This document is a Questions and Answers (Q&A) file for a road infrastructure project involving Hawk Creek Road Improvements and Hawk Creek Road Stabilization. The project is associated with WA FLAP LINCOL 57860(1) and WA NPS LARO 208(1), suggesting involvement of federal agencies such as the National Park Service (NPS) and potentially a Federal Lands Access Program (FLAP). The Q&A entry shows a general inquiry about the project's timeline, with the respondent confirming the project is still anticipated to be advertised during the winter, with a response date of 11/13/25. No specific details about the road improvements, stabilization work, budget, or technical specifications are provided in this document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA FLAP LINCOL 57860 (1), & WA NPS LARO

208(1), Hawk Creek Road Improvements &

Hawk Creek Road Stabilization

# General Technical Question Answer Date

1 X

I wanted to reach out and see if this was still going to drop during this winter or based on the shutdown if it is going to slide to the right a bit. I wanted to check and see if there was a new estimated drop date or time frame.

We are still anticipating that this project will be advertised this winter.

11/13/25

Check General or Technical