636/22294. SMD; Riverside CF Building - Demolitions Project
Solicitation number
RFQ - 171 - 230000000369
Issued by
Ionia County, Michigan

About this file

This document is an Addendum to the Bidding Documents for the Riverside Correctional Facilities Building Demolition project in Ionia, Michigan, issued by the Michigan Department of Technology, Management and Budget (DTMB) State Facilities Administration Design and Construction Division. The addendum extends the contract length to December 31, 2023, provides additional asbestos sampling results, and includes clarifications and answers to additional questions. The project involves the demolition of multiple buildings at the Riverside Correctional Facilities site, and the bid opening date is April 26, 2023.

The addendum also notes that Addendum 2 combined the Deerfield and Riverside sites into a single contract with one bid form, which may affect bid bonding, permits, and similar facets of the bids. The addendum provides detailed information on the asbestos-containing materials found through additional sampling, including approximate quantities and locations. Bidders are instructed to review the addendum and acknowledge it in their bid submissions, as failure to do so may result in the bid being rejected.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 10/22)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND

BUDGET

State Facilities Administration Design and Construction Division

CONSTRUCTION BID ADDENDUM NO. 3

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

04/21/2023

PROJECT NAME

Riverside Correctional Facilities Building Demolition – Ionia MI

FILE NUMBER

636/22294.SMD

PROFESSIONAL

TriMedia Environmental

PROJECT DIRECTOR

Scott DeKorte

BID OPENING DATE:

4/26/2023

ADDENDUM ITEMS:

The contract length will be extended to December 31, 2023.

Note - Please review Addendum 2. Addendum 2 combines the Deerfield and Riverside sites into a single contract with one bid form. This may affect bid bonding, permits and similar facets of bids.

Additional asbestos sampling was performed (see attached table):

• Resampling of soffit fascia associated with Building R15 returned results indicating ACM. There is approximately 1,000 square feet of cementitious ACM associated with Building 15.

• The approximately 135 square feet of HID fixture shielding associated with Building R13a has been confirmed to contain asbestos.

• Samples of accessible tunnel sealant were collected at Building R13, R17, and R18. All collected samples returned results of “none detected”.

• Additional roofing samples from Buildings R12, R17, and R18 returned analytical results of “none detected”.

• Roofing materials associated with Buildings R13, R13a, R15, R16 are known to contain asbestos.

• Roofing materials associated with Building R9 and R14 remain as “assumed to contain asbestos”.

• 400-point count results for window glazing samples are presented in the attached table. Previous point count results are included in building HMA reports.

Additional questions and answers are attached.

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

PROFESSIONAL: Alexi Koltowicz – TriMedia Environmental and Engineering DATE: 04/20/2023 APPROVED BY: Scott DeKorte

DATE: 04/20/2023

http://www.michigan.gov/SIGMAVSS

PROJECT DIRECTOR:

Table 2 Materials Sampled and Found to Contain Asbestos State of Michigan

Riverside - Roofing Materials

Riverside - Point Count Results TriMedia 2022-3340

Sample # Location Material/Description Asbestos Concentration

R-15-101 Building 15 Roofing Fascia 18% Chrysotile

R-15-102 Building 15 Roofing Sealant 40% Chrysotile

R-13-101 Building 13 Roofing Membrane 14% Chrysotile

R-13A-101 Building 13A Heat Shield 35% Chrysotile

223340R-04-10 Glazing 1.50% Chrysotile

223340R-04-12 Tar Paper 0.25% Chrysotile

223340-R-03-07 Window Caulk 1.75% Chrysotile

223340-R-03-08 Inner Window Glazing 1.25% Chrysotile

223340-R-03-09 window glazing 1.50% Chrysotile

223340R-05-06 Building 5 Adhesive B 0.75% Chrysotile

223340R-02-01 Window Glazing 0.50% Chrysotile

223340R-02-05 Window Glazing <0.25% Chrysotile

223340R-18-36 Building 18 Glazing 0.4% Chrysotile

223340R-17-19 Building 17 Interior Glazing 0.4% Chrysotile

223340R-13-27 Interior Glazing 0.6% Chrysotile

223340R-13-28 Glazing 1% Chrysotile

223340R-13-29 Glazing 0.6% Chrysotile

223340R-13-42 Junction 1x1 Glue Pod 0.6% Chrysotile

Point Count Results

Roofing Material Results

Building 3

Building 2

Building 4

Building 13

Table 1 Materials Sampled and Found to Not Contain Asbestos State of Michigan

Riverside - Roofing Materials

TriMedia 2022-3340

Sample #

(Layers)* Location Material Description

R-6-101 Building 6 Sealant

R-13-101 Tar Layer

R-13-101 Tar Paper Layer

R-13-101 Insulation Layer

R-12-101 Built Up Roof

R-12-101 Tar Paper Layer

R-12-101 Insulation Layer

R-13-102 Buidling 13 Sealant

R-17-101 Sealant

R-17-102 Roof

R-18-101 Roof

R18-102 Sealant

*Material layers seperated in lab

Building 13

Building 12

Building 17

Building 18

Addendum 3

Deerfield / Riverside Questions and Answers

1. What types of underground utilities are required to be removed completely? Are there any that will be acceptable to be cut and abandoned in place?

Answer: All buried utilities shall be removed in full except active municipal lines which include a water main located on the east end of the subject property (Riverside) and a municipal sewer line located within the Riverside portion of the subject property. Known municipal utilities are marked on the provided site drawings. The Contractor shall coordinate with municipal or private utilities to cut, cap, and appropriately abandon service feeds for the subject property.

2. What kind of backfill material will be required?

Answer: The Contractor shall provide clean backfill material. Regarding, including the use of borrow material, will be allowed providing it does not negatively impact stormwater drainage of the subject property.

3. Will topsoil be required along with grass seed and mulch?

Answer: Restoration of the subject property shall be completed in accordance with MDOT specifications as referenced in the project specification. Site topsoil, including from borrow, may be used for site restoration.

4. Per the specifications, will the contractor workforce be required to maintain 51% minimum Michigan residency?

Answer: The Contractor shall meet specification requirements for prevailing wage and associated requirements.

5. The anticipated timeframe required for issuance of contract documentation once a selection is made (mid-May) will be difficult to achieve (essentially within 1 month) and quite possibly could cause the anticipated start date of June 2023 to be pushed. Taking into consideration our recent permitting experience on similar projects, the likelihood of getting the SESC & demo permit between notice of intent to award and the project start may not allow enough time. If there is a start date delay, will the project schedule be extended into Spring 2024? This should also be considered if restoration efforts of grass seed and mulch will be required since germination during winter months will be difficult at best, if not impossible to achieve.

Answer: The contract length will be extended until the end of 2023 per the issued addendum. Adjustments to contract length and project schedule may be considered on a case-by-case basis.

6. Is the contractor responsible for removing the gas utilities shown on Riverside Addendum #1 drawing M100?

Answer: The Contractor will be responsible for appropriately cutting and capping the gas supply line parallel to the access road (shown in drawing M100) in coordination with the utility supplier in the vicinity of the Limits of Demolition. The Contractor will not be required to remove the gas line to W. Riverside Drive.

7. Riverside Addendum #1 P.39 is small, difficult to read when blown up and not to scale. What extent of underground utilities are required to be removed on this sheet? Is there a better version to use as a reference?

Answer: The provided drawings are for reference only and do not constitute engineer drawings. All buried utilities within the limits of demolition, except in use municipal utilities, shall be removed by the Contractor.

If additional drawings are obtained, they will be provided to the Contractor.

8. Riverside Addendum #1 P.21 for building #13a shows a tunnel on the North side that is not reflected on Figure 2 provided in the bid set outlining the other tunnels. Is there also a tunnel here that needs to be removed? If so, do we know the extents?

Answer: During Hazardous Materials Assessment field work, the tunnel shown on the referenced drawing for Building 13A ends at an electrical service room (Shown in site photos associated with Building 13). No additional tunnel area to the north of the electrical service room was discovered.

9. The bid summary states that Builders Risk Insurance is required to be provided by the contractor unless otherwise indicated in the bid documents. The only other location in the specs we can see that Builders Risk is mentioned is in article 7.6.1 as pollution liability insurance. Is builders risk insurance going to be a requirement for this project?

Answer: Builder’s Risk Insurance shall be required for this project.

10. Is the requirement of the Alternate #1-3 pricing to provide a cost difference to leave the main R1, R2 & R6 structures in place, but demolish the attached silos for building R2 & R6 as well as any loose contents inside of all structures? Base bid is assumed to be complete removal of structures, silos, and interior contents complete. Please confirm.

Answer: The base bid shall include complete demolition of R1, R2, and R6. The requirements of Alternate #1-3 shall include removal of all loose contents from R1, R2, and R6 without any demolition of structures.

Potential demolition of silos associated with R2 and R6 may be addressed with the selected Contractor depending on the acceptance of Alternate #1-3.

11. Will demolished concrete & brick be allowed for use as backfill material? If so, will the bid date be extended to obtain vendor quotes for crushing operation?

Answer: No demolition debris will be allowed as fill.

12. Will as-builts or additional drawings be provided?

Answer: Available building and site drawings were provided in Addendum 1. These represent the extent of known drawings for the site.

13. Will an additional site visit opportunity be available?

Answer: No. The mandatory and non-mandatory site walkthroughs as listed in the specification will be the only available site visit opportunities.

14. Will the bid be extended?

Answer: No. The bid due date of April 26 will not be extended.

15. Are we able to backfill with crushed concrete or material on site? Is there a specification for type of backfill material required? Can the site be balanced with soil on site?

Answer: No building materials may be used for backfilling. Specifications for backfill material are provided in the project specification related to grading and restoration. Briefly, clean fill shall be used. Soil on site may be used for site balancing and adjustments to existing grade will be allowed, provided that grade adjustments do not negatively impact site drainage.

16. Is concrete (and asphalt) crushing allowed on site?

Answer: Yes. Crushing of recyclable concrete, masonry, and asphalt on site is allowed. Stockpiling of crushed material on site is allowed.

17. Is TriMedia providing all on site air monitoring for the project?

Answer: TriMedia will provide required clearance air sampling and appropriate perimeter air sampling related to asbestos abatement activities. TriMedia will not provide MIOSHA required personal air sampling of abatement workers. TriMedia may provide personal air sample analysis.

18. Will there be additional testing of assumed materials?

Answer: Additional sampling of some assumed materials has been completed and will be published with Addendum 2.

19. Is it possible to verify where water will be available and what hydrants are usable?

Answer: It is not possible to verify the availability of individual hydrants. The facility hydrants and lines are connected to municipal water in the southeast section of the subject property (Riverside). Hydrants throughout Riverside can potentially be charged; however, the working state of the mains and hydrants is unknown. The Contractor shall be responsible for coordination with the municipal utility operator and responsible for any water use charges.

20. Has owner removed all salvage materials from the site?

Answer: Yes. Remaining materials shall be the responsibility of the selected Contractor.

21. Are demolition permits being waved or should the associated fees be included in submitted bids?

Answer: No permits will be waived. The Contractor is responsible for obtaining necessary permits and any costs associated with necessary permits.

22. Will the project consider Minority Owned Businesses as covered by the Governor’s recent Executive Order?

Answer: Due to the project specification being developed prior to the final issuance of the executive order, classification as a minority owned business will not be used during contractor selection.

23. Will on site crushing be permitted?

Answer: Yes.

24. Will the entire tunnel system have to be removed?

Answer: Yes. All subsurface structures, regardless of depth below grade, shall be removed by the Contractor.

25. Can you clarify roof construction related to asbestos or assumed asbestos roofing materials?

Answer: Buildings R13, R16, R17, and R18 are known to have concrete roof decks.

26. Can you provide additional information related to assumed asbestos roofing material.

Answer: Additional full depth sampling of roofing material has been completed and analytical information is provided in the table included with Addendum 2. Not all roofing systems listed as assumed in the original Hazardous Materials Assessment will need to be managed as asbestos. Note that asbestos roofing materials have different requirements under MIOSHA regulations than other asbestos containing materials. Asbestos roofing does not have to be removed by licensed workers or contractors. Many commercial roofing companies are qualified to perform asbestos roofing removal.

27. Will the Contractor be required to remove materials which contain <1% asbestos prior to demolition?

Answer: No. Materials which contain <1% asbestos may be regulated by MIOSHA under historical interpretations; however, the building owner does not mandate removal prior to demolition.