OR FLAP DOT CRGNSA 100(8), Multnomah Falls Viaducts Repair
Solicitation number
69056723B000019
Issued by

About this file

This document is an amendment to a solicitation for repair work on the Multnomah Falls Viaducts. The amendment revises the special contract requirements section to update the language for the Class 2 rubbed concrete finish that is required for bridge superstructures, piers, piles, columns, abutments, retaining walls, arch rings, spandrel columns, abutment towers, pedestrian undercrossings, culvert headwalls and endwalls, and railings. The solicitation number is 69056723B000019 and is being issued by the Department of Transportation Federal Highway Administration for OR FLAP DOT CRGNSA 100(8), Multnomah Falls Viaducts Repair.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A002 09/21/2023 N/A See Box 14

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X

69056723B000019

9B. DATED (SEE ITEM 11)

09/05/2023

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers (__ ) is extended, ( x ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

N/A

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

N/A

D OTHER (Specify type of modification and authority) N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

OR FLAP DOT CRGNSA 100(8), Multnomah Falls Viaducts Repair

See page 2

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Amendment No. A002, dated 09-21-2023 OR FLAP DOT CRGNSA 100(8) Solicitation No. 69056723B000019 Multnomah Falls Viaducts Repair

REVISIONS ARE AS FOLLOWS:

SPECIAL CONTRACT REQUIREMENTS

Page F-22, Subsection 552.16(b), Class 2 – rubbed finish. Revises the first paragraph of Subsection (2).

ENCLOSURES

Pages:

F-22

F-22 DIVISION 550

Special Contract Requirements Project: OR FLAP DOT CRGNSA 100(8), Multnomah Falls Viaducts Repair

(3) Surfaces to be buried and culvert surfaces above finished ground that are not visible from the traveled way or a walkway.

Begin finishing as soon as the forms are removed. Remove fins and irregular projections from all surfaces that are exposed or will be waterproofed. Remove bulges and offsets with carborundum stones or discs. Remove localized, poorly-bonded rock pockets and honeycombed concrete, and replace with sound concrete or packed mortar. Fill all holes with mortar in the same cement/aggregate ratio as the concrete being finished, and float to an even, uniform finish. A bonding agent may be used with the approval of the CO.

Clean and point form tie cavities, holes, broken corners and edges, and other defects. Saturate the area with water. Finish the area with mortar that is less than 1-hour old. After the mortar is set, rub it (if required) and continue curing. Match exposed surfaces to surrounding concrete.

Carefully tool and remove free mortar and concrete from construction and expansion joints.

Leave joint filler exposed for its full length with clean, true edges.

Rub or grind bearing surfaces on piers and abutments to the specified elevation and slope.

If the final finished surface is not true and uniform, rub it according to Subsection 552.16(b).

Delete paragraph (b) and substitute the following:

(b) Class 2 – rubbed finish.

(1) Finish the following surfaces with a Class 2 rubbed finish:

(a) Surfaces of bridge superstructures except those surfaces designated to receive a Class 1 or other finish;

(b) Surfaces of bridge piers, piles, columns and abutments, and retaining walls above finished ground and to at least 12 inches below finished ground;

(c) Surfaces of open spandrel arch rings, spandrel columns and abutment towers;

(d) Surfaces of pedestrian undercrossings except floors and surfaces to be covered with earth;

(e) Surfaces above finished ground of culvert headwalls and endwalls when visible from the traveled way or walkway;

(f) Inside surfaces of culvert barrels higher than 48 inches that are visible from the traveled way. Finish for a distance inside the barrel at least equal to the height of the culvert; and

(g) Surfaces of railings.

(2) Complete a Class 1 finish according to Subsection 552.16(a); and Create a Class 2 rubbed finish according to steps (a)(1) through (f)(6), below.