5-St. George Industrial 2 MG Tank Bid Technical Specifications 2025-08-26 (1).pdf

PDF 8 MB Posted

Attached to
IFB - ST GEORGE INDUSTRIAL 2 MG TANK PROJECT
Solicitation number
24-180
Issued by
Washington County, Utah

About this file

This document is a technical specification file for the St. George Industrial 2 MG Tank Replacement project, prepared by Alpha Engineering for the City of St. George, Utah. The project involves removing the existing 2 million gallon water storage tank and constructing a new reinforced concrete tank at the same location, with a 140-foot inside diameter and approximately 19 feet in height. The tank will be built on a site with basalt bedrock, requiring extensive excavation and preparation. The contractor will be responsible for maintaining water service during construction, notifying affected homeowners 48 hours in advance, and ensuring no single homeowner experiences water outage for more than two consecutive days or more than 8 hours at a time.

The project is competitively bid, with a contract time of 365 calendar days from the Notice to Proceed and liquidated damages of $550 per calendar day for delays. Bidders are required to submit a 5% bid bond, and a 100% performance and labor materials bond will be required. The total project involves multiple bid items including mobilization, removals, earthwork, tank construction, piping installation, valves, fittings, and associated infrastructure. The geotechnical investigation reveals complex site conditions involving basalt bedrock, with potential requirements for rock hammering or blasting during excavation. The project will be funded by the City of St. George and requires careful geological and engineering considerations to ensure proper tank construction and site preparation.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

041-162

PART B

TECHNICAL SPECIFICATIONS

General Requirements 101-1

SECTION 101

GENERAL REQUIREMENTS

1.1 SUMMARY OF THE WORK. The St. George Industrial 2 MG Tank Replacement project involves the removal of the existing 2 MG water storage tank at the St. George Industrial site, construction of a new tank at the same location, and filling in the old tank area to grade once the new tank is completed. The project scope includes demolition of the old tank structure, site preparation, installation of the new water tank, and final site restoration.

The Contractor is responsible to maintain water service during the progression of the work. The Contractor is also responsible to notify homeowners that will be affected by construction 48 hours in advance of construction activities. No single homeowner shall have the water out of service for more than two consecutive days and for no more than 8 hours at a time. All water services shall function between the hours of 6:00 p.m. and 8:00 a.m.

The contractor shall coordinate any road closures and construction activities so as not to interfere with access to individual homes. The contractor shall insure that driveways or property access are returned to service at the end of each working day as determined by St. George City. This shall include temporary road base, grading, or use of trench plating at crossing locations as required by St. George City.

The contractor shall insure that all trenches are restored to finish grade daily. Any trenches not restored to finish grade by the end of work shift shall be plated and barricaded according to the current MUTCD standards. Re-pavement of streets shall be in a timely manner.

If there is a conflict between the requirements of this section and requirements of other sections of these specifications, the General Requirements shall govern.

1.2 CONTRACT TIME. The project timing is extremely critical. The Contractor will be required to complete the St. George Industrial 2 MG Tank Replacement project within 365 calendar days from the Notice to Proceed.

In the event the Contractor does not meet the above time schedule, liquidated damages of $550.00 per calendar day for each calendar day required to complete the project until the project is certified complete by the Engineer for either bid schedule. Liquidated damages will be assessed in accordance with the General Conditions.

1.3 SITE EXAMINATION. The Bidder should examine the site before submitting his proposal and inform himself regarding existing facilities and conditions affecting the proposed work.

Failure to make such inspection shall in no way relieve the Contractor of any of the obligations or conditions of the specifications and special provisions to serve in any way as a basis of

101-2 extra renumeration to the Contractor for conditions arising from the unfamiliarity with the site or conditions affecting the work.

1.4 CONSTRUCTION STAKING. The Engineer will provide all control necessary to establish both line and grade for construction of the project. Re-staking required by the Engineer as a result of the Contractor’s carelessness or failure to protect survey marks and stakes shall be accomplished at the expense of the General Contractor.

Construction staking will be provided by the Engineer and will include stakes for line and grade for the new waterline and pipeline connection points, valves and hydrants. Line and grade for sewer line and manholes, rough grade, slope staking, and finish grade staking for the access road(s), and rough grade, slope staking and finish grade for the tank sites.

Application for construction staking in writing must be made by the General Contractor at least 48 hours prior to the time that the stakes are needed. Construction Staking Request Forms are available from the offices of Alpha Engineering.

1.5 INTERFERING STRUCTURES AND UTILITIES RESPONSIBILITY

1.5.1 The Contractor shall exercise all possible caution to prevent damage to existing structures and utilities, whether above ground or underground. An attempt has been made to show these structures and utilities on the plans. While the information has been compiled from the best available sources, its completeness and accuracy cannot be guaranteed, and it is presented simply as a guide to possible difficulties. The Contractor shall notify all utility offices concerned at least 48 hours in advance of construction operations in which a utility agency's facilities may be involved. This shall include, but not be limited to irrigation, water, sewer, telephone, cable television, gas, fiber optic, and electric lines. The Contractor shall be responsible for any and all changes to, relocation of or reconnections to public utility facilities encountered or interrupted during prosecution of the work, and all costs relating thereto shall be at the Contractor's expense. The Contractor shall contract with and pay public utility agencies for work required in connection with all utility interferences and handle all necessary notifications, scheduling, coordination and details. The cost of public utility interferences and/or changes shall be included in the Contractor's lump sum or unit price bid covering the major contract facility to which interference or changes are attributable.

1.5.2 It shall be the responsibility of the Contractor to locate and expose all existing underground structures and utilities in such a manner as to prevent damage to same.

Any structure or utilities damaged by the work shall be repaired or replaced in a condition equal to or better than the condition prior to the damage. Such repair or replacement shall be accomplished at the Contractor's expense without additional compensation from the Owner. All lines shall be uncovered a minimum of 500 feet ahead of pipe laying operations.

101-3

1.5.3 The Contractor shall remove and replace such small, miscellaneous structures as fences and culverts at his own expense without additional compensation from the Owner. The Contractor shall replace these structures in a condition as good as or better than their original conditions.

1.5.4 At points where the Contractor's operations are adjacent to or across properties of railway, telegraph, telephone, irrigation or canal, power, gas, water, or adjacent to other property (damage to which might result in considerable expense, loss, and inconvenience), no work shall be started until all arrangements necessary for the protection thereof have been made by the Contractor.

1.5.5 The Contractor shall be solely and directly responsible to the owners and operators of such properties for any damage, injury, expense, loss, inconvenience, delay, suits, actions, or claims of any character brought because of an injury or damage which may result from the carrying out of the work to be done under the contract.

1.5.6 In the event of interruption to either domestic or irrigation water, or to other utility services, as a result of accidental breakage or in the completion of the contract by the Contractor, the Contractor shall promptly notify the proper authority. The Contractor shall cooperate with the said authority in restoration of service as soon as possible and shall bear all cost of repair and resulting civil liability. In no case shall interruption of any water or utility service be allowed to exist outside working hours unless prior approval is received from the Engineer.

1.5.7 The locations of the major existing pipelines, as shown on the plans, were taken from records, and preliminary investigations have indicated they are generally reliable.

However, it should be expected that some location discrepancies will occur. Neither the Owner nor their officers or agents shall be responsible for damages, expenses, or delays to the Contractor as a result of the locations of the utilities being other than those shown on the plans or for the existence of utilities not shown on the plans.

1.6 CONSTRUCTION SEQUENCE. It is the intention of these contract documents that the progress of the work shall proceed in a systematic and expeditious manner so the minimum of inconvenience will result to the public in the course of construction. The Contractor, therefore, shall submit, prior to any construction activity, a proposed schedule of work which is acceptable to the Owner and the Engineer and shall, during the course of construction, strictly adhere to the schedule. The construction schedule shall be designed such that each phase of the construction process can immediately follow the preceding phase in an efficient and orderly manner.

1.7 LAND MONUMENTS. The Contractor shall preserve existing City, County, State, and Federal land monuments wherever possible. When these monuments cannot be preserved, the Contractor shall notify the Engineer at least two weeks in advance of the proposed

101-4 construction in order that the Engineer will have ample opportunity to reference these monuments for later replacement. The Contractor shall be responsible for all monument replacement to an existing or better than condition as determined by the Engineer.

1.8 SAFETY AND HEALTH. The Contractor shall comply with, and is responsible for enforcement of safety and health regulations for construction, promulgated by the Secretary of Labor under Section 107 of the Contract Hours and Safety Standards Act, as set forth in Title 29, C.F.R.

Copies of these regulations may be obtained from the Labor Building, 14th and Constitution Avenue NW, Washington, DC 20013.

The Contractor shall also comply with the provisions of the Federal Occupational Safety and Health Act as amended.

1.9 PUBLIC SAFETY AND CONVENIENCE

1.9.1 The Contractor shall comply with rules and regulations of City, County, and State authorities regarding the closing of public streets. No street shall be closed by the Contractor to the public except by express permission of the Engineer. Sites from which the public is excluded shall be marked and guarded by such Contractor in a manner appropriate for the hazard.

1.9.2 All obstructions within the traveled roadways shall be protected by approved visual warning devices such as signs, barricades, and lights where necessary or as ordered by the Engineer for the safety and convenience of the traveling public. Such devices shall conform to the requirements of the Occupational Safety and Health Administration. The Contractor shall be responsible for the safety and convenience of the public on that right-of-way wherein the Contractor shall place pipeline or pipeline accessories according to the contract agreement. Failure of the Owner or the Engineer to notify the Contractor of deficiencies in providing for the public safety and convenience shall not relieve the Contractor from his responsibility. The Contractor shall use every reasonable precaution to safeguard the persons and property of the traveling public. All obstructions shall be protected with lighted barricades which shall operate from sunset to sunrise.

1.9.3 The Contractor shall be required to confine construction operations within the dedicated rights-of-way for public thoroughfares, or within areas for which construction easements have been obtained, unless he has made special arrangements with the affected property owners in advance. The Contractor shall be required to protect stored materials, cultivated trees and crops, and other items located adjacent to the proposed construction site. Property owners affected by the construction shall be notified by the Contractor at least 48 hours in advance of the time the construction begins. During all construction operations, the Contractor shall construct and maintain such facilities as may be required to provide access by all property owners to their property. No person

101-5 shall be cut off from access to his residence or place of business for a period exceeding 8 hours, unless the Contractor makes special arrangements with the affected persons.

1.9.4 Any damage to private property, either inside or outside the limits of the easements provided by the Owner, shall be the responsibility of the Contractor. Before final payment will be authorized by the Engineer at completion of the construction, the Contractor shall obtain from the permit or easement grantors, a release indicating the work of restoration has been satisfactorily completed in accordance with the terms of the permit or easement. Should it be found impossible for the Contractor to obtain any of the required releases, either because of the absence of the grantors or because of impractical demands by the grantors, the Engineer may waive this requirement if, in his opinion, the Contractor has fulfilled his obligations.

1.9.5 The Contractor shall conduct his work in a fashion that will minimize inconvenience to residents of the area. The Contractor shall observe all local noise ordinances and working hour ordinances. The Contractor shall control air-borne debris that originates in the construction right-of-way. Air-borne fine particles, dust, sand, smoke, trash, and debris shall be controlled on a regular basis, as approved by the Engineer, by the use of a dust settling spray. The Contractor is also responsible for the disposal of paper trash and other debris.

1.10 QUANTITIES AND PAYMENT. The amount of work to be done, and materials or services to be furnished under the Contract as noted in the proposal, are estimates and are not to be taken as an expressed or implied statement that the actual amount of work or materials will correspond to the estimate. In the event the total amount of the lowest acceptable bid exceeds the amount of funds available for the project, the scope of work will be modified as determined by the Owner and Engineer.

The right is reserved to increase or decrease or to entirely eliminate certain items from the work or materials if found desirable or expedient, and the Contractor is cautioned against unbalancing his bid by prorating his overhead into one or two items only when there are a number of items on the proposal. The overhead and indirect charges should be prorated on all items in the proposal.

The Contractor will be allowed no claims for anticipated profits, loss of profits, or for damages because of any difference between the estimated and the actual amount of work done, or materials furnished or used in the completed project.

Other items of work defined in the specifications, but not listed in the Bid Schedules, shall be considered incidental to one or more of the items listed in the Bid Schedules and shall be paid for under the bid item listed to which it is related, as determined by the Engineer.

1.11 RESTORATION OF CONSTRUCTION SITE. Throughout the period of construction, the Contractor shall keep the work site free and clean of all rubbish and debris and shall promptly remove from any portion of the site or from property adjacent to the site of the work all

101-6 unused materials, surplus earth and debris, excepting select material which may be required for refilling or grading.

Upon completion of the work and prior to final acceptance of the project, the Contractor shall remove from the vicinity of the completed work, all surplus materials and equipment belonging to him or used under his direction during construction. Cleanup and restoration around the booster pump station, sand trap/water tank and associated waterlines shall be completed and in accordance with the time schedule in these specifications. Along the entire project location, the Contractor shall do the following special cleaning for all trades at completion of the work: dress up earthwork areas around pipelines, structures, and other facilities; fine grade rough areas to final grade; remove boulders and unsightly areas; feather cut and fill into existing terrain; other cleanup work as requested by the Engineer .

1.12 TAXES. The Contractor will pay all sales, consumer, use and other similar taxes required by the law of the place where the work is performed.

1.13 REFERENCES. Abbreviations used in this specification for various societies, organizations, or government bodies shall stand for the following:

AASHTO American Association of State Highway and Transportation Officials ACI American Concrete Institute ANSI American National Standards Institute ASTM American Society for Testing and Materials AISC American Institute of Steel Construction AITC American Institute of Timber Construction AISI American Iron and Steel Institute APA American Plywood Association AWWA American Water Works Association AWS American Welding Society ICBO International Conference of Building Officials NEC National Electric Code NEMA National Electrical Manufacturers' Association NWWDA National Wood Window & Door Association UL Underwriter's Laboratory UBC Uniform Building Code

Project Meetings 102-1

SECTION 102

PROJECT MEETINGS

1.1 PRECONSTRUCTION CONFERENCE. A pre-construction conference between Engineer, Owner's representative, and Contractor shall be held at the site prior to commencement of the Work.

(a) This meeting shall be for the purpose of -

(1) Resolving current problems,

(2) Further orienting Contractor to requirements of the Contract Documents,

(3) Informing Contractor of Engineer's responsibility to Owner for inspection,

(4) Working out with Contractor a general schedule of inspection.

1.2 PROGRESS MEETINGS. Periodic job site meetings will be held by Engineer.

(a) Contractor shall attend such meetings and shall require subcontractors to attend as necessary.

(b) These meetings are for the purpose of -

(1) Insuring that all activities are being coordinated properly on project,

(2) To assist in staying on schedule.

(3) Checking Status of -

(a) Submittals,

(b) Changes,

(c) Progress payments,

(d) Other matters will be reviewed.

Submittals 103-1

SECTION 103

SUBMITTALS

1.1 SUBMITTALS. Deliver submittals to the Engineer unless indicated otherwise. Accompany each submittal with a letter of transmittal indicating:

(a) Title of Project

(b) Name of Contractor

(c) Title of Submittal

1.2 PROGRESS SCHEDULE. Immediately after being awarded the Contract, prepare and submit for review an estimated progress schedule for the Work. Progress schedule shall be in sufficient detail to include but not be limited to:

(a) Significant elements of the Work.

(b) Time frame for each element of work with a beginning and ending point.

(c) Percentage of progress of work placed or to be placed in a monthly period of time.

(d) Value of the elements of work and relationship of elements of work one to the other for the total work under the Contract.

Progress schedule shall be updated monthly and submitted with each periodic estimate for partial pay, and shall show the original progress schedule or revised progress schedule one entry for each item of work as follows:

(a) Progress of work placed prior to period of partial payment then being requested.

(b) Progress during period of partial payment being requested.

(c) Remaining work to be done by each item of work and for total work remaining under the Contract.

1.3 SUBMITTAL SCHEDULE.

Contractor shall, within ten (10) calendar days after receipt of Notice to Proceed, furnish a submittal schedule listing all items that will be furnished for review to Owner and Engineer.

(a) This schedule shall include, among other things, shop drawings, Manufacturer's

103-2 literature, certificates of compliance, materials samples, materials colors, guarantees, etc.

(b) Schedule shall indicate type of item, contract requirement reference, Contractor's scheduled dates for submitting the items, and projected need dates for review answers from Engineer. Schedule shall show a minimum of seven (7) calendar days after receipt for review by Engineer. If re-submittal is required, an additional five (5) days will be allowed for after receipt. Contractor shall revise and/or up-date this schedule as appropriate and submit it with each payment estimate until all items have been submitted and reviewed.

(c) Submittal schedule shall be coordinated with progress schedule for all the Work. Contractor shall revise and/or up-date the schedule to insure consistency with the progress schedule as it may be revised and/or updated. Such revised submittal schedules shall be promptly provided.

(d) Furnishing of the submittal schedule or revision thereto shall not be interpreted as relieving Contractor of his obligation to comply with all the Specification requirements for items on the schedule.

Progress schedule shall be updated monthly and submitted with each periodic estimate for partial pay, and shall show the original progress schedule or revised progress schedule one entry for each item of work as follows:

(a) Progress of work placed prior to period of partial payment then being requested.

(b) Progress during period of partial payment being requested.

(c) Remaining work to be done by each item of work and for total work remaining under the Contract.

1.4 PROGRESS REPORTS.

Contractor shall prepare daily reports of his operations and forward them to Engineer on at least a weekly basis. The daily report will contain at least the following information:

(a) Weather conditions,

(b) Manpower on the job in each trade,

(c) Major items of equipment on the job,

(d) A brief summary of work accomplished that day,

(e) Materials, equipment, or Owner-furnished items arriving or leaving site, 103-3

(f) Significant events,

(g) Any tests made and their result if known,

(h) Any oral instructions received,

(i) Visitors to the job.

Contractor shall maintain a file of copies of all daily reports on the site and make it available to Engineer or Owner upon request.

1.5 SHOP DRAWINGS, PRODUCT DATA, & SAMPLES.

Definitions.

(a) Shop drawings are drawings, diagrams, illustrations, schedules, performance charts, brochures, and other data which are prepared by Contractor or any subcontractor, manufacturer, supplier, or distributor. Shop drawings illustrate some portion of the Work and confirm dimensions and conformance to Contract Documents.

(1) Shop drawings are not a part of the Contract Documents.

(b) Samples are physical examples furnished by Contractor to illustrate materials, equipment, color, or workmanship and to assist in the establishment of standards by which the Work will be judged.

Procedure.

(a) Contractor shall review and designate (stamp) his approval and submit to Engineer, with reasonable promptness and in orderly sequence, all shop drawings and samples required by the Contract Documents.

(1) Divisions and Sections of the Project Manual requiring submission of shop drawings to Engineer are as follows. If a broadscope Section heading is given, all of the subsections in that Section are to submit shop drawings.

103-4

(2) Shop drawings and samples not required by the Contract Documents but requested by Contractor or supplied by those under contract to him need not be submitted to Engineer for approval unless specifically requested. These shop drawings shall meet all specified shop drawing requirements except those relating to submission to Engineer.

(b) Shop drawings and samples shall be properly identified as specified or as Engineer may require.

(c) Contractor shall reject shop drawings not in conformance with the Contract Documents.

(d) Shop drawings shall be complete and detailed. If reviewed by Engineer, each copy of the shop drawings will be identified as having received such approval by being so stamped and dated. If review “with exception” or “as noted” by Engineer is so identified, stamped, and dated, Contractor shall comply with notations shown. If such qualified review is shown or if the shop drawings are not reviewed by Engineer or if resubmission is so directed, Contractor shall make any corrections required or indicated by Engineer at Contractor's expense.

(1) Any shop drawing or correction indicated on a shop drawing which does not conform to the Contract Documents shall be submitted as a change order and approved, as required under Section 14, of the General Conditions, prior to performing the changed work.

(2) Number of copies of shop drawings and other submittals required will be established at the Pre-construction Conference if more than three are required. Contractor shall bear cost of reproducing copies of shop drawings required by all concerned. In lieu of prints, a sepia may be required.

By approving shop drawings and samples, Contractor thereby represents that he has determined and verified all field measurements, field construction criteria, materials, catalog numbers, and similar data, or will do so, and that he has checked and coordinated each shop drawing and sample with requirements of the Work and of the Contract Documents.

No work requiring a shop drawing or sample submission shall be commenced until submission has been approved by Engineer.

Samples.

(a) Where specified or required, Contractor shall submit samples to Engineer together with specification material, affidavits, and other documentation as may be required by Engineer.

(b) It is Contractor's specific responsibility to ascertain that samples submitted have been

103-5 checked and approved by him.

(c) Cost of samples, together with transportation, delivery, and any other costs, shall be borne by Contractor. Samples shall be submitted in duplicate and one of each sample shall be retained in the office of Engineer until completion of the Project.

(d) Where samples are specifically required to be submitted for approval, no work involving the sampled materials shall proceed until written approval has been obtained from Engineer.

Review By Engineer.

(a) Review of shop drawings by Engineer shall not be construed as a complete check but will indicate only that the general method of construction and detailing is satisfactory. Review of such drawings will not relieve Contractor of responsibility for any error which may exist in the submittals.

1.6 SCHEDULE OF VALUES. A schedule of dollar values shall be submitted to Engineer and Owner not less than twenty (20) days prior to first request for payment and shall be a condition precedent to processing first payment. Schedule of values shall be submitted on Owner's standard payment request form. This breakdown shall follow the trade Divisions of the Specification and each item there under shall include its pro rata part of overhead and profit so the sum of the items will equal the contract price. Breakdown will correspond exactly to items of work in the progress schedule including work of subcontractors.

1.7 CONSTRUCTION PHOTOGRAPHS

Contractor shall prepare construction photography of the project construction corridor and forward them to Engineer at least 1 (one) week prior to the start of construction. The construction photography will contain at least the following information:

(a) Submit photography which adequately documents the preconstruction conditions of the construction site, including all adjacent property, driveway access, and landscaping. Submittal of photography shall be as soon as processed and before construction begins.

(b) Photography may be either still photography or video tape documentation.

(c) Additional photography may be required during construction as determined by the Engineer.

(d) Submit two (2) color prints (minimum 3 ½” X 5 ½”) of each view if still photography is used, or two copies of the video tape in DVD or electronic format if video taping is used.

103-6

(e) Identify on each print or video tape listing: name of the project, date of photography, name and address of photographer, and photographer’s numbered identification of exposure or station or other definite location identification.

(f) All photography shall, when submitted, have accompanying dated and notarized documentation stating the above information.

(g) Photography shall consist of a fractural presentation with correct exposure and focus.

Photography shall be performed when there is no snow on the ground.

(h) The contractor shall pay all costs for specified photography and prints or video taping. There is no separate pay item for photography. Therefore, the cost of photographs or video media shall be included in the lump sum price for mobilization.

Material & Equipment 104-1

SECTION 104

MATERIAL & EQUIPMENT

1.1 MATERIAL & EQUIPMENT. Materials incorporated into Project shall be new, except as otherwise indicated in the Specifications, of specified quality, and furnished in sufficient quantity to facilitate proper and speedy execution of the Work.

Contractor shall, if required, furnish evidence of the quality of any materials.

Materials not meeting requirements of the Contract Documents shall be removed from Project by Contractor without expense to Owner.

1.2 DELIVERY, STORAGE, & HANDLING. Materials shall be delivered to the site in original packaging with labels and trademarks intact, and such labels and trademarks shall remain intact until used.

Contractor shall confine his apparatus, storage of materials, and operations of his workmen to limits indicated by law, ordinances, and permits and shall arrange and maintain parking of vehicles and storage of materials in an orderly manner leaving all walks, driveways, roads, and entrances, unencumbered.

All equipment on site shall be protected from physical damage and from the elements by measures satisfactory to Engineer. All rotating equipment shall be rotated four turns once each week during construction.

It shall be the responsibility of the Contractor to coordinate with the supplier all delivery schedules and to unload all materials. Materials will be delivered to locations where the trucks can deliver under their own power.

It shall be the responsibility of Contractor to inspect all materials as they are unloaded at the project site. If there is any cause for rejection of the materials, the Contractor shall immediately notify the project inspector and shall obtain a written release of liability for the replacement of the damaged materials. Any material damaged by the Contractor unloading the material or of which a written release of liability for the replacement of damaged materials is not obtained shall be replaced in kind by the Contractor, at the Contractors sole expense.

It shall be the responsibility of Contractor to secure and safeguard all materials supplied for the project and unloaded and accepted by the Contractor. Any material lost, stolen, or damaged shall be replaced in kind by the Contractor, at the Contractors sole expense.

1.3 PRODUCT OPTIONS & SUBSTITUTIONS. When several materials are specified in the

Material & Equipment 104-2

Contract Documents by name for one use, Contractor may select any one of those so specified.

The mixing of several products specified by name for one use is prohibited.

Wherever an item or class of material is specified exclusively by trade name, name of maker, or by catalog reference, use such item only unless Engineer's approval for a substitution is secured by Addendum a minimum of 10 days before bid opening time. Items and material not specified in the Contract Documents and installed in the Work shall be removed and replaced by specified items and material at no additional cost to Owner and for no additional time added to Contract.

Wherever words “Approved by”, “Satisfactory to”, “submitted to”, “inspected by,” or similar phrases are used in this Specification, they shall be understood to mean that the material or item referred to shall be approved by, be satisfactory to, submitted to, or inspected by Engineer.

Contract Closeout 105-1

SECTION 105

CONTRACT CLOSEOUT

1.1 FINAL CLEANING. Contractor shall, at completion of work, remove all rubbish from under and about the Construction Site.

If Contractor fails to clean up, Owner may do so and the cost thereof will be charged to the Contractor.

1.2 PRESUBSTANTIAL COMPLETION, SUBSTANTIAL COMPLETION, & FINAL

INSPECTIONS.

Pre-substantial Completion Inspection.

(a) Upon Contractor's request, Engineer (and his consultants as appropriate) will make an inspection and furnish to Contractor a list of items to be corrected by Contractor.

(b) Upon correction of these items, Engineer will arrange a substantial completion in-spection to include Owner.

Substantial Completion Inspection.

(a) At the substantial completion inspection, unless building is rejected, Owner, Engineer, and Contractor will execute a Certificate of Substantial Completion which states the dates for -

(1) Commencement of warranties,

(2) Final completion inspection,

(3) Modifications to the amount assessed for liquidated damages.

(b) After inspection, Engineer will furnish final list of items to be corrected.

Final Inspection.

(a) Final Completion Inspection will ensure that all deficiencies noted at the substantial completion inspection have been corrected according to terms of the substantial completion certificate.

(b) The Contractor shall obtain signed release waivers from all suppliers and subcontractors before final payment will be authorized.

Contract Closeout 105-2

(c) When all items have been corrected, Engineer will issue a certificate authorizing final payment.

(d) If all items have not been corrected as agreed, Owner may elect to complete the Work under provisions of Section 16 of the General Conditions.

1.3 PROJECT RECORD DOCUMENTS. Contractor shall deliver to Engineer prior to substantial completion inspection:

(a) Accurate “as built” drawings and letters of the work if the work is constructed in any way at variance to that shown on Contract Documents. “As built” drawings or descriptive letters for other work will be supplied if requested.

(b) Certificates of inspection and of occupancy that may be required by authorities having jurisdiction over the Work.

1.4 WARRANTIES & BONDS. When written guarantees beyond one year after substantial completion are required of any section of the Work, Contractor shall secure such guarantees and/or warranties properly addressed and signed and in favor of Owner. These documents shall be delivered to Engineer upon substantial completion of Contractor's work and prior to execution of Certificate of Substantial Completion.

Delivery of guarantees and warranties shall not relieve Contractor from any obligation assumed under any other provisions of his contract.

Nothing herein intends or implies that guarantees and/or warranties shall apply to work abused or neglected by Owner.

Mobilization 106-1

SECTION 106

MOBILIZATION

DESCRIPTION

1.1 GENERAL. This item of work is provided to cover the Contractor's cost for general and miscellaneous responsibilities and operations not normally attributable to, or included in, any other single bid schedule item. This shall include, but not necessarily be limited to, work, described or enumerated in this section under the following subsections.

CONSTRUCTION

2.1 MOVING TO AND FROM JOB SITE. This shall include the Contractor's preliminary arrangements for starting construction operations, work schedules, and transportation of equipment and personnel to and from the project.

2.2 TEMPORARY FACILITIES.

Field Office. The Contractor shall provide and maintain a temporary field office on the project or within 5 miles of the project limits.

Sanitary Facilities for Construction Workers. The Contractor shall provide, for all his workers on the project, adequate and reasonably convenient uncontaminated drinking water supply and temporary toilet facilities. All facilities shall comply with the Utah Safety and Health Act.

Utilities for Construction Operations. The Contractor shall make arrangements for, secure and pay for, any and all utility supplies such as electric power, water, natural gas or telephone that may be required for prosecution of the work.

Temporary Lighting. The Contractor shall provide all temporary lighting required for prosecution of his work and for employee and public safety. As a minimum, lighting levels during working hours shall meet the requirements of U.O.S.H.A. Subsection 1926.56 Illumination.

Heating and Ventilating. The Contractor shall provide any and all heating and ventilating equipment required to assure a safe environment for workers and to prevent damage to the project facilities from freezing or excessive temperature.

2.3 PUBLIC SAFETY AND TRAFFIC CONTROL. The cost of all safety and traffic control devices shall be included in the lump sum bid price for “Mobilization.”

Mobilization 106-2

2.4 RESTORATION OF CONSTRUCTION SITE. The cost of all clean-up work as specified in the following sections shall be included in the lump sum price for “Mobilization” in the Bid Schedules.

2.5 TEMPORARY UTILITIES. The Contractor shall arrange for, secure and pay directly any and all temporary utility supplies he may require for prosecution of his work. The cost of such utilities shall be included in the lump sum price of “Mobilization.”

2.6 BONDS AND PERMITS. The Contractor shall secure all bonds and permits required for the prosecution of the work, the cost of which shall be included in the lump sum price of “Mobilization”.

2.7 CONSTRUCTION PHOTOGRAPHY. The cost of all construction photography shall be included in the lump sum bid price for “Mobilization.”

2.8 STORMWATER POLLUTION PREVENTION PLAN. The contractor shall complete and maintain the Storm Water Pollution Prevention Plan (SWPPP) for the project per the State of Utah requirements. The contractor shall file a notice of intent and notice of termination with the State of Utah for the Storm Water Pollution Prevention Plan (SWPPP). All costs associated with the creation and implementation of the plan, including filing fees shall be included in the lump sum price of “Mobilization”.

Method of Measurement and Basis of Payment 107-3

SECTION 107

METHOD OF MEASUREMENT AND BASIS OF PAYMENT

All work will be measured by the units indicated in the Bid Schedule. Payment will be considered complete compensation for all labor, material and equipment necessary to complete each item in accordance with this Specification and the City of St. George Standard Specifications for Design and Construction.

1.1 Bid Item #1: Mobilization. Payment for this work will be made at the contract unit price for "Mobilization" under bid item #1 of the Bid Schedule. Five payments will be made in accordance with the following schedule:

(1) When 5% of the original contract amount is earned, 25% of the amount bid for mobilization, or 2 1/2% of the original contract amount, whichever is lesser, will be paid.

(2) When 25% of the original contract amount is earned, an additional 35% (cumulative total:

60%) of the amount bid for mobilization, or 6% of the original contract amount, whichever is lesser, will be paid.

(3) When 65% of the original contract amount is earned, an additional 30% (cumulative total:

90%) of the amount bid for mobilization, or 9% of the original contract amount, whichever is lesser, will be paid.

(4) When 80% of the original contract amount is earned, an additional 10% (cumulative total:

100%) of the amount bid for mobilization, or 10% of the original contract amount, whichever is lesser, will be paid.

(5) Upon completion of all work on the contract any unpaid amount of the original contract amount for mobilization will be paid.

Nothing herein shall be construed to limit or preclude partial payments. Payment for this item will be made at the contract lump sum price specified in the Bid Schedule under Bid Item #1.

1.2 Bid Item #2: Removals

Measurement for payment of this item shall be lump sum. The price bid shall include removal and disposal of all items incidental to improvements including concrete, piping, or unsuitable material, asphalt, road-base, fencing, and landscaping removal as indicated on the plans. This price bid shall also include removal of the existing 2 MG tank, liner, and any other appurtenances required to install the new 2 MG tank. This item shall include trucking, hauling, loading and properly disposing of all such materials. All disposal locations shall be approved in writing by the Engineer prior to payment.

Payment for this item will be made at the contract lump sum price specified in Bid Schedule under Bid Item #2.

107-4

1.3 Bid Items #3, and #4: Earthwork and Grading for Water Tank

This item is to excavate the Tank Site and backfill as required to the elevations shown on the construction drawings. This item shall include all excavation and grading necessary for construction of the new Tank and turn around area at the tank. This item will include all excavation by any means, placement and compaction of fill material, and hauling and properly disposing of any excess material or importing any material required for the tank site. Excavation for subgrade of the tank shall be a minimum of 12” below bottom of footing to allow for a leveling course as outlined in the Geotechnical Investigation. All excavation and structural fill for the tank and pipeline shall meet or exceed the specification and the requirements of the Geotechnical Investigation St. George Industrial 2 MG Tank Replacement prepared by RB&G Engineering.

The price bid for this item shall consist of all materials, labor and equipment necessary to excavate, backfill, and compact around the new Tank.

Measurement for payment of this item shall be at the unit price specified in the Bid Schedule under Bid Items #3, and #4

1.4 Bid Item #5: Furnish and Install 2,000,000 Gallon Concrete Water Tank

This item shall consist of furnishing all materials, labor and equipment necessary to construct the 2 MG reinforced concrete water tank with as specified in the construction drawings. The pay limit for this item includes everything within 10’ of the edge of the water tank as indicated on the plans, including structural fill under the tank, leveling course, and base course. This item does not include excavation and backfill. Excavation and backfill for this item is paid for under bid item #3 & #4.

This item shall include, but not be limited to all materials, labor, concrete, concrete admixtures, steel reinforcement, hatches, vents, ladders, piping, manifolds, valves, fittings, shoring, bracing, forms, pumping, water stops, and base course to construct the water tank as shown on the construction drawings.

This item shall also include cleaning and disinfection of the water tank and leak testing the tank.

The owner will provide the water to fill the water tank one time. If the water tank does not pass the leak test or bacteria test on the first try the contractor will be responsible to dispose of the water and pay for the water to refill the tank at the current hydrant meter pricing.

Measurement for payment of this item shall be lump sum as specified in the Bid Schedule under Bid Item #5.

1.5. Bid Items #6 & #7: Install Piping.

This item is for furnishing and installation of 12-inch culinary water pipe and materials as indicated in the bid schedule and on the construction drawings. The Ductile Iron Pipe shall be Class 51 pipe and shall be supplied with a blue poly sock. The PVC drain pipe shall be SDR-35 pipe. This item shall include, but not be limited to, all clearing, trench excavation including rock excavation, gaskets, bedding, backfill, installation with locator wire, replacement of disturbed material, leak

107-5 and pressure testing, disinfecting (chlorination) and restoration of surface improvements not specifically covered in a separate bid item. This item shall also include import and compaction of bedding material, trench backfill and compaction, and export of excess trench material and/or import of additional trench backfill material as required.

Measurement for payment of this item shall be based on the number of lineal feet of Pipe actually furnished and installed under the Bid Schedule, Bid Items #6 & #7.

1.6 Bid Items #8 – Furnish and Install Cleanout

The price bid for this item shall be considered full compensation for all labor, materials, and equipment necessary to furnish and install a cleanout at the size and the location and grade shown on the construction drawings including, but not limited to, cast iron monument ring and cover, concrete collar, brass cap, piping, additional excavation, trucking, and backfill.

Payment for this item will be made at the contract unit price bid for each as specified under bid items #8.

1.7 Bid Item #9: Furnish and Install Headwall

This item shall consist of furnishing all materials, labor and equipment necessary to install a concrete headwall with rodent screen on the overflow for the water tank as shown on the construction drawings.

This item shall include, but not be limited to, concrete, rebar, excavation, hauling grading, grouting, forming, placing, rodent screen, and any other item necessary to construct the headwall as shown on the construction drawings.

Measurement for payment of this item shall be on a lump sum basis as indicated in the Bid Schedule under Bid Item #9.

1.8 Bid Item #10: Butterfly Valves

This item is to furnish and install valves at locations shown on the construction drawings.

The unit price bid for this item shall consist of all materials, labor and equipment necessary to provide a complete and functioning valve of the size and type specified. This shall include, but not be limited to, valve, valve box, thrust restraints, reinforced concrete support blocks, valve spacers, tracer wire, polyethylene wrapping, gaskets, pressure testing, trenching, excavation, import and compaction of bedding material, trench backfill and compaction, and export of excess trench material and/or import of additional trench backfill material as required.

Measurement for payment of these items shall be based on the actual number of valves installed under the Bid Schedule, Bid Item #10.

1.9 Bid Items #11-13: Install Elbows, Tees, Flanges, Reducers, and Caps

107-6

These items are for the furnishing and installation of ductile iron fittings, flange adaptors, blind flanges, caps, and other miscellaneous fittings as identified in the bid schedule and construction drawings.

The unit price bid for these items shall consist of all materials, labor and equipment necessary to furnish and install fittings. This shall include, but not be limited to, thrust restraints, tracer wire, polyethylene wrapping, gaskets, pressure testing, trenching, excavation, import and compaction of bedding material, trench backfill and compaction, and export of excess trench material and/or import of additional trench backfill material as required.

Measurement for payment of these items shall be based on the actual number installed of each of the fittings installed under the Bid Schedule, Bid Items #11-13.

1.10 Bid Item #14-15 – Remove & Replace Existing Butterfly Valves

This item shall consist of furnishing all materials, labor and equipment necessary to remove and replace the existing Butterfly valves as shown on the construction drawings on the water pipeline.

The price bid for this item shall be considered full compensation for all labor, materials, and equipment necessary to remove the existing valve and provide a complete and functioning valve of the size and type specified. This shall include, but not be limited to, valve, valve box, thrust restraints, reinforced concrete support blocks, valve spacers, tracer wire, polyethylene wrapping, gaskets, pressure testing, solid sleeves, couplers, joint restraints, pipe and fittings, trenching, excavation, import and compaction of bedding material, trench backfill and compaction, and export of excess trench material and/or import of additional trench backfill material as required.

Measurement for payment of this item shall be on a per each basis as indicated in the Bid Schedule under Bid Items #14-#15.

1.11 Bid Item #16 - #17 – Connection to Existing Water Lines

The price bid for this item shall be considered full compensation for all labor, materials, and equipment necessary to connect the new water pipe or fitting to the existing water pipe or fitting including, but not limited to, solid sleeves, couplers, joint restraints, pipe and fittings, additional excavation, trucking, and backfill and compaction.

Payment for this item will be made at the contract lump sum bid for each as specified in the Bid Schedule under Bid Item #16-#17.

1.12 Bid Item #18 – Cut into Existing System with 12” Tee and (3) 12” BF Valves

This item shall consist of furnishing all materials, labor and equipment necessary to cut into the existing line and install a 12” tee and (3) 12” BF Valves as shown on the construction drawings on the water pipeline.

107-7

The price bid for this item shall be considered full compensation for all labor, materials, and equipment necessary to cut into the existing line and install a 12” tee and (3) 12” BF Valves. This shall include, but not be limited to, valve, valve box, thrust restraints, reinforced concrete support blocks, valve spacers, tracer wire, polyethylene wrapping, gaskets, pressure testing, solid sleeves, couplers, joint restraints, pipe and fittings, trenching, excavation, import and compaction of bedding material, trench backfill and compaction, and export of excess trench material and/or import of additional trench backfill material as required.

Measurement for payment of this item shall be on a per each basis as indicated in the Bid Schedule under Bid Item #18.

1.13 Bid Items #19 & #20 – Install Fencing

This item shall consist of furnishing and installing temporary and permanent fencing according to the plans.

Payment for this item shall be considered complete compensation for materials, labor, tools, and equipment necessary to construct the fencing.

Measurement for these items shall be by the linear foot along the outside face of the fencing.

Payment for this item will be made at the contract unit price specified in the Bid Schedule Under Bid Items #19 & #20.

1.14 Bid Items #21– Salvage and Service Power Equipment to New Tank The price bid for this item shall be considered full compensation for all labor, materials, and equipment necessary to salvage telemetry and power equipment from the existing tank and service the new tank.

Payment for this item will be made at the contract unit price specified in the Bid Schedule Under Bid Items #21.

Non-Payment Items 108-1

SECTION 108

Non-Payment Items

Non-Payment Items. The Contractor shall not be paid for the following items.