AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A001 03/02/2022 N/A See Box 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056721R000010
9B. DATED (SEE ITEM 11)
02/09/2022
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
WY NPS GRTE 2017(1), Moose Wilson Road Phase 1
See page 2.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A001, dated 03-02-2022 WY NPS 2017(1) Solicitation No. 69056721R000010 Moose Wilson Road Phase 1
REVISIONS ARE AS FOLLOWS:
SPECIAL CONTRACT REQUIREMENTS
Page E-32, Subsection 108.01, Commencement, Prosecution, and Completion of Work.
Adds paragraph (f).
Page F-86, Subsection 636.07, Traffic Counter. Revises description of locations.
PLANS
Plan Sheet A.6 Adds Note 1.
Plan Sheet A.7 Adds Note 2.
Plan Sheet M.1 Revises quantity for Item No. 63602-6020.
ENCLOSURES
Pages:
E-32
Plan Sheets:
A.6 through A.7 M.1
12-07-2021
2. See Levee Access Road Staging Area quantities shown on Sheet D.1. Revised by Amendment A0011 1
Revised by Amendment A0011
E-32 DIVISION 100
Special Contract Requirements Project: WY NPS GRTE 2017(1), Moose Wilson Road Phase 1
Section 108. — PROSECUTION AND PROGRESS
04/02/21– FP-14
108.01 Commencement, Prosecution, and Completion of Work. Amend as follows:
Delete the text of the second paragraph and substitute the following:
A preconstruction conference will be held after the task order is awarded and before beginning work. Seven days before the preconstruction conference, submit copies of the preliminary construction schedule according to Section 155.
Add the following:
Furnish at least a 48-hour advanced notice before changing the current work schedule. Work schedule changes that include additional shifts require a 14-day advanced notice.
Perform work under this contract by limiting work as provided for in Sections 105, 107, 156, and 157; and the following.
(a) Do not perform work during the following periods;
(1) Between 3:00 p.m. Friday and 7:00 a.m. the following Tuesday of the Memorial Day and Labor Day weekends; and
(2) Between 3:00 p.m. Friday July 1 and 7:00 a.m. Tuesday July 5.
(b) Notify the CO 14 days prior to commencing any clearing activities.
(c) Irrigation Ditch Culvert. Install new culvert in John Miller Ditch (115+00) and Chicago Ditch (125+45), prior to Memorial Day weekend to avoid impacts to irrigation schedule.
(d) Moose Wilson Road Reconstruction from Station 125+00 to Station 290+20 and Overlay of LSRP (Laurance S. Rockefeller Preserve) Access Road. Perform work according to the following limitations;
(1) Complete base lift of pavement south of Kaufman Creek Bridge by October 30, 2022.
(2) No work on Moose Wilson Road north of station 160+00, including the Levee Access Road Staging Area and the LSRP overlay, will be allowed after May 25, 2023.
(e) Perform construction operations during daylight hours (see Subsection 156.08), or from 7:00am to 7:00pm, whichever is more restrictive.
(f) Winter shutdown for the project is November 1, 2022 through April 15, 2023.
108.01A Labor. (Added Subsection).
Follow the requirements of FAR Clause 52.222-6 Construction Wage Rate Requirements.
Revised by Amendment A001
02.28.2022
F-86 DIVISION 600
Special Contract Requirements Project: WY NPS GRTE 2017(1), Moose Wilson Road Phase 1
(4) Fuse holders, fuses, and cable disconnect devices;
(5) Wiring and connection diagrams of all cabinets, circuits, contactors, and ground rods;
and
(6) Grounding systems.
(e) Specify the brand name, any identifying numbers, relevant technical data, and any other information necessary for the agency responsible for maintenance of the system to procure exact replacements of any and all equipment and material used on the Project. Furnish new, equipment that is approved by Underwriters Laboratories, Inc. or other Nationally Recognized Testing Laboratory.
(f) Submit shop drawings of traffic counter systems (equipment and locations) for approval by CO according to Section 104.
636.05 Conduit. Add the following:
Maintain conduits clean and dry and protect ends of conduit with plugs, caps, or fittings.
Provide pull or splice boxes every 500 feet or less. If the conduit bends exceed 360 degrees of bend between any two pull or splice boxes, then add additional pull or splice boxes to bring the total amount of bends to under 360 degrees of bends between any two pull or splice boxes for ease of conductor pulling purposes. Install boxes at conduit ends, at all wiring splices, at all conduit angle points, and at all other locations shown on the plans. Additional pull or splice boxes to facilitate the work may be installed.
Provide pull or splices dictated by the diameter of the largest trade size conduit entering that pull or splice box and by the conductor size to be installed in that conduit.
(a) For #6 AWG and smaller conductors provide a box or conduit body with a length not less than six times the metric designator (trade size) of the largest raceway. Example: 2-inch diameter conduit with number 6 AWG conductors provide a box with the length of 12 inches minimum. (2 x 6 = 12).
(b) For #4 AWG or larger conductors provide a box or conduit body with a length not less than eight times the metric designator (trade size) of the largest raceway. Example: 2-inch diameter conduit with number 4 AWG conductors provide a box with the length of the box 16 inches minimum. (2 x 8 = 16).
636.07 Traffic Counter. Add the following after the first sentence:
At three roadway locations, Poker Flats, Woodland Crossing Moose Wilson Road 264+05, and LSRP Access Road 2+50, mount the controller/detector equipment inside cabinet on pole as shown on plans. Furnish and connect to solar panel system to power equipment. Furnish equipment that communicates traffic count information via modem/cellular data connection.
Revised by Amendment A001
03.01.2022