19005-SPC-832-01_Technical_Specifications_Rev_A_signed.pdf
PDF 5 MB Posted
- Attached to
- Tug to Replace Performance Federal contract opportunity
- Solicitation number
- 6923G520RTUGREPLACEMENT
About this file
Technical Specifications
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PREPARED FOR
1201 WESTERN AVENUE, SUITE 200
SEATTLE, WASHINGTON 98101-2953
T 206.624.7850
GLOSTEN.COM
INNOVATIVE
MARINE
SOLUTIONS
PREPARED CHECKED APPROVED
HT-60 HARBOR TUG
TECHNICAL SPECIFICATIONS
MASSENA, NEW YORK
SAINT LAWRENCE SEAWAY DEVELOPMENT CORPORATION
30 AUGUST 2019
FILE NO. 19005.01
DOC. NO. 19005-SPC-832-01
REV. A
Digitally Signed 30-Aug-2019
K. V. SULTANI-WRIGHT, PE PETER S. SOLES GARTH WILCOX, PE
PROJECT ENGINEER PROJECT MANAGER PRINCIPAL-IN-CHARGE
HT-60 Harbor Tug 30 August 2019 Technical Specifications i Job 19005.01, Rev. A
REVISION HISTORY
Section Rev Description Date Approved
All - Initial issue. 6/7/2019 GW
047.3 A Added four additional options for pricing. 8/30/2019 GW
073 Added rubber isolation for grating.
084 Added option for Massena delivery.
090.6 Added detail for bollard pull testing.
323 Added option for welder receptacle.
420.3 Added cell phone booster.
504.2 Added option for potable water tank TLI.
583.4 Added safety and damage control section.
Added option for hull tank and docking plug markings.
634.4.4 Changed carpet to rubber tile in staterooms. Added epoxy coating to plywood sub-flooring.
Changed stand-up desk to work bench with tool cabinet.
HT-60 Harbor Tug 30 August 2019 Technical Specifications ii Job 19005.01, Rev. A
TABLE OF CONTENTS
GROUP 0 GENERAL DESIGN AND CONSTRUCTION REQUIREMENTS
000 PROJECT DESCRIPTION
042 GENERAL ADMINISTRATIVE REQUIREMENTS
044 SHIP OPERATION
045 CARE OF VESSEL DURING CONSTRUCTION
070 GENERAL REQUIREMENTS FOR DESIGN AND CONSTRUCTION
071 ACCESS AND MAINTENANCE
073 NOISE AND VIBRATION
074 WELDING
075 MATERIALS
076 STABILITY
077 SAFETY
083 SPARE PARTS AND SPECIAL TOOLS
084 VESSEL DELIVERY
085 ENGINEERING DRAWINGS, REPORTS, AND SPECIFICATIONS
086 TECHNICAL MANUALS
087 FACILITIES
088 PERSONNEL AND TRAINING
089 VESSEL INSPECTIONS
090 VESSEL TESTS AND TRIALS
097 INCLINING EXPERIMENT
GROUP 1 HULL STRUCTURE
100 GENERAL
110 SHELL
114 SHELL APPENDAGES
120 STRUCTURAL BULKHEADS
125 TANKS, VOIDS, AND SPACES
130 DECKS
152 BULWARKS
167 HULL STRUCTURAL CLOSURES
168 UPTAKES
170 MASTS
171 FOUNDATIONS
GROUP 2 PROPULSION PLANT
200 PROPULSION
233 PROPULSION ENGINES
243 Z-DRIVES, PROPELLERS, AND SHAFTING
252 PROPULSION CONTROL SYSTEM
HT-60 Harbor Tug 30 August 2019 Technical Specifications iii Job 19005.01, Rev. A
259 ENGINE EXHAUST
GROUP 3 ELECTRICAL
300 GENERAL
302 ELECTRIC MOTORS AND EQUIPMENT
303 PROTECTIVE DEVICES FOR ELECTRIC CIRCUITS
304 ELECTRIC CABLE
305 ELECTRICAL DESIGNATION AND MARKING
310 SHIP SERVICE ELECTRICAL SYSTEM
311 SHIP SERVICE POWER GENERATION
313 BATTERY SYSTEMS
323 RECEPTACLES
324 SWITCHBOARD AND POWER PANELS
330 LIGHTING SYSTEM
GROUP 4 COMMUNICATIONS, NAVIGATION, AND SHIP CONTROL
400 GENERAL
410 CONTROL SYSTEMS
411 PILOTHOUSE OPERATING CONSOLE
412 Z-DRIVE CONTROL SYSTEM
420 NAVIGATION SYSTEMS
430 INTERIOR COMMUNICATIONS
431 ALARM AND MONITORING SYSTEM
GROUP 5 AUXILIARY SYSTEMS
500 GENERAL
503 PUMPS
504 INSTRUMENTATION AND INSTRUMENT BOARDS
505 PIPING
506 VENTS, FILLS, SOUNDS, AND OVERFLOWS
507 MACHINERY AND PIPING DESIGNATION AND MARKING
508 THERMAL INSULATION FOR PIPING AND MACHINERY
509 HEATING, VENTILATION, AND AIR CONDITIONING (HVAC)
510 MACHINERY ROOM VENTILATION
521 FIREMAIN AND BILGE SYSTEM
524 RAW WATER COOLING AND SEACHEST
526 DECK DRAINS AND FREEING PORTS
528 SANITARY DRAINS
533 POTABLE WATER
541 FUEL OIL SYSTEM
542 COMPRESSED AIR SYSTEMS
555 FIRE EXTINGUISHING
573 CARGO HANDLING
HT-60 Harbor Tug 30 August 2019 Technical Specifications iv Job 19005.01, Rev. A
582 MOORING AND TOWING
583 LIFESAVING SYSTEMS
GROUP 6 OUTFITTING
600 GENERAL
602 HULL DESIGNATING AND MARKING
603 DRAFT MARKS
604 LOCKS, KEYS, AND TAGS
611 HULL FITTINGS
612 RAILS, STANCHIONS, AND LIFELINES
613 RIGGING AND LINES
621 NON-STRUCTURAL BULKHEADS
622 FLOOR PLATES AND GRATINGS
623 LADDERS
624 NON-STRUCTURAL CLOSURES
625 WINDOWS AND PORTLIGHTS
631 PAINTING AND COATING
633 CATHODIC PROTECTION
634 DECK COVERING
635 INSULATION
640 ACCOMMODATION SPACES
661 PILOTHOUSE
662 MACHINERY SPACE
670 STOWAGE SPACES
HT-60 Harbor Tug 30 August 2019 Technical Specifications 1 Job 19005.01, Rev. A
GROUP 0 GENERAL DESIGN AND CONSTRUCTION REQUIREMENTS
000 PROJECT DESCRIPTION
This specification describes the technical and administrative requirements for the construction and delivery of an ice-capable 60 ft azimuthing stern drive (ASD) tug.
042 GENERAL ADMINISTRATIVE REQUIREMENTS
042.1 General
These Technical Specifications and associated Contract Drawings form the basis of the Contract Design Package. Additional detail design such as, but not limited to, lofting and foundations will be required of the Contractor to fully define the construction details. 5
In accordance with good shipbuilding practice, the Contractor shall furnish all materials, labor, and equipment required for construction of the vessel called out or otherwise referred to in this specification, excepting those items specifically identified as Owner-furnished equipment.
Items specifically identified as Owner-furnished equipment shall be installed by the Contractor in accordance with the recommendations of the manufacturer and tested by the Contractor to 10 demonstrate successful operation. The Contractor shall also perform any required or necessary detail design work.
The provisions of Group 0 shall apply to all sections of the Technical Specification and all addenda, appendices, and change-orders thereto, unless specifically exempted. In the event of a discrepancy between Group 0 and the provisions of other sections of this Technical 15 Specification, the provisions of Group 0 shall govern.
The Contract Drawings shall be considered contractually binding. The Contractor shall be responsible for reviewing all drawings provided by the Owner. Any discrepancies discovered by the Contractor shall be brought to the immediate attention of the Owner for resolution.
The technical requirements of this specification do not directly address all potential safety 20 issues. Crew safety shall be upheld by the Contractor as a fundamental guiding principle in the vessel detail design. The vessel shall be outfitted with all features, details, and equipment necessary for protecting the safety and health of the crew. All applicable USCG, ADA, US Public Health, EPA, and State requirements in way of crew access and safety shall be met by the Contractor. 25
042.2 Equivalent Equipment
The Contractor is not restricted to the manufacturer name, make and/or model number where specified or on the drawings. Such use is to invoke by reference the manufacturer’s specifications, quality, size, weight, and performance characteristics. Physical size and weight shall be considered as part of the performance characteristics.
The Contractor may propose, in writing, equivalent substitutions to these equipment selections 30 for the Owner’s approval prior to equipment ordering. The Owner’s decision on the acceptability of a substitution shall be final. The Contractor shall be responsible for all impacts due to substitutions.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 2 Job 19005.01, Rev. A
042.3 Optional Items
There are optional items described in this specification. The Contractor shall provide a cost estimate for each optional line item. The Owner will determine which options will be 35 activated. Optional line items are as follows:
1. Watertight bulkhead between Engine Room and Lazarette (Frame 21), see Section 120.1.
2. Stainless steel propellers, see Section 243.1.1.
3. Spare propellers, see Section 243.1.1. 40
4. Pivoting topmast, see Section 170.1.1.
5. Crane winch and top sheave, see Section 573.1.1.
6. Potable water level indication, see Section 504.2.
7. Welder receptacle on Aft Deck, see Section 323.
8. Tank boundary hull marking, see Section 602. 45
9. Delivery to Massena NY, see Section 084.
042.4 Buy American Requirements
This vessel is subject to Federal Acquisition and Jones Act Regulations which limit the amounts of foreign equipment content and foreign steel. Refer to actual regulations for complete details.
042.5 Terms, Acronyms, and Initialisms
The Contractor shall interpret terms, acronyms, and initialisms used throughout the 50 specification as follows:
ABS American Bureau of Shipping
AWS American Welding Society
ADA American with Disabilities Act
AGM Absorbent glass mat
AIS Automatic Identification System
ANSI American National Standards Institute
ASD Azimuthing Stern Drive (Z-drive)
ASTM American Society for Testing Materials
BWE Builders Weight Estimate
CFR Code of Federal Regulations
Contractor The business or firm under contract to construct and deliver the vessel.
CRES Corrosion resistant steel
HT-60 Harbor Tug 30 August 2019 Technical Specifications 3 Job 19005.01, Rev. A
DWL Design waterline
EPA Environmental Protection Agency
FCC Federal Communications Commission
FRL Filter regulator lubricator
GA General alarm
GFCI Ground fault circuit interrupting
GPS Global positioning system
HMI Human machine interface
HVAC Heating, ventilation, and air conditioning
HP Horsepower
HPU Hydraulic power unit
IACS International Association of Classification Societies
IEEE Institute of Electrical and Electronics Engineers
IMO International Maritime Organisation
ISO International Standards Organization
JW Jacket water
LED Light emitting diode
LVP Low voltage protection
LVR Low voltage release
MDFT Minimum dry film thickness
NEC National Electrical Code
NEMA National Electrical Manufacturers Association
Owner Saint Lawrence Seaway Development Corporation or other designated agents or employees of Saint Lawrence Seaway Development Corporation, to the extent that those individuals have been authorized by Saint Lawrence Seaway Development Corporation to act on its behalf.
OWS Oily water separator
PTT Push to talk prepare To develop or produce data or information for submittal and/or distribution to the Owner, or to regulatory bodies.
provide Design, purchase, install/integrate into the vessel, test and verify proper function for intended use.
RPM Revolutions per minute
SAE Society of Automotive Engineers
SCAC Separate circuit aftercooler
SNAME Society of Naval Architects and Marine Engineers
STW Speed through water
SWBS Ship work breakdown structure
TLI Tank level indicator
TVA Torsional vibration analysis
UL Underwriters Laboratories
USCG United States Coast Guard
HT-60 Harbor Tug 30 August 2019 Technical Specifications 4 Job 19005.01, Rev. A
VAC Volts alternating current
VDC Volts direct current
VFD Variable frequency drive
VHF Very high frequency
Z-drive Azimuthing Stern Drive
044 SHIP OPERATION
044.1 Operational Guidelines
The vessel shall be built to be operated by a two or three-person crew: one (1) master (on watch in the Pilothouse), and one (1) or two (2) deckhands, as circumstances require.
The vessel will operate from a base in Massena, NY.
The vessel’s mission consists of the following: 55
Commissioning, decommissioning, and servicing of fixed and floating aids to navigation in the Saint Lawrence River between Cornwall, Ontario and Cape Vincent, New York, and up to 10 miles into Lake Ontario.
Assist in transporting and maneuvering a 150 ft long by 60 ft wide by 7-8' freeboard deck barge (“Buoy Barge”), a 150 ft long by 75 ft wide by 3-10' freeboard heavy lift derrick 60 barge (Grasse River), and a 2-3' freeboard sectional spud barge.
Ice management operations.
044.2 Operating Environment
The vessel shall be capable of operating in a seawater and marine air environment. The vessel and its subsystems shall be capable of functioning in the environmental conditions listed in Table 1. 65
Table 1 Environmental conditions
Minimum Air Temperature -25°F
Minimum Seawater Temperature 28°F
Maximum Air Temperature 95°F
Maximum Seawater Temperature 85°F
045 CARE OF VESSEL DURING CONSTRUCTION
All parts of the vessel shall be maintained in good condition throughout the construction period. The Contractor shall adequately protect all items with finished surfaces to prevent damage during construction and final outfitting. The Owner may reject any materials and/or equipment improperly stored or handled. 70
Materials, equipment, and surfaces damaged or otherwise marred shall be repaired or replaced by the Contractor to the satisfaction of, and without additional expense to the Owner.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 5 Job 19005.01, Rev. A
A comprehensive and effective system of fire prevention, fire detection, and firefighting shall be maintained at all times during construction.
Periodic inspection of all spaces and tanks below the waterline shall be conducted when the 75 vessel is afloat, and at least two (2) pumps shall be readily available in the event that flooding is detected.
Rigid control of welding and grounding shall be maintained for the protection of the vessel’s hull, its systems, and its appendages. The Contractor shall adhere to the following requirements, at a minimum: 80
Any power source used for welding on the vessel shall not be used for any other vessel or structure.
Ground (return) cables attached to the vessel shall not be grounded to any other vessel or structure.
Welding and ground cables shall properly insulated. 85
Welding and ground cables shall be kept dry at all times.
Grounding lugs shall be tightly secured to grounding plates.
Contact surfaces between grounding lugs and grounding plates shall be periodically cleaned to base metal.
The Contractor shall be responsible for the insurance, climate-controlled storage in secure 90 buildings or warehouses, and periodic maintenance and handling of Owner-furnished equipment in accordance with the manufacturer’s requirements after delivery to the Contractor’s plant.
The Contractor shall also be responsible for climate-controlled storage in secure buildings or warehouses for post-Delivery items procured by the Owner during the construction of the 95 vessel.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 6 Job 19005.01, Rev. A
070 GENERAL REQUIREMENTS FOR DESIGN AND CONSTRUCTION
070.1 Vessel Characteristics
Table 2 General Characteristics
Length Overall, Moulded 60'-0"
Beam, Moulded 28'-0"
Depth, Main Deck 11'-6"
Draft, Navigational 10'-5 ¼"
Displacement 182 LT FW
Gross Tonnage (estimated) 75 GT
Range (estimated) 1,400 nm
Height of Eye 15'-8" (Pilothouse)
Performance
Bollard Pull (estimated) 18 ST
Speed (estimated) 10 kts
Tank Capacities
Fuel 11,300 gal
Potable Water 790 gal
Gray Water 600 gal
Black Water 165 gal
070.2 Regulatory Requirements
The vessel as delivered shall be constructed and outfitted in accordance with 46 CFR Subchapter C, Uninspected Vessels, and shall comply with all applicable federal regulations. 100
The vessel shall have a tonnage certificate indicating that the vessel admeasures less than 100 domestic gross regulatory tons.
The vessel shall not be classed; however, ABS Rules for Building and Classing Steel Vessels Under 90 meters (295 feet) in Length and Ice Class C0 shall serve as the design standard for hull structure, and Finnish-Swedish (Baltic) Ice Class IC shall be used for machinery. 105
The requirements of 46 CFR Subchapter M, Towing Vessels, shall be used to select and specify vessel equipment. The vessel is not intended to handle tank barges carrying oil or other hazardous materials in bulk.
071 ACCESS AND MAINTENANCE
Access arrangements for routine inspections, cleaning, and painting shall be provided for all compartments and other vessel spaces by means of permanent ladders, doors, manholes, 110 hatches, and bolted plates.
Partial obstruction or other restriction of access openings by pipes, valves, or other fittings shall be avoided to the extent practicable.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 7 Job 19005.01, Rev. A
Special consideration shall be given to vessel’s engine and machinery layout and design to facilitate clear and easy access for maintenance, removal/replacement, and cleaning. Access 115 arrangements shall consider, specifically: coolers, small (non-integral) tanks, electrical panels, valves, pumps, and other machinery items.
Battens, gratings, and protective casings around pipes shall be readily removable. Access closures shall be provided with proper gaskets, cover plates, fasteners, hinges, hasps and locks, as appropriate. 120
Monorails, padeyes, and lifting fittings shall be provided and attached to adequate structure, to permit equipment and machinery removals and installations.
Permanent fittings shall not be installed in a manner that obstructs or restricts paths for removal of machinery or equipment.
Passageways shall have a clear width (distance between protuberances) of at least 28". 125
073 NOISE AND VIBRATION
The Contractor shall be responsible for all elements of design and construction regarding noise and vibration on the vessel. During construction, and in the selection and installation of materials and equipment, the Contractor shall take steps to prevent or abate noise and vibration (both airborne and structural) throughout the vessel, to the maximum extent practicable.
Prior to the start of construction, the Contractor shall notify the Owner of any requirements set 130 forth in this specification or reflected in associated Contract Drawings that, in their experience, could result in excessive noise or vibration on the vessel.
These specifications call for specific measures to reduce noise and vibration levels in the vessel while operating. These measures include, but are not limited to:
Sound isolation mounts under all engines. 135
Flexible connections on all engine exhaust system components.
Flexible connections on Engine Room ventilation fans.
Composite (carbon fiber) driveshafts.
Sound isolation mounts and supports for hydraulic HPU and piping.
Rubber isolation strips on all grating supports under metal grating. 140
No specific vibration tests are required during trials; however, if the Owner observes excessive or objectionable vibration levels during trials or the warranty period, the Contractor will be required to locate and correct vibration parameters that exceed allowable levels, as defined in
ISO 6954:2000.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 8 Job 19005.01, Rev. A
074 WELDING
074.1 General
Careful consideration shall be given to assembly sequence and the overall shrinkage of plate 145 panels and assemblies, resulting from the processes employed. Welding shall proceed systematically with each welded joint being completed in correct sequence without undue interruption. Where practicable, welding shall commence at the center of a joint and proceed outwards or at the center of an assembly and progress outwards towards the perimeter so that each part has freedom to move in one or more directions. 150
Temporary welds incident to erection shall be carefully removed and flushed off by chipping or grinding.
Intermittent welding may be used where appropriate to minimize distortion and where oil-tightness or water-tightness is not required. However, intermittent welding shall not be used in locations exposed to the weather or water. 155
Structural welding will be carried out in such sequence as to compensate for shrinkage as the work progresses, prevent locked in stresses, and minimize distortion.
Structural steel may be manual or machine welded, depending on the Contractor’s standard practice.
Welds shall be neatly finished, with all spatter and slag removed, and ground flush where 160 required.
Welding bead sizing, lengths, and spacings shall be in accordance with ABS Rules for Building and Classing Steel Vessels Under 90 meters (295 feet) in Length.
074.2 Preparation
The preparation of plate edges shall be accurate and free from blemishes. Joints shall be properly aligned and closed or adjusted before welding. Means shall be provided for holding 165 the work in proper alignment without rigid restraint during welding operations. Excessive force shall not be used in fairing and closing the work. Where excessive gaps exist between surfaces or edges to be joined, the corrective measures adopted shall be to the satisfaction of the Owner.
Before a manual sealing run is applied to the back of the weld, the original root run shall be cut back to sound metal. 170
Joint edges shall be scratch-brushed (or other acceptable method) immediately before welding to remove oxide or adhering films of dirt and filings.
074.3 Cleanliness and Environment
The surfaces in way of all parts to be welded shall be made clean, dry, and free from grease and other contaminants that might adversely affect weld quality, by cleaning with suitable chemicals or solvents. 175
The welding environment shall be in accordance with AWS D1.1, Section 5.12. Adequate protection shall be provided where welding is required to be carried out in exposed positions
HT-60 Harbor Tug 30 August 2019 Technical Specifications 9 Job 19005.01, Rev. A in wet, windy, or cold weather. Special precautions shall be taken to protect the building area from contamination by dissimilar metals (e.g., iron, steel, and copper).
074.4 Tack Welding
Consumables for tack welding shall be of the same grade as those used for the main weld. 180
Tack welds that are to be retained as part of the finished weld shall be clean and free from defects before being incorporated into the weld.
Care shall be taken when removing tack welds used for assembly to ensure that the material of the structure is not damaged.
Any defects in the structure resulting from the removal of temporary attachments shall be 185 prepared, welded, and ground smooth so as to achieve a defect-free repair.
074.5 Alignment and Fit
Workmanship shall result in fair lines and smooth surfaces.
Structure shall fit tightly without excessive gaps between seams, buckles, kinks or other surface irregularities.
Care shall be taken to obtain good alignment of structural members, particularly where such 190 members oppose each other on opposite sides of bulkheads or decks. Alignment shall comply with the tolerances specified in the IACS Rec. No. 47, Shipbuilding and Repair Quality Standard. Additionally, any cases where misalignment exceeds half the thickness of the thicker member shall be considered deficient and require correction. Where discontinuities of structure are unavoidable, suitable brackets or other reinforcement shall be installed. 195
The Contractor shall take every precaution to keep distortion and welding stresses to a minimum. Excessive unfairness in plating may be corrected by local spot-heating and quenching, provided such methods are approved by the regulatory bodies. Deviation and distortion of structural material shall, in general, be within the tolerances prescribed in IACS Rec. No. 47, Shipbuilding and Repair Quality Standard. Hull plating and all decks, interior 200 and exterior, shall have a maximum deformation of 1/8" between frames.
Shims, liners, “dutchmen,” or “sleepers” shall not be used for correcting improper fit. Clamps with wedges or strong-backs used for this purpose shall be suitably arranged to allow freedom of lateral movement between adjacent elements. Welded temporary attachments used to aid construction shall be removed carefully. 205
075 MATERIALS
Materials, machinery, and equipment provided by the Contractor shall be new, of current manufacture, and currently supported by spare parts readily available in the United States of America.
Materials, machinery, and equipment provided by the Contractor shall be of commercial marine quality, in full conformity with the technical requirements of this specification, and 210 suitable for the intended use.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 10 Job 19005.01, Rev. A
Critical vessel equipment shall have technical service available in New York State. Critical vessel equipment consists of main engines and Z-drives. All other systems shall have technical support available in the United States of America.
Dissimilar metals (not electrolytically compatible) shall not be directly joined. Electrolytic 215 corrosion shall be prevented by insulating dissimilar metals from one another by way of gaskets, washers, sleeves, or bushings made of insulating materials.
Except for machinery foundation shims, faying surfaces between materials (i.e. metals, laminates, or any combination thereof), shall be protected by the use of bedding compound(s) plus one coat of primer. Faying surfaces between wood and other materials shall be protected 220 by use of wood preservative-fortified bedding compound.
076 STABILITY
The vessel is designed to meet the following stability criteria in all loading conditions with service life allowance at trims ranging from 1 ft aft to 0.5 ft forward.
46 CFR §170.170, Weather.
46 CFR §173.095, Towing. 225
46 CFR §174.145, Intact stability for towboats.
46 CFR §173.020, Lifting (protected waters).
Any changes proposed to the design which significantly modify the weight distribution or hull and appendage shape shall be evaluated against these criteria at the Owner’s request.
After incline test, the vessel shall be evaluated against these criteria. 230
077 SAFETY
The vessel design shall reflect system and personnel safety considerations, including the elimination or minimization of the potential for human error during operation and maintenance, under routine, non-routine, and emergency conditions. System safety shall be integrated into the design to avoid hazardous manual handling operations as far as reasonably practicable and shall limit activities to the required range of physical capabilities. Human-machine interfaces 235 shall minimize the potential for and the consequences of human error.
Safety guards shall be installed over the unprotected moving parts of rotating or oscillating equipment and machinery that could pose a hazard to personnel.
083 SPARE PARTS AND SPECIAL TOOLS
As each new machinery/equipment item is ordered, the Contractor shall submit to the Owner a list in Microsoft Excel format of the manufacturer’s recommended spare parts and special 240 tools. The list shall include the unit price of each spare part and the manufacturer’s part number and include diagrams or drawings as necessary. The Owner reserves the right to procure any items from the list at the unit price, submitted by change order.
All spare parts and special tools shall be placed onboard the vessel prior to delivery.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 11 Job 19005.01, Rev. A
084 VESSEL DELIVERY
The vessel shall be delivered at the shipyard, afloat and fully complete. 245
As an option, delivery shall be made to Massena, NY.
085 ENGINEERING DRAWINGS, REPORTS, AND SPECIFICATIONS
085.1 Contract Drawings
The Contract Drawings are listed in Table 3.
Table 3 Contract Drawing list
Drawing No. Title
19005-070-01 General Arrangement
19005-070-02 Lines Plan
19005-100-01 Structural Arrangement
19005-100-02 Foundation Details
19005-166-01 Fendering Arrangement
19005-240-01 Propulsion Shafting
19005-259-01 Stack Arrangement
19005-300-01 Electrical One-Line Diagram
19005-330-01 Lighting Arrangement
19005-512-01 HVAC System Diagram
19005-532-01 Firemain, Bilge, and Cooling
19005-533-01 Potable Water & Sanitary Drains System
19005-541-01 Fuel System Diagram
The Owner will make available all Contract Drawings in AutoCAD (*.dwg) file format for the Contractors use during, and only during, this vessel build. These files shall not be used for any 250 other purposes outside the scope of this vessel’s construction program.
085.2 Contractor Engineering
The Contractor shall perform the engineering, design, calculation, and investigative work necessary, and develop all working drawings needed for construction, outfitting, testing, and delivery of the vessel, as well as all other required deliverables (e.g. stability letter, certifications, reports, etc.). This encompasses all efforts required by USCG for approval. 255
Engineering work performed by the Contractor and/or any subcontractors shall be available to the Owner for review and comment throughout the design development.
085.3 Working Drawings
The Contractor shall develop working drawings for all hull, mechanical, and electrical systems identified by the Contract Drawings and this specification, using a numbering convention that follows the ship work breakdown structure (SWBS). The Contractor shall assume all risk 260 and/or liability associated with failure to obtain Owner approval in advance of construction.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 12 Job 19005.01, Rev. A
085.4 Submittal and Review of Working Drawings
Drawings shall be submitted by the Contractor in Adobe Acrobat (pdf) format, and in native format(s) (AutoCAD, ShipConstructor, Cadmatic, etc.), if requested. Editable AutoCAD drawings submitted to the Owner will be used for Owner's internal purposes only.
Contractual review of drawings will be carried out electronically, by way of pdf files and 265 Adobe Acrobat edit/comment functions. The Owner will review and return drawing comments to the Contractor, typically within 14 working days of receipt. Subsequent revisions will be reviewed by the Owner prior to the Contractor starting work on items affected by the revision.
The above review process shall not relieve the Contractor of responsibility for any deviations from the Contract Drawings and/or the requirements of this specification unless the Contractor 270 has called attention to such deviations in writing, and requested Owner approval at the time of submittal. Similarly, the above review process shall not relieve the Contractor of responsibility for any errors or omissions.
085.5 As-Built Drawings
The Contractor shall provide final revisions of all working drawings, termed As-built Drawings, that represent the vessel as delivered. 275
Not more than 30 days after delivery of the vessel, the Contractor shall furnish Adobe Acrobat (*.pdf) and AutoCAD (*.dwg) files for all drawings to the Owner. All drawings shall follow the general format of the Contract Drawings. An index of the drawings furnished shall also be provided.
The Contractor shall place on board the vessel at time of delivery, 11" x 17" drawings for use 280 by the crew. These shall include drawings as listed on the drawing index, in their latest revision at time of delivery. The following items shall also be supplied with the vessel upon delivery:
Inclining experiment/stability test data.
Three (3) revised copies of the stability letter with operating instructions and example loaded conditions for satisfactory vessel stability and trim. 285
Two (2) copies of all machinery test documents with performance data recorded.
Three (3) copies of all stability calculations.
One (1) copy of the GHS computer model used for stability calculations.
Two (2) copies of the hull lines plan.
The Contractor shall update all working drawings and stamp or otherwise clearly mark 290 “FINAL AS-BUILT” in the title block. The Contractor shall ensure that all As-built Drawings accurately reflect the systems and arrangements of the vessel as finally completed and accepted by the Owner.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 13 Job 19005.01, Rev. A
085.6 Vessel Record Plans and Vendor Drawings
The following additional drawings shall be developed by the Contractor (unless fully incorporated in an As-built Drawing) and furnished to the Owner not more than 30 days after 295 delivery of the vessel:
Docking plan, showing location of all sea chests, transducers, thrusters, overboard discharges, anodes, and hull fittings/attachments.
General arrangement drawing.
Machinery arrangement drawing. 300
Lifesaving and fire equipment plan.
Switchboard wiring diagrams.
Elementary and isometric wiring diagram of lighting, power, and electronics systems (one-line diagram).
Detail wiring diagram, wire list, and terminal board layouts for alarm and sensor systems. 305
Master cable schedule.
Operational piping and instrumentation diagrams for all pipe and system drawings.
Drawings shall include specification for the system volume.
Consolidated set point list for instrumentation and controls, including all vendor-supplied equipment. 310
Consolidated hull valve list, including valve specifications.
086 TECHNICAL MANUALS
The Contractor shall prepare and provide a complete vessel Operating Manual. One (1) paper copy and one (1) electronic copy of the Operating Manual shall be provided to the Owner at least seven (7) days prior to the agreed-upon delivery date.
The operating manual provided shall contain at least the following information: 315
Main particulars of vessel.
Description of the vessel and its equipment.
List of openings and doors to be kept closed at sea.
Description and operation of systems (machinery, auxiliary, remote control and warning, electrical, fire protection, radio and navigational aids). 320
Stability report and letter detailing loading procedures and limitations.
Details of life saving appliances.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 14 Job 19005.01, Rev. A
Emergency operation.
Note that this manual is to be provided in addition to the machinery and equipment documentation requirements outlined below. 325
The Contractor shall provide bound instruction books for all unique machinery, equipment, and systems provided by the Contractor, whether manufactured by the Contractor or not.
Manufacturer supplied manuals are acceptable for standard equipment items installed on the vessel. The instruction books provided shall, at a minimum, contain:
Complete theory of operation, as well as complete operating, installation, maintenance, 330 troubleshooting, and repair instructions (including parts lists). This shall be provided in sufficient detail for operating personnel to operate, maintain, and repair the equipment.
Maintenance instructions listed in tabular form including recommended periodicity for completion of specific maintenance tasks. The parts lists shall be complete (including part descriptions) such that replacement parts can be easily identified and ordered. 335
Assembly plans (e.g. exploded view drawings), section view drawings, schematics, wiring diagrams, and line art as necessary to properly identify the various parts of the assembly. The parts lists shall be keyed to the plans and line art to provide identification of the various parts. Diagrams shall contain complete information such as pump and fan characteristics, pipe or duct sizes, materials, flows, velocities (normal and maximum), 340 pressure drops and other pertinent design data such as associated components, identification and operation characteristics, including all control and alarm settings.
Items that are merely advertisements for other or related equipment shall be omitted.
Bold or magnified text, where required, to ensure clear understanding of procedures or other pertinent information. 345
Signed and completed test memoranda as required by this specification for the applicable equipment and/or systems.
Copies of all equipment certifications by the applicable regulatory bodies (e.g. USCG, FCC).
The Contractor shall not use operating manuals intended for final delivery to the Owner as 350 working manuals for installing, operating, or testing equipment. If the Contractor requires information for installing, operating, or testing equipment, additional manuals and/or information must be ordered expressly for that purpose with any associated cost borne by the Contractor. Instruction manuals and books clearly showing misuse will not be accepted by the Owner. 355
The Contractor shall provide an Equipment Identification List with complete nameplate data, including serial number, for each piece of machinery and equipment installed on the vessel.
One paper copy and one electronic copy of the Equipment Identification List shall be provided to the Owner not later than one (1) week prior to the agreed-upon delivery date.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 15 Job 19005.01, Rev. A
087 FACILITIES
The Contractor shall provide secure warehouse/storage facilities with cover and 360 ventilation/heat as required to properly store all equipment prior to installation on the vessel.
The Owner shall have access to the warehouse facility to inspect equipment upon delivery, provided the equipment is readily accessible (i.e. not enclosed in crates or cases that inhibit inspection).
In cases where equipment is not readily accessible, the Contractor shall notify the Owner when 365 such equipment is uncrated or otherwise available for inspection.
088 PERSONNEL AND TRAINING
Following the Acceptance Trial, the Contractor shall provide 16 hours (two days) of operational training for the vessel’s crew. Operational training shall consist of vessel operation and maneuvering, including fire and safety drills, machinery operation, and maintenance instruction. 370
During operational training, the Contractor is solely responsible for the vessel and shall provide a licensed master and one deckhand as designated operators. Technical representatives from the manufacturer of the main engines, propulsion controls, and vessel’s electrical system shall be present for the duration of the training.
089 VESSEL INSPECTIONS
The Owner, Owner’s Representatives, and Owner-contracted personnel shall be granted 375 unrestricted access to the vessel throughout the duration of the contract. As a condition of access, personnel attending the vessel under the terms of this section will be required to carry their own insurance for Contractor’s liability coverage. Every effort will be made by attendees to minimize interference with the Contractor’s work.
090 VESSEL TESTS AND TRIALS
090.1 General
Tests, trials, and related inspections shall occur in stages, such that problems associated with 380 defective or improperly specified equipment, deficient designs, improper equipment installation or construction, or other causes, can be identified and remedied as early as possible.
To that end, test programs and procedures shall be developed in writing for the following test stages, as applicable to each work item, material, equipment, or system to be tested:
Shop Tests 385
Construction Inspections and Tests
Operation and Dock Trials
Contractor’s Sea Trials
Acceptance Trials
HT-60 Harbor Tug 30 August 2019 Technical Specifications 16 Job 19005.01, Rev. A
Any defects that develop or become apparent following these tests shall be repaired or 390 otherwise resolved by the Contractor at their expense.
All tests shall be conducted by the Contractor and/or its subcontractors at the Contractor’s expense.
Tests shall be conducted during normal business hours; and the Owner and regulatory bodies shall be notified a reasonable period in advance of test scheduling, so that they may arrange to 395 be present for any and all of these tests.
The attendance and witnessing of tests by the Owner shall in no way relieve the Contractor of their contractual responsibilities and obligation as described in this specification.
The Contractor shall also provide all personnel required to conduct the tests and to record the data. 400
090.2 Shop Tests
Shop tests shall be conducted by the manufacturer for all major equipment, systems, and assemblies listed below for verification of proper manufacture, assembly, function, and conformity with performance criteria prior to shipment. The Contractor shall require inspections and tests as discussed in this subsection by way of contractual agreement with the manufacturer. 405
Shop inspections and tests shall be conducted in accordance with the recommendations of SNAME Technical and Research Bulletin No. 3-39, Guide for Shop and Installation Tests, supplemented by any additional requirements of the regulatory bodies, the requirements of this specification, and the standard operating practices of the equipment manufacturers.
Stage 1 of the test, trials, and inspections program shall consist of at least the following shop 410 inspections and tests for the equipment items listed below:
Main Engines
Generators
Propulsion Control Systems
System Control Units 415
Accessory Power Systems
Generators shall be load tested using load bank(s) with adequate capacity to fully load each generator at its rated capacity. The load bank(s) shall be suitable for performing transient response tests and verifying governor and associated control system settings, safety trips, and interlocks. 420
Shop test reports shall be submitted to the Owner prior to shipment from the manufacturer.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 17 Job 19005.01, Rev. A
090.3 Construction Inspections and Tests
Construction inspections and tests are static demonstrations that precede operational testing.
These tests and inspections shall verify that equipment, systems, and fabricated construction materials are installed in accordance with the detail design and the requirements of the manufacturer, regulatory bodies, and this specification. 425
Construction inspections and tests shall be conducted in accordance with the recommendations of the applicable regulatory bodies and equipment manufacturers, and the requirements of this specification.
Stage 2 of the test and trial program shall consist of at least the following inspections and tests, conducted in accordance with Owner-approved test memoranda: 430
Cleanliness tests to verify cleaning and flushing of all piping systems fabricated and installed by the Contractor.
Hydrostatic testing (and/or pneumatic testing, where permitted) of all piping systems fabricated and installed by the Contractor.
Insulation resistance testing and point-to-point verification electrical cables and 435 connections installed by the Contractor.
Propulsion drive train alignment testing.
Static load testing of all load-bearing hull and/or fittings, including but not limited to padeyes, cleats, bitts, and chocks with a rated safe working load greater than 2,000 lbs.
Pressure testing of structural and independent tanks fabricated and installed by the 440 Contractor.
Tightness testing of weather deck doors, hatches, windows and other similar vessel features intended to prevent passage of liquid, gas, or atmosphere, including penetrations in watertight bulkheads and decks.
Calibration of instrumentation and associated documentation. 445
Welding inspections and quality assurance checks.
Protective coating inspections and quality assurance checks.
Hull fairness and alignment inspections and quality assurance checks of all structural fabrications.
All construction inspections and tests shall be carried to the satisfaction of the applicable 450 regulatory bodies and the Owner.
090.4 Operation and Dock Trials
Dock trials consisting of simultaneous dockside operation of the diesel generating plant, propulsion system, propulsion plant controls, and associated auxiliaries shall be conducted to demonstrate readiness for sea trials. In addition, certain installation, operational, and
HT-60 Harbor Tug 30 August 2019 Technical Specifications 18 Job 19005.01, Rev. A performance tests unrelated to the machinery plant, but of particular interest in preparation for 455 sea trials, shall be conducted as part of dock trials, as specified in this subsection.
Dock trials shall be performed in accordance with the recommendations of SNAME Technical and Research Bulletin No. 3-47, Guide for Sea Trials, supplemented by any additional requirements of the regulatory bodies, the requirements of this specification, and the recommendations of the equipment manufacturers. 460
Dock trials shall consist of at least the following:
Main Engine and Ship Service Diesel Generator Tests. These tests shall include: 1) non-operational cold checks of the engines; 2) operational tests; and, 3) other applicable tests, such as basic coolant and lubricant level checks prior to, and during equipment operation.
Operational tests shall confirm proper operation of monitoring instrumentation, 465 shutdowns, alarms, speed-limiting devices, and overspeed trips. Main engines shall be run under full load for 8 hours. Generators shall also be test run under load with auxiliary system equipment.
Auxiliary Systems Tests: Operational tests shall be conducted for each of the following systems: 470 o Fuel System.
o Firemain and Bilge System.
o Potable Water and Sanitary Drain Systems.
o Auxiliary Cooling Systems.
o Heating Ventilation and Air Conditioning (HVAC) Systems. 475 o Compressed Air System.
Lighting Systems Tests. All internal communication systems required for vessel operations and safety shall be functionally demonstrated.
Thermographic Tests. All electrical switchboards, distribution panels, and power connections shall be tested by an independent contractor with experience reporting on 480 shipboard electrical thermographic test results. Dockside thermographic testing shall include all electrical systems that can be powered up safely at the pier.
Radio Equipment Tests. All radio equipment shall be tested for proper operation and performance, including tests for radio interference.
Navigation Equipment Tests. All electronic navigation and sounding equipment, 485 associated alarm systems, and the vessel’s whistle shall be tested for proper operation and performance. Proper installation of the compasses and all other navigation equipment shall be verified.
Internal Communication Systems Tests. All internal communication systems required for vessel operations and safety shall be functionally demonstrated. 490
HT-60 Harbor Tug 30 August 2019 Technical Specifications 19 Job 19005.01, Rev. A
Emergency and Lifesaving Equipment Survey (for proper stowage and provisioning only).
090.5 Sea Trials
Builder’s sea trials shall be conducted at sea, prior to acceptance trials, to check the operation of the machinery installations; make any necessary adjustments to establish proper operation;
verify conformity with vessel, equipment, and systems performance requirements; and to 495 assess/establish the vessel’s readiness for acceptance trials.
Builder’s sea trials shall be performed in accordance with the requirements of this specification, supplemented by any additional requirements of the regulatory bodies, and the recommendations of the equipment manufacturers.
The vessel shall be loaded to 50% of the maximum displacement when the displacement of the 500 vessel will impact test results. Weights shall be secured to prevent shifting during trials. All speed trials shall be conducted on reciprocal courses in calm waters with no detectable tidal or wind driven surface current. Fore and aft vessel freeboards shall be recorded for all tests.
Builder’s sea trials shall include the following trial events and related tests, conducted in accordance with Owner-approved test memoranda. Other tests and trials can be carried out at 505 the Contractor’s discretion:
Auxiliary System Tests: Auxiliary systems and components that could not be fully tested during dock trials shall be tested during Builder’s sea trials.
Thermographic Testing: Any thermographic testing that could not be performed safely at full power during dock trials shall be completed or repeated during Builder’s sea trials. 510
Machinery Plant Control System Tests: This test shall be conducted to demonstrate proper operation of all control systems. Control system tests shall include local and remote stations and emergency controls.
Loss of Electrical Power Test: This test shall be conducted to demonstrate safe operation of the vessel and proper function of emergency backup systems during a simulated loss 515 of electrical generating power and electrical battery power.
Navigation Equipment Tests: The purpose of this test is to adjust and calibrate the navigation equipment. Compasses and electronic navigation equipment shall be adjusted and calibrated as appropriate during initial phases of Builder’s sea trials. The Contractor shall demonstrate the mechanical and electrical intrasystem and intersystem adjustments, 520 and alignment of the steering gear with the vessel’s rudder angle indicators and autopilot.
Speed Trials: The purpose of this trial is to develop a speed vs. rpm graph for the vessel.
Shaft speed shall be increased in even increments and recorded (along with vessel speed through water (STW)), beginning with the required shaft speed to achieve a STW of approximately 4 knots, and finishing at maximum shaft RPM. This trial shall result in 525 not fewer than five speed data points. Average speed, vessel trim, and propulsion motor power shall be recorded.
HT-60 Harbor Tug 30 August 2019 Technical Specifications 20 Job 19005.01, Rev. A
Ahead Endurance Trials: The purpose of this trial is to confirm the propulsion system, and its associated systems, can withstand rigorous use. This trial shall be conducted at the maximum continuous service rating of the enginess for a continuous period of not 530 less than 4 hours.
Astern Trial: The purpose of this trial is to document the maximum astern speed of the vessel. Shaft speed shall be increased in even increments and recorded (along with vessel speed through water (STW)), finishing at maximum shaft RPM. This trial shall result in not fewer than five speed data points. Average speed, vessel trim, and propulsion motor 535 power shall be recorded. Note that this test shall be adjusted to avoid dangerous situations such as but not limited to water on deck, excessive vibration, and excessive cavitation or ventilation.
Ahead and Astern Steering Test: The purpose of this test is to document the maneuvering capability of the vessel. Average speed, vessel trim, position, heading, and propulsion 540 motor power shall be recorded. Trials shall be conducted at a slow and constant “maneuvering” speed, both ahead and astern, and at full propulsion motor power, ahead only.
Quick Reversal from Ahead to Astern Test: The purpose of this test is to confirm proper operation of the vessel in an emergency stopping maneuver. Starting speed, stopping 545 time and head reach shall be recorded.
090.6 Acceptance Trial
Acceptance trials shall be carried out for the purpose of demonstrating vessel conformity with this specification and as a prerequisite to regulatory certification and acceptance of the vessel by the Owner.
Acceptance trials shall be carried out in accordance with the requirements of this specification, 550 supplemented by any additional requirements or recommendations of the regulatory bodies and the recommendations of the equipment manufacturers.
The…
This is the start of the file's text. The full file is on GovTribe.