Sample Payment Milestone Schedule
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6923G520RTUGREPLACEMENT ATTACHMENT
The offeror may propose customary contract financing for shipbuilding projects for this project.
Progress payments will be based on a stage of completion.
Suggested milestones include:
• Submission of Required Plans and Documentation 10%
• Steel ordered 15%
• Keel laying 10%
• Engines tested 10%
• Hull 90% framed and plated 15%
• Deckhouse/Wheelhouse attached 15%
• Launch 10%
• Dock trials 5%
• Delivery/acceptance 10%
A three (3) % retainage will be deducted from each progress payment.
Offerors shall include anticipated completion dates for each proposed milestone based on a twelve (12) month project completion/delivery time.
The offeror’s proposed progress payment schedule will be evaluated to determine if the proposed financing is in the best interest of the government.