This document is a detailed bid schedule for the Hawk Creek Road Improvements & Road Stabilization project located 30 miles northwest of Davenport, Washington. The project involves 0.68 miles of road work with an estimated price range between $5 and $10 million, targeting completion in Summer/Fall 2026. Key project elements include earthwork, grading, base preparation, paving, drainage, soil nail retaining walls, and guardrail installation.

The comprehensive project scope spans multiple divisions, including project requirements, earthwork, slope reinforcement, aggregate base courses, asphalt pavements, and incidental construction. Specific activities include clearing 4.5 acres, excavating 8,000 cubic yards, installing 1,350 linear feet of guardrail, placing 1,700 tons of asphalt concrete, constructing culverts, installing underdrains, establishing turf on 3.8 acres, and implementing environmental mitigation measures such as root wad installations. The project also includes extensive traffic control, erosion control, and landscaping components, with multiple construction survey, quality control, and testing requirements.

View the file

Other files

File Type Posted
QA_11-13-25.pdf PDF
Hawk Creek_Prelim Letter Update.pdf PDF
lincol57860(1)_PreAd PLAN.pdf PDF
Prelim Letter_Hawk Creek Road.pdf PDF
Project Description Hawk Creek Road.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA FLAP LINCOL 57860(1), Hawk Creek Road Improvements & WA NPS LARO

208(1), Hawk Creek Road Stabilization

This work consists of: Earthwork, grading, base, paving, drainage, soil nail retaining walls, and guardrail

Project Location: 30 Miles NW of Davenport, Washington

Project Length: 0.68 Miles

Estimated Price Range: Between $5 and 10 Million

Tentative Fixed Completion Date: Summer/Fall 2026

(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

O n e S ch ed u le

S ch

N am e

_A

DIVISION 150 – Project Requirements

152 Construction Survey & Staking (yes/no) Yes

153 Contractor Quality Control and Assurance (yes/no) Yes

154 Contractor Sampling & Testing (yes/no) Yes

155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes

157 Soil Erosion & Sediment Control (Stream Diversion) LPSM

157 Soil Erosion & Sediment Control (Fiber roll) 12,000 LNFT

DIVISION 200 – Earthwork

201 Clearing & Grubbing 4.5 ACRE

203 Removal of Structures & Obstructions (Removal of Headwall) 1 EACH

203 Removal of Structures & Obstructions (Concrete barrier) 142 LNFT

204 Excavation & Embankment 8,000 CUYD

204 Unclassified Borrow 17,000 CUYD e S ch ed

N

DIVISION 250 – Slope Reinforcement and Retaining Walls

251 Riprap 1,600 CUYD

257 Contactor-Designed Retaining Walls (contractor completed designs) LPSM

259 Soil Nail Retaining Walls 6,000 SQFT

DIVISION 300 – Aggregate and Base Courses

302 Minor Crushed Aggregate 2,050 CUYD

DIVISION 400 – Asphalt Pavements & Surface Treatments

403 Asphalt Concrete 1,700 TON

DIVISION 600 – Incidental Construction

601 Minor Concrete Structures (Concrete headwall for 54” culvert) 2 EACH

602 Culverts (24” pipe culvert) 115 LNFT

602 Culverts (54” pipe culvert) 65 LNFT

604 Catch Basins (Type 1) 2 EACH

605 Underdrains (French Drain) 105 LNFT

609 Gutter (concrete – minor structures) 600 LNFT

617 Guardrail (Type 2, Class A, Steel Post) 1,350 LNFT

619 Remove and Rest Gates 2 EACH

619 Remove and Rest Fence 43 LNFT

621 Monuments & Markers (construction survey & staking) (yes/no) No

622 Rental Equipment (yes/no) Yes

623 General Labor (yes/no) Yes

624 Topsoil (landscaping & related items) 3.8 ACRE

625 Turf Establishment 3.8 ACRE

626 Plants, Trees, Shrubs, Vines & Groundcovers (Cuttings, Willow Pole) 360 EACH e S ch ed

N

629 Rolled Erosion Control Products & Cellular Confinement Systems (turf establishment) 630 SQYD

633 Permanent Traffic Control (traffic control devices) 71 SQFT

634 Permanent Pavement Markings (traffic pavement markings) 28,500 LNFT

635 Temporary Traffic Control – Flagger LPSM

635 Temporary Traffic Control – Plastic Fence 875 LNFT

647 Environmental Mitigation (Root Wad) 19 EACH

647 Environmental Mitigation (Root Wad, anchored) 7 EACH