About this file

This is an Evaluation Criteria document from Boulder County Procurement for the Willoughby Corner Phase II (IIA and IIB) Construction Manager/General Contractor (CM/GC) project administered by the Boulder County Housing Authority. The project seeks qualified CM/GC firms to provide pre-construction, construction, and construction administration services for a 400-unit permanently affordable housing development on a 24-acre parcel near Lafayette, Colorado. The development will include duplexes, townhomes, multi-family apartments, and owner-occupied residences, along with significant site improvements and resident amenity spaces. The project is financed primarily through low-income housing tax credits (LIHTC) from the Colorado Housing Finance Authority and Private Activity Bonds.

The evaluation process will be conducted by a selection committee that may request additional information or conduct interviews with vendors. Proposals will be scored on a 100-point matrix comprising three primary categories: Statement of Qualifications (40 points), Statement of Approach (30 points), and Proposed Fee Structure (30 points). The county reserves the right to base final evaluation and selection on any or all of these criteria, with final decisions made following the committee's comprehensive review of submissions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Boulder County Procurement 1325 Pearl Street

Boulder, CO 80302

Evaluation Criteria

The proposals will be reviewed by a selection committee. The committee may request additional information from vendors or request interviews with one or more vendors. Final evaluation and selection may be based on, but not limited to, any or all of the following:

• Statement of Qualifications

• Statement of Approach

• Proposed Fee Structure

A scoring matrix to be used by the county in its evaluation and selection process is shown below:

Description Points Statement of Qualifications 40 Statement of Approach 30 Proposed Fee Structure 30

Total Possible 100