVICES
59. SUPERSTRUCTURE
OTHER
DEFLECTION AND/OR VIBRATION
UTILITIES
DRAINS AND DRAINAGE
PARAPETS AND/OR RAILINGS
CURBS, SIDEWALKS, AND MEDIAN
RIDEABILITY
WEARING SURFACE
EXPANSION JOINTS
DECK SLAB
OTHER
SETTLEMENT OR DEFLECTION
EROSION AND/OR SCOUR
FOUNDATIONS
CAPS AND/OR BEARING SEATS
PILE BENTS
WALLS AND/OR COLUMNS
PIER(S)
OTHER
SLOPE PROTECTION
SETTLEMENT OR DEFLECTION
EROSION AND/OR SCOUR
EXPANSION JOINTS
WEEP HOLES
WINGWALLS
FOUNDATIONS
BACKWALLS AND/OR BULKHEADS
CAPS AND/OR BEARING SEATS
PILE BENTS
BREASTWALLS OR COLUMNS
ABUTMENTS
60. SUBSTRUCTURE
1.
10.
2.
3.
4.
5.
6.
7.
8.
9.
10.
9.
8.
7.
6.
5.
4.
3.
2.
1.
PAINT
11.
G F N N N N N N G
N G
G N F N N G G N F G N N
G N N N F G N
11.
10.
9.
8.
7.
6.
5.
4.
3.
2.
1.
12.
13.
14.
15.
16.
17.
18.
19.
58.1,4 MODERATE TO SEVERE TRANSVERSE AND MAP CRACKING UP TO
0.050 INCHES WIDE, SPACED 6"-24" APART THROUGHOUT TOP OF
SLAB. MINOR CRACKING WITH EFFLORESCENCE ON DECK
OVERHANGS. MODERATE TO SEVERE WEAR HAS RESULTED IN
EXPOSED AGGREGATE ON DECK WITH ROUGH RIDING SURFACE.
EXPOSED REBAR ON DECK UNDERSIDE OF SPAN #2, EAST SIDE,
AND SPAN #4, WEST SIDE, DUE TO INSUFFICIENT COVER. EXPOSED
REBAR, 2.2' LONG IN SOUTHBOUND LANE OF SPAN #1 DUE TO
INSUFFICIENT COVER. SMALL AREA OF EXPOSED REBAR IN WEST
CURBLINE NEAR SOUTH PIER.
58.2 MINOR LEAKAGE THROUGH EXPANSION JOINTS. MODERATE SOIL
AND DEBRIS ACCUMULATION IN SLIDING PLATE JOINTS AT ENDS.
58.5 MINOR SCALING OF SIDEWALKS. MAP CRACKING WITH LIGHT
EFFLORESCENCE IN ENDS OF SIDEWALKS, ADJACENT TO END
WALLS.
58.5,6 JOINT FILLER MISSING FROM PARAPET AND SIDEWALK JOINTS.
MODERATE DEBRIS ACCUMULATION WITH VEGETATION GROWTH IN
SIDEWALK JOINTS.
58.6 MINOR CRACKING AND SPALLING OF PARAPETS WITH EXPOSED
REBAR. SEVERAL AREAS HAVE BEEN PATCHED.
MODERATE SOIL DEPOSIT AND MOSS GROWTH AT BASE OF MOST
RAILING POSTS.
58.7 MINOR TO MODERATE DEBRIS ACCUMULATION AT SCUPPERS,
SEVERAL ARE CLOGGED. UP TO 2" OF DEBRIS ACCUMULATION
ALONG CURBS.
59.2 TRANSVERSE HAIRLINE CRACK WITH LIGHT EFFLORESCENCE ON
UNDERSIDE OF GIRDER IN SPAN #2 AT EAST EDGE. MINOR
TRANSVERSE CRACKING WITH LEAKAGE AND STAINING ON
UNDERSIDE OF BOX GIRDER AT EAST SIDE OF SPAN #1 NEAR
NORTH ABUTMENT AND IN SPAN #2. SPANS #2 AND #3 EXHIBIT
NOTICEABLE SAGGING AT EAST SIDE AT MIDSPAN (MAY HAVE BEEN
AS-BUILT). MINOR SPALLING WITH EXPOSED REBAR ON
UNDERSIDE OF SPAN #2, AND #3 AT EAST SIDE, AND SPAN #4 AT
WEST SIDE, DUE TO INSUFFICIENT COVER. STAINS AROUND (3)
DECK DRAINS ON UNDERSIDE OF SPAN #2.
N F G G F N
N
G
G
F
INSPECTION DATE: 7/13/17
STRUCTURE NO. 5140-119P FIELD INSPECTION REPORT
U.S. ROUTE 74A BRIDGE
ITEM REFERENCE AND REMARKS
AVERAGE CLEAR OPENING 8.
NORMAL VELOCITY 7.
ADEQUACY OF OPENING 6.
OTHER 5.
WATERWAY OBSTRUCTIONS 4.
CHANNEL PROTECTION 3.
EROSION AND/OR SCOUR 2.
1. ALIGNMENT
61. CHANNEL 7
G G N F N
MED
EXCESS
45 FT.
9. STREAM BED COMPOSITION :
ROCK, SILT
222. APPROACHES 6
OTHER 9.
ALIGNMENT 8.
SIGNS 7.
SETTLEMENT 6.
EROSION 5.
SURFACING 4.
APPROACH GUARDRAIL 3.
RELIEF JOINTS 2.
1. APPROACH SLABS N
N N F G F N G N
223. RETAINING WALL 8
OTHER 6.
SETTLEMENT OR DEFLECTION 5.
EROSION AND/OR SCOUR 4.
FOUNDATION 3.
WEEP HOLES 2.
1. WALL
(BURIED)
G G G N N N
36. TRAFFIC AND SAFETY FEATURES
APPROACH GUARDRAIL ENDS D.
APPROACH GUARDRAILS C.
TRANSITIONS B.
BRIDGE RAILINGSA. 1
N N N
TRAFFIC SAFETY RATING CODES
N
Does not meet standards or a safety feature is required and none is provided.
Meets currently acceptable standards.
Not applicable or a safety feature is not required.
60.1,3
60.9,17
60.13
61.4
222.4
222.6
MINOR WATER LEAKAGE AND STAINING AT BOTH ABUTMENTS AND
MINOR CRACKING ON BREASTWALLS. VERTICAL CRACK WITH
EFFLORESCENCE AT WEST END OF NORTH ABUTMENT. MODERATE
SPALL ON SOUTH ABUTMENT EAST OF CENTERLINE AT BEARING
SEAT STEP IN BREASTWALL. MINOR SPALLS WITH EXPOSED
REBAR DUE TO INSUFFICIENT COVER. MINOR POPOUT WITH
EXPOSED REBAR ON BOTH CHEEKWALLS OF SOUTH ABUTMENT;
AREAS OF DELAMINATION WITH EXPOSED REBAR IN NORTHWEST
CHEEKWALL.
4' DIAMETER, 7' DEEP EROSION HOLE AT TOP WEST CORNER OF
CONCRETE SLOPE PROTECTION AT SOUTH PIER. ATTEMPTS MADE
TO SEAL MODERATE CRACKING OF SLOPE PROTECTION HAVE
FAILED. PARTIALLY FILLED IN WITH RIPRAP.
ACTIVE EROSION AT SOUTH ABUTMENT SLOPE, UP TO 2' WIDE AND
1' DEEP TOWARDS PIER #3. 1 1/2" OF SETTLEMENT AT PIER #3
SLOPE PROTECTION.
MINOR SPALL ON BASE OF CENTER PIER, NORTH FACE.
MODERATE DEBRIS AND FALLEN TREES ACCUMULATION IN
DOWNSTREAM CHANNEL.
MINOR TO MODERATE TRANSVERSE AND LONGITUDINAL CRACKING
IN ASPHALT AT NORTH APPROACH.
CRACKING AT PREVIOUSLY REPAIRED PAVEMENT AT SOUTH
APPROACH.
NORTH APPROACH HAS SETTLED UP TO 3/4" CAUSING ROUGH
TRANSITION ON AND OFF BRIDGE.
STRUCTURE LOAD RATING STRUCTURE NO. 5140-119P
TRUCK TYPE
INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)
TONS METRIC TONS TONS METRIC TONS
H 15 14 25 23
HS 22 20 37 34
TYPE 3 21 19 36 32
TYPE 3S2 26 23 43 39
TYPE 3-3 28 25 47 42
DESIGN LOADING: H15 (M13.5)
X CAPACITY MEETS OR EXCEEDS DESIGN LOAD
CAPACITY IS LESS THAN DESIGN LOAD
ORIGINAL LOAD RATING CALCULATION APPLICABLE
ORIGINAL LOAD RATING CALCULATION REVISED
DATE OF LOAD RATING CALCULATION:
LOAD RATING CONTROLLED BY:
REMARKS: RATING IS BASED ON DESIGN LOAD OF STRUCTURE.
| STRUCTURE INVENTORY AND APPRAISAL | STRUCTURE NO. 5140-119P |
| U.S. ROUTE 74A BRIDGE | INSPECTION DATE: 7/13/17 |
STRUCTURE IDENTIFICATION
(201) PARK: BLUE RIDGE PARKWAY (1) STATE: ....................................... 374 - NORTH CAROLINA (NC)
(202) STRUCTURE NAME: .......... U.S. ROUTE 74A BRIDGE (2) STATE HWY. AGENCY DIST:
(203) STRUCTURE KIND: ............ 1 - BRIDGE (3) COUNTY CODE: ........................ 021 - BUNCOMBE
(204) STRUCTURE NUMBER: ..... 5140-119P (4) CITY/PLACE CODE:
(205) NPS REGION: .................... 4 - SOUTHEAST (5) INVENTORY ROUTE:
(206) ROUTE CODE NUMBER: ... 1 (6) FEATURES INTERSECTED:....... U.S. ROUTE 74A
(207) ROAD SECTION NO: .......... 119P (7) FACILITY CARRIED: .................. BLUE RIDGE PARKWAY
(208) NPS ROAD CLASS: ............ 1 - PRINCIPAL PARK ROAD (8) STATE STRUCTURE NO: .......... 5140119P0000000
(209) WITHIN NPS BNDRY?: ....... YES (9) LOCATION: ................................ 1.2 MILES TO INTERSTATE 4
(210) OPERATING UNIT: ............. GILLESPE (10) INV. RTE. - MIN. VERT. CLR: .. 99.99 FT (99.99 M)
(211) PROJECT NO(S): ................ 2R1 (11) MILE POINT: ............................. 384.75 (KM PT 618.78)
(212) DRAWING NUMBERS: ....... NONE (27) YEAR BUILT:
(21) MAINTAINED BY: ................. 66 - NATIONAL PARK SERVICE (106) YEAR RECONSTRUCTED: .... N/A
(22) OWNER: ............................... 66 - NATIONAL PARK SERVICE (20) TOLL: ........................................ 3 - FREE ROAD
(37) HISTORICAL DESIGNATION: .. 5 - NOT ELIGIBLE
STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE
(43A) MAIN STR. MATERIAL: ..
(43B) MAIN STR. TYPE:
(45) NO. OF MAIN SPANS:
(48) MAX. SPAN LENGTH:
(49) STRUCTURE LENGTH:
(216A) ABUTMENT #1 FDN:
(216B) ABUTMENT #2 FDN:
(217A) PREDOM. PIER FDN.: ..
(217B) SECOND. PIER FDN: ...
(107) DECK TYPE:
2 - CONCRETE CONTINUOUS
06 - BOX GIRDER - SINGLE or SPREAD
102.0 FT (31.1 M)
340.0 FT (103.6 M)
2 - SPREAD FTG ON BEARING MAT'L
2 - SPREAD FTG ON BEARING MAT'L
0 - UNKNOWN
0 - UNKNOWN
1 - CONCRETE CAST-IN-PLACE
(44A) APPR. STR. MATERIAL: ........ 0 - OTHER
(44B) APPR. STR. TYPE: ................ 00 - OTHER
(46) NO. OF APPROACH SPANS: .. 0
(108) WEAR SURFACE/PROTECT SYSTEM:
A) TYPE WEARING SURFACE: .. 1 - MONOLITHIC CONCRETE
B) TYPE MEMBRANE: ................. 0 - NONE
C) TYPE PROTECTION: .............. 0 - NONE
(218) IS SALT USED?: ..................... YES
LOAD RATING AND POSTING
(31) DESIGN LOAD: ................. 2 - H15 (M13.5) (41) LOAD RESTRICTION: ......... A - OPEN, NO RESTRICTION
(66) INVENTORY RATING: ...... 22.4 TONS (20.3 METRIC TONS) (70) BRIDGE POSTING: .............. 5 - NO POSTING REQUIRED
(64) OPERATING RATING: ...... 37.3 TONS (33.9 METRIC TONS)
INSPECTION DATES
(90) INSPECTION DATE: 7/17 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):
(219) ADD. STUDIES NEEDED: Y - 1 - DECK SURVEY (A) FRACTURE CRITICAL: ... NO
INSP. EVERY: MONTHS - LAST INSP. : (220) SPECIAL STUDY TYPE: 0 - NONE
(B) UNDERWATER: .............. NO
(221) SPECIAL STUDY DATE: INSP. EVERY: MONTHS - LAST INSP. :
(C) SPECIAL INSPECTION: .. NO
INSP. EVERY: MONTHS - LAST INSP. :
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5140-119P
GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA
(51) CURB TO CURB WIDTH: ........... 28.0 FT (8.5 M)
(16) LATITUDE: ............................. 35°33'45.60"
(17) LONGITUDE: ......................... 82°29'33.40"
(19) DETOUR LENGTH: ............... 8 MI (13 KM)
(28A) LANES ON STRUCT:
(28B) LANES UNDER STRUCT: ... 02
(42A) SERVICE ON: ..................... 5 - HIGHWAY-PEDESTRIAN
(42B) SERVICE UNDER: .............. 6 - HIGHWAY-WATERWAY
(29) AVG. DAILY TRAFFIC:
(30) YEAR OF ADT:
(114) FUTURE ADT:
(115) YEAR OF FUTURE ADT:
(101) PARALLEL STRUCTURE: ... N - NONE
(38) NAVIGATION CONTROL?: ... 0
(39) VERTICAL CLEARANCE: ...... 0.0 FT (0.0 M)
(40) HORIZ. CLEARANCE: ........... 0.0 FT (0.0 M)
(111) ABUT. OR PIER PROT:
LATERAL UNDERCLEARANCE:
(55) RIGHT: ....................... 10.0 FT (3.0 M)
(56) LEFT: ......................... 0.0 FT (0.0 M)
CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST
(58) DECK:
(59) SUPERSTRUCTURE:
(60) SUBSTRUCTURE:
(61) CHANNEL:
(62) CULVERT: ........................... N
(222) APPROACHES:
(223) RETAINING WALL:
(36) TRAFFIC SAFETY FEAT: ... 1NNN
(75A) TYPE OF WORK:
(75B) WORK DONE BY:
(76) IMPROVEMENT LENGTH: ..
(52) DECK WIDTH:
(32) APPR. ROADWAY WIDTH:
(213) APPR. PAVEMENT WIDTH:
LEFT SHOULDER:
RIGHT SHOULDER:
(33) BRIDGE MEDIAN:
(34) SKEW ANGLE:
(35) DECK FLARE?:
(47) TOTAL HORIZ. CLEARANCE:
(50) SIDEWALKS:
LEFT :
RIGHT :
(214) BRIDGE RAIL TYPE:
RAIL CONFIGURATION:
MATERIAL:
DESIGN TYPE:
(215) BRIDGE RAIL HEIGHT:
(53) MIN. VRT. CLEAR. OVER DECK:
(54) MIN. VRT. UNDERCLEARANCE:
36.0 FT (11.0 M)
38.0 FT (11.6 M)
22.0 FT (6.7 M)
8.0 FT (2.4 M)
8.0 FT (2.4 M)
0 - NO MEDIAN
29 °
NO
28.0 FT (8.5 M)
2.7 FT (0.8 M)
2.7 FT (0.8 M)
2 - MOUNTED ON PARAPET
3 - CONCRETE/STEEL
1 - CONTINUOUS RAIL
2.75 FT (0.84 M)
99.99 FT (99.99 M)
40.00 FT (12.20 M)
(67) STRUCTURAL EVALUATION:
(68) DECK GEOMETRY:
(69) UNDERCLEARANCES:
(71) WATERWAY ADEQUACY:
(72) APPROACH ALIGNMENT:
(113) SCOUR CRITICAL:
(225) PURPOSE OF IMPROVEMENT:
(226) PRIORITY OF IMPROVEMENT:
(227) MAINTENANCE COST:
(228) REHAB./RECONSTR. COST: ...
(229) CONSTRUCTION COST:
7 - Countermeasures installed to
2 - REHAB/RECONSTRUCTION
C - MODERATE
ADDITIONAL INFORMATION
(230) STRUCTURE HISTORY:
1981-JOINT REPAIR.
(231) ADDITIONAL CONSIDERATIONS:
(330) ADDITIONAL CONFIG. INFO.:
http:82�29'33.40 http:35�33'45.60
APPENDIX STRUCTURE NO. 5140-119P
PHOTOGRAPHS STRUCTURE NO. 5140-119P
PHOTO #1 - LOOKING NORTH TOWARD BLOWING ROCK
FLOW
PHOTO #2 - EAST (UPSTREAM) SIDE
PHOTO #3 - GENERAL TOPSIDE VIEW LOOKING NORTH
PHOTO #4 - DIAGONAL CRACKING OF TOP OF DECK, SOUTHBOUND
LANE NEAR NORTH ABUTMENT SHOWN
PHOTO #5 - TRANSVERSE AND LONGITUDINAL CRACKING IN WEARING
SURFACE AT NORTH APPROACH
PHOTO #6 - TRANSVERSE AND DIAGONAL CRACKING OF DECK
SURFACE, SOUTHBOUND LANE NEAR SOUTH END
PHOTO #7 - TRANSVERSE CRACKING OF DECK SURFACE, NORTH AND
SOUTHBOUND LANES OF SPAN #1 SHOWN
PHOTO #8 - TRANSVERSE CRACKING AND EXPOSED REBAR IN DECK
SURFACE IN SOUTHBOUND LANE OF SPAN #1 SHOWN
PHOTO #9 - DEBRIS ACCUMULATION AND VEGETATION GROWTH
ALONG NORTHWEST APPROACH CURBLINE
PHOTO #10 - DEBRIS ACCUMULATION ALONG EAST CURBLINE
PHOTO #11 - CLOGGED SCUPPER ALONG EAST CURBLINE NEAR
SOUTH END OF BRIDGE
PHOTO #12 - EXPANSION JOINT AT NORTH ABUTMENT; NOTE DEBRIS
AT ENDS
PHOTO #13 - EXPANSION JOINT AT SOUTH ABUTMENT
PHOTO #14 - SECTION OF EAST TOP RAIL NOT CONNECTED AT
ANCHORAGE POST IN SPAN #3
PHOTO #15 - MISSING NUT ON EAST RAILING ANCHORAGE POST
ABOVE PIER #2; NOTE MOSS GROWTH ON NUTS
PHOTO #16 - TYPICAL SOIL AND MOSS ACCUMULATION AT BASE OF
RAIL POSTS, WEST RAIL POST NEAR NORTH END SHOWN
PHOTO #17 - TRANSVERSE CRACKING OF PREVIOUSLY REPAIRED
SOUTH APPROACH PAVEMENT
PHOTO #18 - TRANSVERSE CRACKING OF SOUTH APPROACH
PAVEMENT
PHOTO #19 - GENERAL UNDERSIDE VIEW OF SPAN #2 LOOKING SOUTH
PHOTO #20 - GENERAL UNDERSIDE VIEW OF SPAN #3 LOOKING NORTH
PHOTO #21 - SPALL WITH EXPOSED REBAR AND WATER STAINING ON
EAST SIDE OF BOX GIRDER UNDERSIDE IN SPAN #2 NEAR NORTH PIER
PHOTO #22 - REPAIRED CRACKING IN WEST SIDE OF BOX GIRDER
NEAR NORTH ABUTMENT
PHOTO #23 - PATCHED AREA WITH PREVIOUS WATER LEAKAGE ON
UNDERSIDE OF BOX GIRDER AT EAST SIDE OF SPAN #1
PHOTO #24 - SPALL WITH EXPOSED REBAR ON UNDERSIDE OF BOX
GIRDER AT EAST SIDE OF SPAN #3 NEAR ACCESS HATCH
PHOTO #25 - SPALL WITH EXPOSED REBAR ON UNDERSIDE OF BOX
GIRDER AT WEST SIDE OF SPAN #4
PHOTO #26 - GENERAL VIEW OF NORTH ABUTMENT
PHOTO #27 - CRACKING WITH WATER LEAKAGE ON NORTHWEST
UNDERSIDE OF BOX GIRDER AND BACKFILL LEAKAGE THROUGH
WEEPHOLE AT NORTH ABUTMENT
PHOTO #28 - GENERAL VIEW OF SOUTH ABUTMENT
PHOTO #29 - CRACKING ON BEARING SEATS NEAR CENTERLINE OF
SOUTH ABUTMENT; NOTE SPALLING AND WATER LEAKAGE
PHOTO #30 - CLOSE-UP OF CRACKING AT BEARING SEAT IN SOUTH
ABUTMENT; NOTE ACTIVE LEAKAGE
PHOTO #31 - CRACKING WITH EFFLORESCENCE AND ACTIVE WATER
LEAKAGE AT WEST END OF NORTH ABUTMENT
PHOTO #32 - EROSION TRENCH CUTTING IN FROM SOUTHEAST
CORNER OF SOUTH ABUTMENT SLOPE
PHOTO #33 - GENERAL VIEW OF NORTH PIER, SOUTH SIDE SHOWN
PHOTO #34 - GENERAL VIEW OF CENTER PIER, SOUTH SIDE SHOWN
PHOTO #35 - SPALL AND DELAMINATION AT BASE OF CENTER PIER ON
NORTH SIDE
PHOTO #36 - GENERAL VIEW OF SOUTH PIER, NORTH SIDE SHOWN
PHOTO #37 - EROSION HOLE ON WEST SIDE OF CONCRETE SLOPE
PROTECTION AT SOUTH PIER
PHOTO #38 - CLOSE-UP OF EROSION HOLE AT WEST SIDE OF
CONCRETE SLOPE PROTECTION AT SOUTH PIER
PHOTO #39 - FAILURE OF JOINT FILLER MATERIAL ON NORTH FACE OF
SOUTH PIER
PHOTO #40 - LOOKING UPSTREAM
PHOTO #41 - LOOKING DOWNSTREAM