About this file

This document contains answers to technical questions regarding Federal Highway Administration Solicitation Number 69056722B000006 to replace the Dickey Creek bridge in Washington. The project will widen and lengthen the existing structure to safely accommodate all vehicles, bicyclists, and pedestrians while reducing flood impacts and restoring natural river processes. Questions addressed include confirming that oversized shafts can facilitate permanent casing installation, and that guidance on casing thickness and material will be provided in Amendment A001. The Department of Transportation is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to WA KITTITAS 5880(1)DICKEY CRK BRIDGE, newest first.
File Type Posted
BidTabulation_WA KITTITAS 5880(1).pdf PDF
BidSum_WA Kittias 5880(1).pdf PDF
Interested Vendors List as of 6_17_22.pdf PDF
Q_A 16-jun-22.pdf PDF
Amendment A001.pdf PDF
DickeyCreekBridge_Floodplain_Memo.pdf PDF
Dickey Creek Bridge - 2019 Bridge Safety Inspection Report.pdf PDF
DickeyCreekBridge_Waterway_Hydraulics_Memo.pdf PDF
Kittitas 5880(1) Clearing Limits.pdf PDF
Kittitas 5880(1) Base Layer Staking Notes.pdf PDF
Kittitas 5880(1) Vt Alignment - Existing.pdf PDF
Kittitas 5880(1) Hz Alignment - Driveway.pdf PDF
Dickey Creek Bridge - 16203_Teanaway_LoadRating_Final.pdf PDF
CompiledSWPPP_WA KITTITAS 5880signed.pdf PDF
GR15-21 Dickey Creek Bridge Replacement Geotech Recomendations Rev. 1.pdf PDF
Kittitas 5880(1) Subgrade Staking Notes.pdf PDF
Kittitas 5880(1) Superelevation Report - Realign.pdf PDF
waa-kittitas5880-Final Planset.pdf PDF
Dickey Creek Bridge - 1963 Bridge Plans.pdf PDF
DickeyCreekBridge_Scour_Memo.pdf PDF
Kittitas 5880(1) - Final XS.pdf PDF
Kittitas 5880(1) Slope Stakes Notes.pdf PDF
Kittitas 5880(1) Vt Alignment - Realign.pdf PDF
Kittitas 5880(1) Hz Alignment - Existing.pdf PDF
Kittitas 5880(1) Earthwork End Area Volume Report.pdf PDF
Additional physical data.zip ZIP file
IFB_69056722B000006_DickeyCrkBridge.pdf PDF
Dickey Creek Bridge - Repair As-Built.pdf PDF
Kittitas 5880(1) Vt Alignment - Driveway.pdf PDF
Kittitas 5880(1) Hz Alignment - Realign.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. WA KITTITAS 5880(1) Project : Dickey Creek Bridge

# General Technical Question Answer Date

1 X

Since these shafts have rock sockets, is it acceptable to drill an oversized shaft to facilitate the installation of the full depth permanent casing?

yes 9‐Jun‐22

2 X Is it acceptable to use permanent casing that is thicker than ¼” thick?

will be addressed under Amendment A001 9‐Jun‐22

3 X Can spiral weld pipe be used for the permanent casing?

will be addressed under Amendment A001 9‐Jun‐22