6 QA dated Nov 14 24.pdf
PDF 155 KB Posted
- Attached to
- HVAC Replacement Norfolk International Airport
- Solicitation number
- 697DCK-25-R-00257
About this file
This document is a Questions and Answers (Q&A) document for the ORF HVAC Replacement Project, released on November 14, 2024. The Q&A covers 49 detailed questions and responses addressing various aspects of the project, including technical specifications, contractor requirements, site conditions, and project logistics. Key highlights include the project's estimated cost range of $2-3 million, a revised offer due date of November 25, 2024, and the involvement of the Federal Aviation Administration (FAA).
Critical details include requirements for the Commissioning Agency (CxA), which the contractor must provide and carry the contract and cost for, and flexibility in project phasing and scheduling. The project involves HVAC replacement at Norfolk International Airport, with specific requirements around equipment installation, controls integration, and on-site personnel. The bidders list includes E-Corp, TMG, Walsh Construction, Westpoint, and StructSure, and the FAA recommends following up on bid results in the first week of December 2024. No bid bond is required, but performance and payment bonds are mandatory.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A #2 for ORF HVAC Replacement Project
Due by: October 30, 2024
Released on: November 14, 2024
1. The previous solicitation for this opportunity removed the following proposal item (Reference
Volume II, Factor 2) by amendment, as it is more appropriate as a post-construction deliverable. We respectfully request that this narrative requirement be removed for this solicitation likewise for this round.
FAA Response: The amendment will reflect the same language used in the first proposal opportunity.
2. Please clarify the submittal instructions for the PPQ. Is the intended to be included in our proposal, as suggested by Factor 3: Past Performance, or submitted directly to the government.
FAA Response: We will accept PPQs submitted with the proposal as well as any submitted directly to us.
3. Please advise whether prior PPQs can be re-used as long as they contain identical information.
We have clients who will not fill in a PPQ more than once and we have been asked not to request more.
FAA Response: Re use of PPQs is permissible.
4. Please confirm that the Q&A responses issued with the RFP documents are official responses binding to the contract.
FAA Response: Confirmed that the Q&A responses issued are official responses binding to the contract.
5. Please confirm the Wage Rate Determination provided as the city of Norfolk does not lie within the boundaries of Mathews County Virginia.
FAA Response: DOL Wage Determination VA20240160 dated 11/8/2024 attached hereto and made a part thereof. The previous Wage Determination VA20240176 is hereby deleted.
6. RFI #11-18, 46, 47 Responses from the January 19, 2024 showed a significant deviation from the specification required staffing and Quality Control Specification Staffing Requirements. Please verify these answers are binding to the contract even if the specifications are not changed via amendment as there is significant cost and planning impacts to the answered deviation.
FAA Response:
Responses from the January 19, 2024 are still valid and should be used and referenced for bidding purposes.
7. Specification 23 08 20 "HVAC Commissioning - General" 1.1 C lists a pre-approved commissioning agency. "The statement The Commissioning Agency is referred to as an independent contractor in this Division and shall be a service provided by the Contractor for the FAA by a company approved by the FAA" is unclear when comparing to RFI #41 Answer "Commissioning is provided by a Commissioning Agency/Authority (CxA). The Commissioning Agency is to remain an independent party." Please verify that the contractor should carry the contract and cost for the services of the CxA.
FAA Response:
Confirmed. Commissioning is provided by a Commissioning Agency/Authority (CxA). The contractor should carry the contract and cost for the services of the CxA that is to remain an independent party and approved by the FAA prior to performing the commissioning services.
8. Is the phasing described in the project drawings, order of addressing, open to change through discussion with the FAA to determine the best method for accommodating a tight schedule?
Yes, the FAA will always be open to any change if it proves to be better, benefits the agency, and reduces/eliminates work disruption.
9. Is the roof fire rated? During the site visit/jobwalk, there was verbal discussion that fire dampers were required on the roof penetration. However, these are not shown on the drawings. Please clarify and offer a response.
Complete set of as-built drawings for the facility (Original Blueprints) has been provided in
KSN under Issued For Bid_R library. If the requested information cannot be obtained from the as-built drawings, the contractor must conform to all applicable codes and standards for the location where the equipment/material is being installed.
10. Could you team please confirm that the controls for the HVAC temporary units are permissible to be by a local 5-day stat only and that no integration with the BAS is required?
FAA Response:
Only new/permanent equipment installed under the scope of this project shall be integrated into the existing controls system. Existing DDC system (Carrier front end and controls) must remain. No need to integrate temp units.
11. During the site visit/jobwalk, conversations were had about existing systems NOT moving (e.g.
pipe, conduit, ceilings, desks, operating systems) that might interfere with the demolition/removal and new work accessibility. These types of support infrastructure may need to be reworked to accommodate new duct/rooftop/AHU locations. Will it be permissible to move those items if necessary to remove and replace items associated with the new work?
Yes, it may be permissible to move those items as long as the following conditions are met:
• Approval is given by the RE prior to any work
• All items to return to their original condition after work is complete
12. Can you please provide the company name and contract information for the roofer we are required to contact to repair the roof? This information did not appear in the drawings or the previous Q&A.
Please see note #1 under SPECIAL NOTES in drawing sheet ORF-D-BLDG-G003.
13. Is a bid bond required?
FAA Response: No bid bond is required; however, performance and payment bonds are required.
14. What percentage of work could we reasonably expect to perform off-hours?
This cannot be expected beforehand as it fully depends on the resident engineer, TechOps, controllers, and several other working conditions. The contractor is strongly encouraged to submit a written request to the RE whenever there is a need/desire for work outside normal working hours.
15. Does the facility have attic stock of ceiling tiles that match the existing ceiling tiles in the different areas where ceiling needs to be removed that the contractor can use?
FAA Response:
Unfortunately, there is no ACT stock anymore. Please remove carefully and reuse. If tiles get damaged while removal, the contractor will be responsible for replacing them at no cost to the FAA. The replacement must match the existing.
16. Can the FAA provide us with existing ceiling tile (for the different areas impacted by above-ceiling work) previous submits or details (size, color, manufacturers)?
FAA Response:
Unfortunately, we do not have this information. However, a complete set of as-built drawings for the facility (Original Blueprints) has been provided in KSN under Issued For Bid_R library.
17. Drawing Sheet M301, Controls General Notes, Note #8 – Please provide more information on this note. What are the bandwidth and communication speed requirements?
FAA Response:
Existing DDC system (Carrier front end and controls) must remain. New equipment installed under the scope of this project shall be integrated into the existing controls system. The specs shall be consulted for any requirements to ensure all new units and equipment are seamlessly integrated into the existing DDC system.
18. Drawing Sheet M401, Detail 1/401, “Keyed Note” #5 – What is the fire rating at this wall (where the pipes penetrate the exterior wall)?
FAA Response:
Complete set of as-built drawings for the facility (Original Blueprints) has been provided in
KSN under Issued For Bid_R library. If the requested information cannot be obtained from the
19. Drawing Sheet S302, “Keyed Notes” #1 – Can the FAA please provide us with the load capacity of the existing steel joists to which this note refers? Or does one refer to the information on Drawing Sheet S402, Detail 5, Joist Schedule for this information?
FAA Response:
The contract documents direct the contractor to engage an engineer to determine the capacity of the existing joist, and develop any strengthening required to support the roof top units.
20. If additional structural joist support is needed that is unforeseen at pre-bid, will the additional cost be addressed with a change order?
FAA Response:
The bid shall provide cost for engineering and design to evaluate existing joist and develop strengthening plans. Any required strengthening work of the joists will be addressed with a contract change.
21. Is an Arc Flash Study required?
Arc flash analysis is required per specification section 260553, with arc flash labeling limited to the scope of work under this contract.
22. Can the FAA provide us with as-built architectural drawings or life safety drawings which show the fire ratings of all of the walls which could be penetrated for piping, ducting, electrical, or communication materials (e.g. conduit)?
FAA Response:
Complete set of as-built drawings for the facility (Original Blueprints) has been provided in
KSN under Issued For Bid_R library. If the requested information cannot be obtained from the
23. Can the FAA please provide HAZMAT surveys previously performed on the facility for the areas impacted by this endeavor’s scopes of work?
HazMat survey will be provided as requested.
24. Can the FAA please provide the Geotechnical Report?
Complete set of as-built drawings for the facility (Original Blueprints) has been provided in
KSN under Issued For Bid_R library. A geotechnical report is not available.
25. Can the FAA provide as-built drawings showing the potential/possible location of underground utilities? We would need to provide this to the utility scanning company in order get an accurate cost estimate.
Only as-built drawings available are for the facility (Original Blueprints).
26. Is there a water source onsite that can be used for construction purposes?
As per SECTION 01 50 00 - 2.1.C., contractor shall install water service as part of their temporary utility installation.
27. Is there a staging area designated for a construction office trailer and for construction materials? Could the FAA please provide a depicted overview of the area?
FAA Response:
The FAA will provide these areas onsite for the trailer and material to facilitate the contraction process. Exact designation will be specified after award.
28. Is there a temporary power source onsite that can be utilized for a construction office trailer?
Please refer to drawing E001, Electrical General Note #32.
29. Please confirm that the FAA is expecting a cost-loaded schedule if P6 is not being used.
The FAA will not mandate the use of Primavera P6. It is up to the contractor’s discretion to select the scheduling software. The FAA will ONLY request a copy (pdf, MS Project, MS Excel, etc.) of the schedule periodically for continuous updates.
30. Per Specifications 01 32 01, Part 2, Paragraph 1.1 “Software,” Paragraph “B” (the second “B”), B.1 – B.4 – Does the FAA still require these four items? If training is expected, how many hours of training does the FAA expect?
No, the FAA will not require these items.
31. Is the contractor required to provide an onsite construction office trailer for the FAA’s CORs?
Please refer to 01 33 00, Part 2, Paragraph 2.I.2, COR Trailer & Equipment.
No, COR trailer is not required.
32. If a COR trailer is required, please provide us with the expectation for size and furnishings.
No, COR trailer is not required.
33. Will the FAA be providing the Commissioning Agent or is this the responsibility of the
Contractor?
It is the responsibility of the contractor. Please refer to RFI #7.
34. Per Factor 3: Past Performance – please advise if the FAA will accept previously submitted
PPQs to be included in our proposals.
FAA Response: Previously submitted PPQs are acceptable and we encourage new PPQs.
35. Please advise if the construction sequence must be completed as stated on Drawing G003 or if it is open to revisions to better accommodate the tight Period of Performance.
FAA Response:
Yes, the FAA will always be open to any change if it proves to be better, benefits the agency, and reduces/eliminates work disruption. Please refer to RFI #8.
36. Please advise if the existing roof is fire rated. It was verbally communicated during the walk that fire dampers were required on the roof penetrations, but they are not shown on the bidding documents. Please clarify.
FAA Response:
Complete set of as-built drawings for the facility (Original Blueprints) has been provided in
KSN under Issued For Bid_R library. If the requested information cannot be obtained from the
37. Please confirm that the controls for the temporary HVAC units will be by a local 5-day stat only and that no integration into the BAS system is required.
Only new/permanent equipment installed under the scope of this project shall be integrated into the existing controls system. Existing DDC system (Carrier front end and controls) must remain. No need to integrate temp units. Please refer to RFI #10.
38. Please advise if a 19' scissor lift is permitted in the building for overhead work. Please note, this would not be required in the TRACON or computer rooms, only in general spaces where it is necessary for safe access.
FAA Response:
Yes, small scissor lift will be permitted only after obtaining approval from the Resident
Engineer. Scissor lift must be small enough to not pose any hazard to the locals and the facility.
39. Equipment Alternates: Please advise if alternates will be considered for the specified equipment. Specifically, would alternate models for exhaust fans, VAVs, ATUs, AHUs, RTUs, and Liebert units be acceptable, provided they meet project specifications and performance requirements.
FAA Response:
The models listed in the drawings are used as “Basis of Design”. Alternates or “approved equal” will be considered for review by the FAA prior to granting acceptance.
40. Refrigerant Discrepancy on Liebert Systems: On Drawing M101 of the equipment schedules, it shows two Liebert systems utilizing refrigerant 410A and the other two utilizing 407C. Please advise if this is accurate or if it may be a discrepancy.
FAA Response:
Liebert models (DS035A) that are used as “Basis of Design” in the drawings utilize R407C as per the manufacturer’s specs. Please disregard R410A.
41. Lineset Replacement for Liebert Systems: Please advise if the plan is to replace the entirety of the refrigerant linesets for the Liebert systems, as none appear to be installed behind drywall.
Yes, existing refrigerant piping to be demolished and replaced with new one.
42. To clarify the previous Q&A received with the revised solicitation documents, please confirm that the Superintendent can also serve as the SSHO.
FAA Response:
Superintended can act for the SSHO / CQC / QC Manager / Project Manager / Coordination
Engineer. Superintendent, who must be onsite fulltime, is defined and assigned as per “FAR
AMS 52.236-6”.
43. To clarify the previous Q&A received with the revised solicitation documents, the specifications appear to require (4) on-site, fulltime positions while construction work is ongoing; Superintendent, SSHO, Quality Control Manager, and Coordinating Engineer. Please advise if any of these positions can be duel or triple hatted.
FAA Response:
Superintended can act for the SSHO / CQC / QC Manager / Project Manager / Coordination
Engineer. Superintendent, who must be onsite fulltime, is defined and assigned as per “FAR
AMS 52.236-6”.
44. Specification 01 40 00-3.3-E provides an Experience Matrix presumably for the “Additional CQC Personnel” required as part of the Independent Quality Control Organization (CQC). With the contractor’s full-time on-site QC Manager and supporting 3rd party testing agencies, please advise if all of the additional roles listed in the Experience Matrix will be required.
FAA Response:
Superintendent can act for the SSHO / CQC / QC Manager / Project Manager / Coordination
Engineer. Superintendent, who must be onsite fulltime, is defined and assigned as per “FAR
AMS 52.236-6”.
45. Confirm the bid date and time listed above are unchanged.
FAA Response: Offer due date was changed to November 25, 2024, second amendment is pending.
46. Construction cost estimate or a construction cost range for the project.
FAA Response: ROM is $2-3 million
47. Planholders list/bidders list and Non-Mandatory pre-bid attendance list
FAA Response: Site Visit List Attached and included as J-10 Bidders List is off the FAA Terminal Nationwide BOA (E-Corp, TMG, Walsh Construction, Westpoint, StructSure)
48. Have you issued an addenda? If so please attach them to this response.
FAA Response: One amendment issued so far extending the offer due date to 11/25/24.
49. When is the best time to follow up for bid results?
FAA Response: Follow up the first week of December.