This document contains answers to technical questions regarding a federal solicitation to repair two bridges and replace a culvert on Denali Park Road in Alaska. The work includes minor bridge repairs with painting bridge rails, replacing a concrete box culvert, and conducting rockfall mitigation such as scaling, installing dowels and bolts, and other minor tasks. A July 1 notice to proceed date is specified with a performance period of just over two months. No coating is required for new sheet or king piles to be installed. While a limited earlier notice to proceed to begin procuring fabricated steel and concrete items was requested, the response indicates bidders should not assume one will be granted and should bid accordingly.

The related federal contract opportunity is for the above stated scope of work on Denali Park Road between mileposts 52 and 52.9 in Alaska's Denali Borough under Solicitation 69056718B000028 from the National Park Service within the Department of Transportation's Federal Highway Administration. The estimated price range for the project is $2-3 million.

View the file

Other files

Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No: AK NPS DENA 10(47) & 10(48) Project Name: Repair Two Denali Park Road Bridges and Culvert Replacement MP 52 & Rockfall Mitigation MP 52.9

# General Technical Question Answer Date

X Bid Item A0240 refers to railroad ties. Drawing B.1 shows it as well under Section G, Geotechnical Details. Could you clarify this, I don’t see railroad ties on the drawings or provided photos.

Will Be addressed under Amendment A002 20‐Apr‐21

2 X Do you have the sheet pile designation of the existing Toklat River Bridge sheet pile where we are to fasten the king pile to it, shown on G.17?

No, please bid accordingly 20‐Apr‐21

3 X Is there any coating required on the sheet pile or king pile that we are to provide and install per G.17 No, please bid accordingly

20‐Apr‐21

X

The completion date is predicated on a July 1 NTP date, with a performance period of just over 2 months. Would it be possible to get a limited NTP earlier to start procurement on fabricated steel and concrete items? No, please bid accordingly

20‐Apr‐21