5a SOW-EHRM NextGen WiFi Upgrades.docx

DOCX document 39 KB Posted

Attached to
Y1DA--FY25: NRM (PROJ: 673-25-704) EHRM Installation of Next-Gen Wi-fi – Tampa, FL
Solicitation number
36C24825R0009
Issued by

About this file

This document is a Statement of Work (SOW) for the EHRM Installation of NextGen Wi-Fi Upgrades project at the James A. Haley VA Medical Center in Tampa, FL. The key details are:

The contractor shall provide all labor, tools, materials, and equipment to install 123 new Wi-Fi access points, 10,000 linear feet of new conduit, and 14,800 linear feet of CAT 6A cabling throughout the medical center campus. This includes penetrations, fire-stopping, and installation of 9 new patch panels. The period of performance is 180 days. The related federal contract opportunity, Solicitation #36C24825R0009, is a firm-fixed price contract set-aside for verified Service-Disabled Veteran-Owned Small Businesses (SDVOSB). Proposals are due by 12/08/2024 and the government intends to award without discussions. Offerors must submit past performance, technical/management approach, and price information for evaluation. The government estimates the project value to be between $250,000 and $500,000.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

James A Haley VAMC 8/2024 2702 E 131st Ave Tampa, FL 33612

CONSTRUCTION SCOPE OF WORK

EHRM NEXTGEN WIFI UPGRADES

POP 180-days

PROJECT NO: 673-25-704

PROJECT NAME: EHRM Installation of NextGen Wi-fi – Tampa, FL

1. GENERAL INTENT:

The Contractor shall furnish all labor, tools, materials, and equipment to support the installation of replacement and new Wi-Fi Access Points at James A Haley Veteran Affair Medical Center (VAMC) campus located at 2702 E 131st Ave, Tampa, FL 33612 and CBOC. Please note that the scope of this work is limited and specifically as listed below.

2. STATEMENT OF WORK:

Provide and install conduit, raceways, horizontal and vertical penetrations, and fire stopping to support NextGen Wi-Fi installation on the James A Haley VAMC campus as shown and described in the project drawings and specifications. A list of required conduits and/or penetrations is provided in SOW Attachment 1.

1. Installation of 123 Access Points. Access Points shall be provided by the VA, but the mounting brackets shall be provided by the Contractor.

2. Installation of 10,000 linear feet of conduit, including junction boxes, pull cords, and fire stopping, throughout the Medical Center. Existing conduit paths between floors/IT rooms will not have the capacity for more cable and new conduit paths will need to be created.

3. Installation of approximately 14,800 linear feet of CAT 6A cable from APs to the nearest IT rooms and terminating in a patch panel (See attachment).

4. Installation of (9) patch panels. See specifications 27 11 19.

5. Minimum disturbance of known asbestos locations for installation of AP and conduit anchors

Recommend Offerors verify field conditions in a pre-bid site walk.

Work shall be completed after hours and on weekends. This could be coordinated with the COR.

3. PERIOD OF PERFORMANCE:

3.1 Work timelines and completion progress shall be communicated to the COR for tracking purposes.

4. REFERENCES:

4.1 VA OEHRM Site Infrastructure and End User Device (EUD) Requirements Version 2.0 (Attachment 3).

4.2 Infrastructure Standards for Telecommunications Spaces Version 4.0 (dated June 1, 2023)

5. SPECIFICATIONS:

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00General Requirements
01 32 16.15Project Schedule
01 33 23Shop Drawings, Product Data, and Samples
01 35 26Safety Requirements
01 74 19Construction Waste Management

DIVISION 02 - EXISTING CONDITIONS

02 41 00 Demolition

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping

DIVISION 27 – COMMUNICATIONS

27 05 11Requirements for Communications Installations
27 05 33Raceways and Boxes for Communications Systems
27 10 00Control, Communication, and Signal Wiring
27 15 00Communications Structured Cabling
27 11 19Communications Termination Blocks And Patch Panels

6. SUBMITTALS:

a. The contractor shall submit the following submittals for review:

1) Product data and a sample of conduit or raceway.

2) As-built drawings for all data locations and labels. The Contractor shall provide the central drawing set to the Owner at the end of the project. The marked-up drawing set will accurately depict the as-built status of the system.

6. ATTACHMENTS:

6.1Attachment 1: List of Access Point locations and site prep requirements.
6.2Attachment 2: NextGen Wi-Fi Access Point location drawings
6.3Attachment 3: VA OEHRM Site Infrastructure and End User Device (EUD) Requirements Version 2.0
6.4Attachment 4: Sensitive Infrastructure Data Classification Memo
6.5Attachment 5: Seasonal Influenza with Vaccines
6.6Attachment 6: Specifications

The above paragraphs constitute a basic outline of the work to be accomplished and in no way comprises all the details for this project. The contractor shall refer to drawings and specifications for comprehensive construction requirements.

End of SOW