This document is a Questions and Answers (Q&A) file for the 2026 WFL Architect/Engineer Indefinite Delivery/Indefinite Quantity (IDIQ) Request for Proposal (RFP) with solicitation number 69056726R000004. Key details include clarifications about proposal submission requirements: the organization chart may be submitted on an 11x17 page (all other pages must be 8.5x11), only the first six project examples will be evaluated, and a Subcontracting Plan is not required for the RFQ. Firms can submit proposals for the WFL AE Design IDIQ with limited Construction Management and Construction Inspection support services, and the AE Design IDIQ and CM/CI Support IDIQ are separate and independent procurements. Additionally, proposers may respond as a prime contractor and simultaneously be a subcontractor for another prime, and proposal cover sheets and cover letters will not be presented to the evaluation team.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE QUESTION ANSWER
12/12/2025
Can we show our IDIQ contract as a representative for Section F example projects?
An IDIQ is not a project. Page 8. If more than six examples are provided, the first six examples presented will be evaluated and the remainder will not beconsidered.
12/12/2025 Can the organization chart be presented on an 11x17 page? See Amendment 002. All pages must be 8.5 X 11 with the exception of the organization chart may be an 11x17
12/16/2025
Are firms able to submit a proposal for the WFL AE Design IDIQ with the understanding that their role would be limited to providing Construction Management and Construction Inspection support services? Yes.
12/16/2025 are the AE Design IDIQ and the CM/CI Support IDIQ considered separate procurements, or are they intended to be awarded and administered together? Separate and Independent IDIQs.
12/24/2025
Could you please confirm our team’s interpretation of the solicitation that a Subcontracting Plan is NOT necessary to submit with our Statement of Qualifications? Subcontracting Plan is not required for the RFQ.
12/24/2025
Could you please confirm if prospective proposers may submit a proposal cover sheet and cover letter as part of our Statement of Qualifications? Will not be presented to the evaluation team.
General question Can we respond as a prime and be a subcontractor for another prime? Yes.
Questions and Answers for Request for Proposal 69056726R000004 2026 WFL Architect/Engineer IDIQ