515-20-101 32 008-AD101 - Bldg 8 2nd Flr Demolition Plans.pdf
PDF 240 KB Posted
- Solicitation number
- 515-20-101
About this file
This solicitation is for renovation services at various buildings at the VA Medical Center in Battle Creek, Michigan. The contractor shall provide all labor, materials, equipment, supervision, documentation and other information to improve common areas in several outpatient care buildings. Scope of work includes replacing worn ceiling, flooring and wall finishes; installing new energy efficient doors and frames with integrated security hardware; improving handrails; and adding wayfinding signage. Affected buildings are 2, 6, 8, 9, 10, 11, 12, 5, 13, 14 and 82. Safety improvements include entrance vestibules. The contractor will have 380 days to complete the work. The soliciting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONFERENCE
LOUNGE
GROUP
TOILET
P
IP
E
TOILET
HSK
EXAM
OFFICE
CLASSROOM
P
IP
E
SHOWER
OFFICE
SELF-MED
P
IP
E
P
IP
E
OFFICE
NURSE
STATION
CLEAN
LINEN
OFFICE
CONFERENCE
OFFICE
TOILETSTORAGE
ROOM
LAUNDRY
OFFICE
OFFICE
DAY ROOM
CLOSET
STAIR
TOILET
CLOSET
ROOM
CLOSET
CLOSET
STAIR
CLOSET
PORCH PORCH
115B
115A
E
S2
118A 119A
E
121 122
E
E
102A
104B
S1
103A
111116A
104A
104C
100E
204A
203A
S2
213E
200E
225 226 227 201 202
E
E
E
224A
SI
E
222A
OFFICE
HSK
OFFICE
OFFICE
TOILET
STORAGE
BEDROOM
BEDROOM
OFFICE
BEDROOM
BEDROOM
BEDROOM
BEDROOM
BEDROOM
BEDROOM
BED RMOFFICE
SHOWER
ROOM
TOILET
LOCKER OFFICE OFFICE
OFFICE
BEDROOM
INTERVIEW
ROOM
P
IP
E
P
IP
E
P
IP
E P
IP
E
CLOSET
STAIRSTAIR
TOILET
CLOSET
CLOSET
CLOSET
4A 6B 7A5B 4A 6B 7A5B 4A 6B 7A5B
4A 6B 7A5B
6B 7A5B
1 11
1 1
1 1
H3
7B
10 10 H4
H4
144 SF
CORRIDOR
333 SF
CORRIDOR
73 SF
VESTIBULE
4A 6B 7B5B 7A
THE HYDRONIC WALL CONVECTORS
WILL TEMPORARILY BE REMOVED AND
REINSTALLED FOR FLOOR REMOVAL
AND NEW INSTALLATION AS REQUIRED.
PROVIDE FLOOR LEVERLER
AS REQUIREED IN
PREPERATION FOR FINAL
FLOOR FINISH; TYP.
GENERAL DEMOLITION NOTES
1. ALL DEMOLITION WORK REQUIRED IS NOT NECESSARILY LIMITED
TO WHAT IS SHOWN ON THE DEMOLITION PLANS. THE INTENT IS
TO REMOVE ALL MATERIALS AND ITEMS AS REQUIRED TO
FACILITATE NEW CONSTRUCTION.
2. CONSTRUCTION AREAS TO BE COMPLETELY SEPARATED FROM
OCCUPIED AREAS WITH A ONE-HOUR FIRE RATED ASSEMBLY,
AND WITH SUITABLE DUST BARRIER. TEMPORARILY SEAL OFF ALL
RETURN & SUPPLY AIR DIFFUSERS IN CONSTRUCTION AREA.
PROVIDE RECIRCULATING HEPA FILTER IN CONSTRUCTION
AREA. ALL DEMOLISHED MATERIAL IS TO BE REMOVED FROM
SITE IN A COVERED CONTAINER. NEGATIVE AIR PRESSURE TO BE
MAINTAINED WITHIN CONSTRUCTION ZONE.
3. CONTRACTORS ARE TO VERIFY FIELD CONDITIONS INCLUDING
ABOVE CEILINGS BEFORE BIDDING, IF CONDITIONS DO NOT
REFLECT WHAT IS NOTED IN THE CONTRACT DOCUMENTS, THE
CONTRACTOR IS TO SUBMIT AN RFI.
4. BEFORE ANY WORK ON FIRE ALARM SYSTEM IS TO BE DONE
CONTRACTOR MUST COORDINATE WITH VA COR AND VA FIRE
SERVICE. ALL SMOKE AND HEAT DETECTORS SHALL BE COVERED
AND SEALED AGAINST DUST ENTRY DURING WORK AND
UNCOVERED AFTER WORK IS CONCLUDED, EACH DAY.
5. THIS PLAN IS TO BE USED IN CONJUNCTION WITH THE ENTIRE SET
OF CONSTRUCTION DOCUMENTS. DO NOT REMOVE ANY ITEMS
WITHOUT VERIFYING AND COORDINATING WITH ALL
CONSTRUCTION DOCUMENTS AND SPECIFICATIONS. ANY
DISCREPANCIES TO BE BROUGHT TO ARCHITECTS ATTENTION
BEFORE WORK IS TO BE DONE.
6. CONTRACTOR IS RESPONSIBLE FOR PROVIDING DUMPSTERS.
LOCATION OF DUMPSTERS TO BE DETERMINED BY COR WITH
CONTRACTORS INPUT.
7. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL
DEMOLISHED MATERIALS. DO NOT ALLOW MATERIALS AND
DEBRIS GENERATED BY DEMOLITION ACTIVITIES TO
ACCUMULATE ON THE JOBSITE. REMOVE DAILY AND DISPOSE
OF IN A LEGAL MANNER. NO ONSITE SALE OR BURNING OF
REMOVED ITEMS IS PERMITTED.
8. THE CONTRACTOR MUST TAKE ALL NECESSARY PRECAUTIONS
TO ENSURE THE SAFETY OF THE PUBLIC AND/OR WORKMEN ON
THE SITE TO PREVENT ACCIDENTS OR INJURY TO ANY PERSON
ON, ABOUT OR ADJACENT TO THE PREMISES. THE CONTRACTOR
SHALL COMPLY WITH ALL LAWS, ORDINANCES, CODES AND
REGULATIONS PERTAINING TO SAFETY AND THE PREVENTION OF
ACCIDENTS.
9. THE CONTRACTOR MUST MAINTAIN ADEQUATE SUPPORT,
INSULATION, WATERPROOFING, EMERGENCY LIGHTING,
SECURITY, ALARMS, ETC. FOR ALL OR PART OF ITEMS WHICH
ARE TO REMAIN. CONTRACTOR TO PROVIDE TEMPORARY
LIGHTING IN THE INTERIM BETWEEN DEMOLITION AND NEW.
10. DO NOT CUT AND/OR PATCH STRUCTURAL ELEMENTS IN A
MANNER THAT COULD CHANGE THEIR LOAD-CARRYING
CAPACITY OR LOAD-DEFLECTION RATIO.
11. PATCH/REPAIR OR REPLACE ALL AREAS DAMAGED BY
DEMOLITION, REWORK AS REQUIRED, PREPARE FOR NEW
CONSTRUCTION AS REQUIRED. BRICK OR BLOCK PATCHING
SHALL BE TOOTHED-IN TO MATCH EXISTING COURSING PATTERN
WHERE EXPOSED.
12. REFER TO ASBESTOS SURVEY, AND IF ADDITIONAL HAZARDOUS
MATERIALS ARE ENCOUNTERED DURING DEMOLITION,
CONTRACTOR SHALL CONTACT COR FOR ABATEMENT.
13. REMOVE, REPLACE, PATCH, AND REPAIR MATERIALS AND
SURFACES CUT OR DAMAGED DURING DEMOLITION, BY
METHODS AND WITH MATERIALS SO AS NOT TO VOID EXISTING
WARRANTIES.
14. CLEAN AREAS AND SPACES WHERE CUTTING AND PATCHING
ARE PERFORMED.
15. INTERIOR WALLS TO BE REMOVED, SHALL BE REMOVED THE
ENTIRE HEIGHT OF THE WALL UNLESS REQUIRED OTHERWISE BY
NEW OPENINGS IN EXISTING WALLS TO REMAIN.
16. CONTRACTOR SHALL PATCH, REPAIR, AND INFILL ALL APPLIED
FIREPROOFING MATERIAL IN AREAS LEFT UNPROTECTED DUE TO
REMOVAL OF EXISTING ELEMENTS OR AREAS DAMAGED
DURING NEW WORK AND DEMOLITION. MATCH EXISTING
FIREPROOFING MATERIAL TYPE AND THICKNESS TO MAINTAIN
REQUIRED LEVEL OR PROTECTION.
A1
DEMOLITION KEY NOTES
REMOVE EXISTING DOOR & HARDWARE. EXISTING
FRAME TO REMAIN. PREPARE FRAME AS REQUIRED
TO RECEIVE NEW DOOR & HARDWARE. EXISTING
DOOR HARDWARE LOCKSETS, CORES, AND
KEYWAYS SHALL BE SALVAGED AND TURNED OVER
TO THE VA COR.
REMOVE EXISTING HARDWARE (DOOR TO REMAIN).
EXISTING DOOR HARDWARE LOCKSETS, CORES,
AND KEYWAYS SHALL BE SALVAGED AND TURNED
OVER TO THE VA COR.
REMOVE EXISTING WALL CAP; PARTIAL WALL TO
REMAIN
REMOVE EXISTING WALL-MOUNTED HANDRAILS
COMPLETE INCLUDING CONNECTORS, MOUNTING
BRACKETS, AND END TERMINATIONS. PATCH AND
REPAIR WALL. TURN BALANCE OVER TO COR UNLESS
DIRECTED OTHERWISE.
REMOVE EXISTING LOW WALL-MOUNTED BUMPER
GUARD COMPLETE. PATCH AND REPAIR WALL
SURFACE TO REMAIN.
REMOVE EXISTING WALL PROTECTION, WALL BASE,
AND ALL ITEMS ATTACHED TO THE WALLS (STORE
AND PROTECT FOR RE-INSTALLATION
ARTWORK/POSTERS). PATCH & REPAIR EXPOSED
SURFACES TO REMAIN AS REQUIRED FOR NEW
CONSTRUCTION AND/OR NEW FINISHES.
REMOVE EXISTING WALL COVERING/WALL PAPER,
WALL BASE AND ALL ITEMS ATTACHED TO THE WALLS
(STORE AND PROTECT FOR RE-INSTALLATION
ARTWORK/POSTERS). PATCH & REPAIR EXPOSED
SURFACES TO REMAIN AS REQUIRED FOR NEW
CONSTRUCTION AND/OR NEW FINISHES. ALL
EXISTING ITEMS ATTACHED TO WALL, SHALL BE
STORED, AND WHERE DIRECTED BY COR
REINSTALLED.
REMOVE EXISTING CORNER GUARDS.
REMOVE EXISTING WOOD VENEER PANEL AND
BACKUP GYP BOARD. REFER TO DEMOLITION
SECTION.
REMOVE EXISTING WOOD VENEER PANEL; EXISTING
BACKUP MATERIAL TO REMAIN.
REMOVE EXISTING WINDOW SILL AND ASSOCIATED
WOOD TRIM; PATCH AND REPAIR WALL SURFACE TO
REMAIN.
REMOVE EXISTING CARPET FLOORING INCLUDING
ADHESIVES, NAILING STRIPS, TRANSITION STRIPS,
AND SETTING MATERIALS DOWN TO EXISTING
SUBSTRATE. GRIND CONCRETE FLOORS AS
REQUIRED TO PROVIDE A SMOOTH AND UNIFORM
SURFACE FOR NEW FINISHES.
REMOVE EXISTING VINYL COMPOSITION TILE/
LUXURY VINYL TILE FLOORING INCLUDING
ADHESIVES, TRANSITION STRIPS, AND SETTING
MATERIALS DOWN TO EXISTING SUBSTRATE. GRIND
CONCRETE FLOORS AS REQUIRED TO PROVIDE A
SMOOTH AND UNIFORM SURFACE FOR NEW
FINISHES.
REMOVE EXISTING TILE FLOORING INCLUDING
TRANSITION STRIPS, AND TILE MORTAR BED DOWN
TO EXISTING SUBSTRATE. GRIND CONCRETE FLOOR
AS REQUIRED TO PROVIDE A SMOOTH AND
UNIFORM SURFACE FOR NEW FINISHES. PROVIDE
FLOOR LEVELER AS REQUIRED.
REMOVE EXISTING ACOUSTICAL CEILING TILE AND
GRID SYSTEM COMPLETE INCLUDING ASSOCIATED
HANGERS, METAL TEE GRID, AND EDGE ANGLES.
EXISTING CEILING MOUNTED LIGHT FIXTURES
(UNLESS NOTED IN CONJUNCTION W/ 7B),
SPEAKERS, CAMERAS, FIRE ALARMS, MECHANICAL
DEVICES, SMOKE DETECTORS, SENSORS, WIRELESS
ACCESS POINT, EXIT SIGNAGE, SAFETY MIRRORS,
ETC. TO BE TEMPORARILY SUPPORTED FOR
REINSTALLATION IN NEW CEILING FINISH; REFER TO
REFLECTED CEILING PLANS FOR EXISTING AND
REINSTALLED LOCATIONS. [NOTE: ITEMS SHALL NOT
BE TEMPORARILY OR PERMANENTLY SUSPENDED
FROM FIRE SUPPRESSION LINES]
REMOVE EXISTING LIGHT FIXTURES COMPLETE AND
RETURN TO COR. EXISTING CIRCUITING (EXTEND AS
REQUIRED)AND CONTROLS TO REMAIN FOR REUSE
WITH NEW LIGHTING. REFER TO NEW WORK
REFLECTED CEILING PLANS FOR EXISTING LIGHTS TO
BE REMOVED AND EXISTING LIGHTS TO REMAIN. ALL
REMAINING CEILING MOUNTED ITEMS TO BE
REINSTALLED AS CALLED OUT IN 7A.
REMOVE EXISTING DRYWALL CEILING AND SUPPORT
SYSTEM. PATCH & REPAIR EXPOSED SURFACES TO
REMAIN AS REQUIRED FOR NEW CONSTRUCTION
AND/OR NEW FINISHES.
REMOVE EXISTING CASEWORK UPPER AND LOWER.
SALVAGE EQUIPMENT & TURN OVER TO COR
UNLESS DIRECTED OTHERWISE. PATCH AND REPAIR
EXPOSED SURFACES TO REMAIN AS REQUIRED TO
RECEIVE NEW CONSTRUCTION AND FINISHES.
REMOVE EXISTING COUNTERTOP INCLUDING BACK/
SIDESPLASH AND ALL ASSOCIATED SUPPORT
BRACKETS AND FRAMING. SALVAGE EQUIPMENT &
TURN OVER TO COR UNLESS DIRECTED OTHERWISE.
PATCH AND REPAIR EXPOSED SURFACES TO REMAIN
AS REQUIRED TO RECEIVE NEW CONSTRUCTION
AND FINISHES.
REMOVE EXISTING PLUMBING FIXTURE COMPLETE.
EXISTING SANITARY, WATER, AND VENT PIPING TO
REMAIN; PATCH AND REPAIR WALL AS REQUIRED.
REMOVE EXISTING STAIRS SYSTEM (TREADS, RISERS,
HANDRAILS, SUPPORTS, GUARD RAILS, ETC.) REFER
TO STRUCTURAL DRAWINGS FOR INFILL OF FLOOR
OPENING.
REMOVE EXISTING STAIR GRIP TAPE INCLUDING ALL
ADHESIVES DOWN TO EXISTING SUBSTRATE. SAND
EXISTING WOOD TREADS AND LANDINGS AND
PROVIDE FLOOR LEVEL AS REQUIRED TO PROVIDE A
SMOOTH AND UNIFORM SURFACE FOR NEW
FINISHES. DEMO EXISTING WALL MOUNTED
HANDRAIL AND SUPPORT.
REMOVE EXISTING WOODEN ROOF SHEATHING
AND STEEL PLATE ICICLE PROTECTION; REMOVE ALL
EXISTING FRAMING EXCLUDING SUPPORT
COLUMNS.
REMOVE EXISTING ROOF & STRUCTURE INCLUDING
WALL MOUNT BRACKETS AND FLASHING. PATCH
AND REPAIR EXISTING BRICK AND MORTAR TO
REMAIN
REMOVE EXISTING SYSTEM FURNITURE AND DESK
STORE AND PROTECT FOR RE-INSTALLATION,
COORDINATE WITH COR.
REMOVE EXISTING TERRAZZO FLOORING AND
INTEGRAL WALL BASE. PATCH AND REPAIR FLOOR.
PROVIDE FLOOR LEVELER AS REQUIRED.
4A
5A
6A
7A
9A
4B
6B
5B
5C
5D
5F
EXISTING FULLY FINISHED SPACE THAT ALL WALL FINISHES,
CEILINGS, FLOORING, CASEWORK, PLUMBING FIXTURES,
CEILING MOUNTED LIGHT FIXTURES ARE TO BE REMOVED.
EXISTING WALL CONSTRUCTION AND COLUMNS ARE TO
REMAIN, UNLESS NOTED OTHERWISE. PREPARE ALL SURFACES
FOR NEW CONSTRUCTION. PROVIDE SKIM COAT ON ALL WALL
SURFACES TO A LEVEL 5 FINISH.
EXISTING INTERIOR SPACE NOT INCLUDED IN SCOPE
OF THIS PROJECT
9B
REMOVE EXISTING CONCRETE STEPS INCLUDING
FOUNDATIONS/FOOTINGS AND EXISTING HANDRAILS AND
BRACKETS; PATCH AND REPAIR EXISTING BRICK TO REMAIN,
REMOVE EXISTING WALL TILE AND BACKING; PATCH AND
REPAIR WALL IN PREPARATION FOR NEW FINISHES.
SAWCUT AND REMOVE EXISTING CONCRETE UP TO EXISTING
CONTROL JOINT IN PREPARATION FOR NEW WORK.
REMOVE EXISTING WALL PARTITION (INCLUDING GLASS
SIDELIGHTS) FULL HEIGHT; PATCH AND REPAIR ADJOINING
FLOOR, WALL AND CEILING SURFACES TO REMAIN.
REMOVE EXISTING EXTERIOR STOREFRONT SYSTEM INCLUDING
DOOR. PATCH AND REPAIR ADJACENT WALL CONSTRUCTION
TO REMAIN.
REMOVE EXISTING FLOOR EXPANSION JOINT; EXISTING WALL
EXPANSION TO REMAIN.
REMOVE EXISTING FIRE EXTINGUISHER AND BRACKET SALVAGE
AND TURN OVER TO THE VA COR.
REMOVE EXISTING KIOSKS AND STORE FOR REINSTALLATION.
TURN BALANCE OVER TO COR.
REMOVE EXISTING DOOR, DOOR FRAME & HARDWARE.
PREPARE OPENING AS REQUIRED TO RECEIVE NEW DOOR &
HARDWARE. EXISTING DOOR HARDWARE LOCKSETS, CORES,
AND KEYWAYS SHALL BE SALVAGED AND TURNED OVER TO THE
VA COR.
5E
7B
6C
HAZARDOUS DEMO KEY NOTES
H1 ABATE AND REMOVE EXISTING DOOR LEAF WITH
ASBESTOS. EXISTING FRAME TO REMAIN.PREPARE
FRAME AS REQUIRED TO RECEIVE NEW DOOR &
HARDWARE.
ABATE AND REMOVE EXISTING ASBESTOS FLOOR TILE
AND ASBESTOS MASTIC. REMOVE EXISTING
ASBESTOS ADHESIVES, TRANSITION STRIPS. GRIND
EXISTING FLOOR SUBSTRATE TO A SMOOTH AND
UNIFORM SURFACE FOR NEW FINISHES. PATCH AND
REPAIR AS REQUIRED.
ABATE AND REMOVE EXISTING ASBESTOS FLOOR TILE
AND ASBESTOS BEDDING COMPOUND. REMOVE
EXISTING TRANSITION STRIPS, AND GRIND EXISTING
CONCRETE SUBSTRATE TO A SMOOTH AND
UNIFORM SURFACE FOR NEW FINISHES.
ABATE AND REMOVE EXISTING WALL TILE AND
ASBESTOS BEDDING COMPOUND. PATCH AND
REPAIR EXISTING/ADJACENT WALL TO REMAIN IN
PREPERATION FOR NEW WORK.
H2
H3
H4
A1
A1
A1 4A 6B 7A5B
4A 6B 7A5B
4A 6B 7A5B
1 1 1
10 H4
6B 7B
512 SF
CORRIDOR
285 SF
CORRIDOR
10 H4
4A 6B 7A5B 4A 6B 7A5B
REMOVE EXISTING
WINDOW COVERING
BLINDS AND ATTACHMENT
CLIPS; PATCH AND REPAIR
WALL TO RECEIVE NEW
FINISHES
1 1 1 22
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DWG. ___ OF 74
7GAE PROJECT NO.: 219122
Sprinkler:
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
FOR CONSTRUCTION
100% BID DOCUMENTS
DEMOLITION FLOOR PLANS VAMC BC RENOVATE
COMMON AREAS, VARIOUS
BUILDINGS
5500 ARMSTRONG ROAD
BATTLE CREEK, MI 49037
515-20-101
PROJECT DIRECTOR
04 - 01 - 2021 JB JS
100% BID
DOCUMENTS
008.AD101
FULLY SPRINKLED
SCALE: 1/8" = 1'-0"008.AD101
BUILDING 8: FIRST FLOOR DEMOLITION PLAN01
SCALE: 1/8" = 1'-0"008.AD101
BUILDING 8: SECOND FLOOR DEMOLITION PLAN02
PLAN NORTH
Revisions: Date:
| Sheets |
| 002.AD100 - GROUND FLOOR DEMOLITION PLAN |
| 002.AD101 - FIRST FLOOR DEMOLITION PLAN |
| 002.AD102 - SECOND FLOOR DEMOLITION PLAN |
| 005.AD101 - DEMOLITION PLAN & ELEVATION |
| 006.AD101 - DEMOLITION PLANS & ELEVATION |
| 008.AD101 - DEMOLITION FLOOR PLANS |
| 009.AD101 - DEMOLITION FLOOR PLANS |
| 010.AD101 - DEMOLITION FLOOR PLANS |
| 011.AD101 - DEMOLITION FLOOR PLAN |
| 012.AD101 - DEMOLITION FLOOR PLANS |
| 013.AD101 - DEMOLITION PLANS & ELEVATION |
| 014.AD101 - DEMOLITION PLAN & ELEVATION |
| 082.AD101 - DEMOLITION PLANS & ELEVATION |
File details come from the government source that posted it. Updated .