5-A - Pelican Haven Wetlands Restoration 100 - All Sheets.pdf
PDF 5 MB Posted
- Solicitation number
- JH27-4
- Issued by
- Weber County, Hildale City, Utah
About this file
This is a construction design plan set prepared by Equinox Engineering for the Pelican Haven Wetlands Restoration project, administered by the State of Utah Department of Natural Resources, Division of Wildlife Resources, in Ogden Bay WMA. The project involves the construction of an 8-foot-wide levee with uniform top elevation of 4212.0 feet and 3H:1V side slopes spanning approximately 37,660 linear feet (stations 0+00 to 37+66). The scope of work includes installation of water control structures (Type A precast concrete structures with 18-inch and 24-inch diameter HDPE outlet pipes), erosion control measures, compacted fill placement, filter fabric installation, gravel surfacing, and various site restoration elements including slope toe protection material, fetch intercept berms, and grubbings islands. The mandatory pre-bid site visit is scheduled for August 4, 2026, at 10:00 a.m. at Ogden Bay WMA Headquarters in Hooper, Utah, with attendance required for bidder eligibility. The project must be completed by September 30, 2026, and contract award will be made to the lowest cost responsive and responsible vendor based on the combined cost of ten line items.
The construction design plans specify detailed technical requirements including concrete compressive strength of 4,000 PSI minimum at 28 days, soil compaction standards of 90 percent modified Proctor density per ASTM D698, HDPE pipe conforming to ADS N-12 specifications, and rip rap erosion control rock meeting specific gradation requirements with filter fabric separation. All materials and workmanship must conform to the International Building Code as amended by Utah and local agencies. The contractor is responsible for all site conditions including dewatering, utility identification and protection, Blue Stakes notification prior to excavation, and obtaining all necessary regulatory permits with minimum 48-hour approval prior to construction start. On-site borrow areas are designated as primary sources for fill material, with specific restrictions on depth and location to prevent damage to adjacent infrastructure and water control structures. The contractor must maintain construction drawings and specifications on-site at all times and document any field changes on a record set of plans.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Vendor Prerequisites - IFB Agency.pdf | ||
| 2-Att.-A-PO-Terms-and-Conditions (3).docx | DOCX document | |
| 7-703722-1 National Audubon Society TNC Pelican haven.pdf | ||
| 3-Attachment C - Assumption and Estimates used for Bid Schedule.docx | DOCX document | |
| 6-Attachment B Scope of Work.pdf | ||
| 4-Attachment D - Bond Language.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CIVIL DESIGN ENGINEER:
(801) 739-8218
WEST JORDAN, UTAH 84081
POST OFFICE BOX 612
EQUINOX ENGINEERING
Wetland Environmental Consulting and Civil Engineering
THE ENGINEER PREPARING THESE PLANS WILL NOT BE RESPONSIBLE
FOR, OR LIABLE FOR, UNAUTHORIZED CHANGES TO OR USES OF THESE
PLANS. ALL CHANGES MUST BE IN WRITING AND MUST BE APPROVED BY
THE PREPARER OF THESE PLANS.
OGDEN BAY WMA
PELICAN HAVEN WETLANDS RESTORATION
SHEET DESIGNATOR
www.equinoxengineering.us
BINDING
ORDER
SHEET TITLE:
SHEET IDENTIFIER:
PROJECT OWNER:
MARK DATE DESCRIPTION
PREPARER:
PROFESSIONAL SEAL:
ENGINEERING
EQUINOX
PROJECT IDENTIFICATION:
PROJECT SPONSOR:
DRAWING BY:
SUBMITTAL #:
CHECKED BY:
DATE:
EQUINOX PROJECT:
OWNER PROJECT:
SMC
WEC
07/09/2026 www.equinoxengineering.us
COVER SHEET
CV 01
AERIAL IMAGE FROM
GOOGLE EARTH
May 21, 2025
OWNER: STATE OF UTAH
DEPARTMENT OF NATURAL RESOURCES
OGDEN, UTAH 84405
1" = 100,000'
VICINITY MAP
1" = ±162 Miles
UTAH MAP
1" = 40,000'
AREA MAP
PROJECT LOCATION
1" = 3,000'
SITE MAP
PELICAN HAVEN
WETLANDS
RESTORATION
STATE OF UTAH
DIVISION OF
NATURAL
RESOURCES
STATE OF UTAH
DEPARTMENT OF
NATURAL
RESOURCES
515 EAST
5300 SOUTH
OGDEN, UTAH
84405
UT-139-01
266113
S-100
AREA MAP INSET SITE MAP INSET
COVER SHEET 1 CV01
GENERAL NOTES 01 - GENERAL CONCRETE NOTES 2 GN01
GENERAL NOTES 02 - GENERAL EARTHWORK / GRADING NOTES 3 GN02
GENERAL NOTES 03/04 - PROJECT SPECIFIC GENERAL NOTES 4 - 5 GN03 - GNO4
CIVIL PLAN VIEW - SHEET LAYOUT - 3600 SCALE (1" = 300') 6 PV01
CIVIL PLAN VIEW - PROJECT SHEET LAYOUT - 1440 SCALE (1" = 120') 7 PV02
CIVIL PLAN VIEW - PROJECT SHEET LAYOUT - 240 SCALE (1" = 20') 8 PV02A
CIVIL PLAN VIEW - PROJECT SHEET LAYOUT - 1440 SCALE (1" = 120') 9 - 10 PV03 - PV04
CIVIL PLAN VIEW - PROJECT SHEET LAYOUT - 240 SCALE (1" = 20') 11 PV04A
CIVIL PLAN VIEW - PROJECT SHEET LAYOUT - 1440 SCALE (1" = 120') 12 - 13 PV05 - PV06
TYPICAL CONSTRUCTION DETAILS CUT SECTION VIEWS 14 - 16 DT01 - DT03
WCS TYPE A 24 TYPICAL 17 - 23 DTWCS A24-1 - DTWCS A24-7
WCS TYPE A SAFETY GRATING / STOP LOG TYPICAL DETAILS 24 DTWCS A-8
SHEET TITLEBINDING ORDER
SHEET SET ASSEMBLY ORDER
SUBMITTAL #: S-100 / BID SET - UPDATED JULY 09, 2026
DRAWING BY:
SUBMITTAL #:
CHECKED BY:
DATE:
EQUINOX PROJECT:
CONTRACT #:
SMC
WEC
07/09/2026
PELICAN HAVEN
WETLANDS
RESTORATION
PROJECT OWNER:
MARK DATE DESCRIPTION
PROJECT IDENTIFICATION:
PROJECT SPONSOR:
BINDING
ORDER
SHEET IDENTIFIER:
PREPARER:
PROFESSIONAL SEAL:
ENGINEERING
EQUINOX
www.equinoxengineering.us
SHEET TITLE:
STATE OF UTAH
DIVISION OF
NATURAL
RESOURCES
STATE OF UTAH
DEPARTMENT OF
NATURAL
RESOURCES
515 EAST
5300 SOUTH
OGDEN, UTAH
84405
UT-139-01
266113
S-100
GN01
THE ENGINEER PREPARING THESE PLANS WILL NOT BE RESPONSIBLE AND/OR LIABLE
FOR UNAUTHORIZED CHANGES TO OR USES OF THESE PLANS. ALL CHANGES MUST
BE IN WRITING AND MUST BE APPROVED BY THE PREPARER OF THESE PLANS.
ABBREVIATIONS / LEGEND
NOT ALL ABBREVIATIONS WILL APPLY TO THIS
PROJECT
AB ANCHOR BOLT
ADDL ADDITIONAL
AL ALUMINUM
APPROX APPROXIMATE
B BOTTOM
BTWN BETWEEN
CL CENTERLINE
CJ CONSTRUCTION JOINT
CLR CLEAR
CONC CONCRETE
CONT CONTINUED / CONTINUOUS
CMP CORRUGATED METAL PIPE
CNTR CENTER
CP CONTROL POINT
DEMO DEMOLITION
DET DETAIL
DIA DIAMETER
DWG DRAWING
DWLS DOWELS
EA EACH
EF EACH FACE
EW EACH WAY
EL ELEVATION
EQ SP EQUAL SPACE / EQUALLY SPACED
EXIST EXISTING
EXP JNT EXPANSION JOINT
FL FLOWLINE
GAVL GALVANIZED
GR GRADE
HDPE HIGH DENSITY POLYETHYLENE PIPE
ID INSIDE DIAMETER
IE INVERT ELEVATION
JTS JOINTS
MAX MAXIMUM
MIN MINIMUM
NO. NUMBER
NTS NOT TO SCALE
OC ON CENTER
OD OUTSIDE DIAMETER
OPNG OPENING
PL PLATE
PROJ PROJECTION
PLCS PLACES
PS PIPE STEEL
PSI POUNDS PER SQUARE INCH
RAD RADIUS
RCP REINFORCED CONCRETE PIPE
REINF REINFORCEMENT
REQD REQUIRED
SB STEEL BENT
SCH SCHEDULE
SECT SECTION
SIM SIMILAR
SQ SQUARE
SR SUPPORT RING
SS STAINLESS STEEL
STA STATION
STD STANDARD
STL STEEL
SYM SYMMETRICAL
T TOP
T&B TOP AND BOTTOM
TH THICKNESS
THRD THREADED
TYP TYPICAL
VERT VERTICAL
WS WATERSTOP
WCS WATER CONTROL STRUCTURE
W/ WITH
GENERAL NOTES
1. CONTRACTOR SHALL BE RESPONSIBLE TO CONTACT BLUE STAKES
PRIOR TO ANY EXCAVATION WITH SUFFICIENT LEAD TIME AS REQUIRED
BY BLUE STAKES. BLUE STAKES UTAH 800.662.4111
2. UNLESS SPECIFICALLY STATED OTHERWISE IN THE PLANS,
SPECIFICATIONS AND/OR CONTRACT DOCUMENTS, THE CONTRACTOR
SHALL BE RESPONSIBLE TO OBTAIN ALL NECESSARY PERMITS FROM
ANY REGULATORY AGENCY THAT HAS JURISDICTION OVER THE
PROJECT SITE AS NEEDED TO COMMENCE CONSTRUCTION ACTIVITY.
ALL PERMITS SHALL BE APPROVED, ISSUED AND IN HAND A MINIMUM
OF 48 HOURS PRIOR TO THE START OF ANY CONSTRUCTION WORK.
3. THE CONTRACTOR SHALL NOT SCALE DRAWINGS FOR CONSTRUCTION
PURPOSES. ANY MISSING DIMENSIONS OR DISCREPANCIES IN THE
DRAWINGS OR PHYSICAL FEATURES SHALL BE BROUGHT TO THE
ATTENTION OF THE ENGINEER FOR RESOLUTION. IF THE CONTRACTOR
PROCEEDS PRIOR TO OBTAINING THE ENGINEERS RESOLUTION THE
CONTRACTOR DOES SO AT THEIR OWN RISK
4. OBSERVATIONS OF THE WORK IN PROGRESS AND ON-SITE VISITS BY
THE ENGINEER OR OWNER ARE NOT TO BE CONSTRUED AS
ACCEPTANCE OR WARRANTIES OF THE CONTRACTOR'S CONTRACTUAL
OBLIGATION.
5. CONSTRUCTION SAFETY IS THE SOLE RESPONSIBILITY OF THE
CONTRACTOR. THE ENGINEER IS NOT RESPONSIBLE FOR SAFETY IN
OR OR ABOUT HE PROJECT SITE, NOR FOR THE COMPLIANCE BY THE
APPROPRIATE PARTY WITH ANY REGULATIONS RELATING THERETO.
6. THE CONTRACTOR SHALL MAINTAIN A SET OF THE CONSTRUCTION
DRAWINGS AND SPECIFICATIONS ON SITE AT ALL TIMES. ONE SET OF
THE CONSTRUCTION DRAWINGS SHALL BE MAINTAINED SOLELY TO
DOCUMENT ANY CHANGES IN THE WORK AS A RESULT OF CHANGE
ORDERS OR FIELD CONDITIONS THAT MAY REQUIRE ALTERNATIVE
CONSTRUCTION DETAILS. ALL SUCH CHANGES SHALL BE MARKED ON
THE RECORD SET OF DRAWINGS IN PERMANENT INK.
7. THE ENGINEER MAY PROVIDE QUANTITIES AND/OR SURVEY DATA FOR
USE BY THE CONTRACTOR. INFORMATION PROVIDED BY THE
ENGINEER IN GOOD FAITH IS ASSUMED TO BE ACCURATE, HOWEVER
THE CONTRACTOR IS RESPONSIBLE FOR VERIFICATION OF QUANTITIES
AS REPORTED ON THE UNIT PRICE BID TABULATION AND SHALL BE
RESPONSIBLE TO LAYOUT AND CONSTRUCT THE WORK TO MEET THE
INTENT OF THE DESIGN.
8. ALL MATERIALS AND WORKMANSHIP SHALL CONFORM TO THE MOST
CURRENT INTERNATIONAL BUILDING CODE (I.B.C.) AS AMENDED BY
THE STATE IN WHICH THE PROJECT IS LOCATED AND LOCAL AGENCIES
AS NEEDED AND AS APPROPRIATE FOR THE PROJECT WORKS.
9. THE STRUCTURES SHOWN ON THE DRAWINGS HAVE BEEN DESIGNED
FOR STABILITY UNDER FINAL CONDITIONS ONLY. THESE PLANS DO
NOT INCLUDE THE NECESSARY COMPONENTS FOR EQUIPMENT OR
EQUIPMENT FOR THE STRUCTURES DURING CONSTRUCTION. THE
CONTRACTOR IS RESPONSIBLE FOR ALL WORK RELATING TO
CONSTRUCTION ERECTION METHODS. BRACING, SHORING, RIGGING,
GUYS, SCAFFOLDING, FORM WORK, AND OTHER WORK AIDS REQUIRED
TO SAFELY PERFORM THE WORK SHOWN.
10. EXCAVATIONS SHALL BE SHORED AS REQUIRED TO PREVENT
SUBSIDENCE OR DAMAGE TO ADJACENT EXISTING STRUCTURES,
UTILITIES OR OTHER EXISTING INFRASTRUCTURE.
GENERAL CONCRETE NOTES CONTINUED
1. ALL CONCRETE IS DESIGNED IN ACCORDANCE WITH AMERICAN
CONCRETE INSTITUTE ACE 350 AND SHALL BE CONSTRUCTED IN
ACCORDANCE WITH THESE PLANS.
2. CONCRETE SHALL HAVE A 28 DAY COMPRESSIVE STRENGTH OF 4000
PSI UNLESS OTHERWISE NOTED.
3. CONCRETE WORK SHALL CONFORM TO ACI 301
4. REINFORCEMENT STEEL SHALL BE DEFORMED BARS CONFORMING IN
QUALITY TO THE REQUIREMENTS OF ASTM A-615. "SPECIFICATIONS
FOR DEFORMED AND PLAIN CARBON-STEEL BARS FOR CONCRETE
REINFORCEMENT". GRADE 60.
5. ALL DETAILING, FABRICATION AND PLACING OF REINFORCING BARS,
UNLESS OTHERWISE INDICATED SHALL BE IN ACCORDANCE ACI-315.
"MANUAL OF STANDARD PRACTICE FOR DETAILING REINFORCED
CONCRETE STRUCTURES". MOST CURRENT EDITION.
6. CONSTRUCTION TOLERANCES SHALL BE IN ACCORDANCE WITH ACI
347.
7. METAL CLIPS OR SUPPORTS SHALL NOT BE PLACED IN
CONTACT WITH
THE FORMS OR THE SUBGRADE. CONCRETE BLOCKS (ADOBE)
SUPPORTING BARS ON SUBGRADE SHALL BE IN SUFFICIENT NUMBERS
TO SUPPORT THE BARS WITHOUT SETTLEMENT, BUT IN NO CASE
SHALL SUPPORT BE CONTINUOUS.
8. REINFORCEMENT BARS AND ACCESSORIES SHALL NOT BE IN CONTACT
WITH PIPE, PIPE FLANGE, OR METAL PARTS EMBEDDED IN CONCRETE.
A MINIMUM OF 2 INCHES CLEARANCE SHALL BE PROVIDE AT ALL TIMES
UNLESS SPECIFICALLY OTHERWISE SPECIFIED.
9. COVER FOR REINFORCEMENT BARS, UNLESS OTHERWISE
SPECIFICALLY NOTED SHALL BE AS FOLLOWS:
A) CONCRETE PLACED AGAINST EARTH - 3 INCHES MINIMUM
B) CONCRETE FORMED BUT EXPOSED TO EARTH, WATER OR WEATHER -
2" MINIMUM
10. UNLESS OTHERWISE NOTED, WALLS AND SLABS SHOWN WITH SINGLE
LAYER OF REINFORCEMENT SHALL HAVE THAT REINFORCEMENT
CENTERED.
11. PLACING OF CONCRETE SHALL CONFORM TO ACI 304R. HOT WEATHER
CONCRETE SHALL BE PLACED PER ACI 305R. COLD WEATHER
CONCRETE SHALL BE PLACED PER ACI 306R.
12. ALL DIMENSIONS TO A JOINT ARE TO THE CENTERLINE OF THE JOINT.
13. DIMENSIONS NOT SHOWN ARE THE SAME AS DIMENSIONS FOR
IDENTICAL DETAILS SHOWN ELSEWHERE.
14. BEFORE PLACING CONCRETE ON GRADE, CARE SHALL BE TAKEN THAT
ALL BURIED MATERIALS BELOW GRADE ARE IN PLACE.
41. REINFORCING STEEL BARS SHALL MEET THE REQUIREMENTS OF
ASTM A615. ALL REINFORCEMENT SHALL BE FREE FROM RUST, OIL,
GREASE, PAINT OR OTHER DELETERIOUS MATTER
42. ITEMS TO BE EMBEDDED IN THE CONCRETE SHALL BE POSITIONED
ACCURATELY AND FIRMLY ANCHORED TO PREVENT DISPLACEMENT
DURING PLACEMENT OF CONCRETE.
43. THE MINIMUM SPLICE LENGTH FOR DEFORMED BARS IS 30 BAR
DIAMETERS OR AS NOTED ON PLANS.
44. UNLESS OTHERWISE SPECIFIED THE MINIMUM REINFORCEMENT FOR
SHRINKAGE AND TEMPERATURE IN MEMBERS SHALL BE ONE HALF
(½) INCH DIAMETER STEEL REINFORCING BARS LOCATED ON TWELVE
(12) INCH CENTERS EACH WAY.
45. FORMS SHALL CONFORM TO THE SHAPES, LINES AND DIMENSIONS AS
SHOWN ON THE DRAWINGS. THEY SHALL BE BRACED AND/OR TIED
TOGETHER TO MAINTAIN POSITION AND SHAPE AND BE SUFFICIENTLY
TIGHT TO PREVENT LEAKAGE. FORMS SHALL BE THOROUGHLY OILED
OR WETTED AND CLEANED OF DEBRIS PRIOR TO PLACEMENT OF
CONCRETE.
46. CONCRETE SHALL BE PLACED OR DEPOSITED AS CLOSELY AS
POSSIBLE TO ITS FINAL POSITION AND WORKED INTO THE CORNERS
AND ANGLES OF THE FORMS AND AROUND ALL REINFORCEMENT AND
EMBEDDED ITEMS IN A MANNER TO PREVENT SEGREGATION OR
AGGREGATES OR EXCESSIVE LAITANCE. CONSOLIDATION OF
CONCRETE SHALL BE ACCOMPLISHED BY MEANS OF INTERNAL TYPE
MECHANICAL VIBRATORS, RODDING, SPACING, OR HAND TAMPING
47. CONCRETE SHALL BE PREVENTED FROM DRYING FOR A CURING
PERIOD OF AT LEAST ONE (1) DAYS AFTER IT IS PLACED. EXPOSED
SURFACES SHALL BE KEPT CONTINUOUSLY MOIST FOR THE ENTIRE
PERIOD. FOR FORMED SURFACES, THE CURING MAY BE LEAVING THE
FORMS IN PLACE AND KEEPING THEM WET FOR THE ENTIRE CURING
PERIOD. MOISTURE SHALL BE MAINTAINED BY SPRINKLING,
FLOODING, OR FOG SPRAYING OR BY COVERING WITH
CONTINUOUSLY MOISTENED CANVAS CLOTH MATS, STRAW, EARTH
OR OTHER APPROVED MATERIAL. IN LIEU OF WATER CURING THE
CONCRETE SHALL BE CURED BY SPRAYING WITH AN APPROVED
SEALING COMPOUND. THE SEALING COMPOUND SHALL BE APPLIED
AS SOON AS PRACTICAL AFTER THE CONCRETE HAS BEEN FINISHED.
THE SEALING COMPOUND SHALL MEET OR EXCEED THE
REQUIREMENTS OF ASTM C309. ALL SURFACES SHALL BE KEPT
MOIST UNTIL THE COMPOUND IS APPLIED.
48. CONCRETE SHALL BE PREVENTED FROM DRYING FOR A CURING
PERIOD OF AT LEAST ONE (1) DAYS AFTER IT IS PLACED. EXPOSED
SURFACES SHALL BE KEPT CONTINUOUSLY MOIST FOR THE ENTIRE
PERIOD. FOR FORMED SURFACES, THE CURING MAY BE LEAVING THE
FORMS IN PLACE AND KEEPING THEM WET FOR THE ENTIRE CURING
PERIOD. MOISTURE SHALL BE MAINTAINED BY SPRINKLING,
FLOODING, OR FOG SPRAYING OR BY COVERING WITH
CONTINUOUSLY MOISTENED CANVAS CLOTH MATS, STRAW, EARTH
OR OTHER APPROVED MATERIAL. IN LIEU OF WATER CURING THE
CONCRETE SHALL BE CURED BY SPRAYING WITH AN APPROVED
SEALING COMPOUND. THE SEALING COMPOUND SHALL BE APPLIED
AS SOON AS PRACTICAL AFTER THE CONCRETE HAS BEEN FINISHED.
THE SEALING COMPOUND SHALL MEET OR EXCEED THE
REQUIREMENTS OF ASTM C309. ALL SURFACES SHALL BE KEPT
MOIST UNTIL THE COMPOUND IS APPLIED.
49. IF THE ENGINEER DETERMINES OR HAS CAUSE TO BELIEVE THAT THE
CONCRETE DOES NOT MEET THE SPECIFICATION THE ENGINEER AT
HIS/HER SOLE DISCRETION MAY REQUIRE THE CONTRACTOR TO
PROVIDE TESTING UP TO AND INCLUDING THE FOLLOWING
SPECIFICATIONS. UTILIZING AN INDIVIDUAL OR COMPANY LICENSED
TO PERFORM CONCRETE TESTING IN THE STATE WHERE THE
PROJECT IS LOCATED, THE CONTRACTOR SHALL PROVIDE AT A
MINIMUM FOR EACH ONE-HUNDRED FIFTY (150) CUBIC YARDS OF
PLACED CONCRETE OR DAILY, WHICHEVER IS LESS, THE
FOLLOWING:
A) SLUMP OR CONSISTENCY TESTING AND MEASUREMENT
IN ACCORDANCE WITH ASTM C143
B) TEMPERATURE TESTING MEASUREMENT IN ACCORDANCE WITH
ASTM C1064
C) AIR CONTENT TESTING MEASUREMENT IN ACCORDANCE
WITH EITHER ASTM C231 (PRESSURE METHOD), ASTM
C173 (VOLUMETRIC METHOD) OR ASTM C138
(GRAVIMETRIC METHOD). THE METHOD CHOSEN BY THE
TESTING FIRM OR COMPANY SHALL BE JUSTIFIED AS
APPLICABLE TO THE RESPECTIVE CONCRETE MIXTURE.
D) STRENGTH SPECIMENS TESTING AND MEASUREMENT IN
ACCORDANCE WITH ASTM C31. A MINIMUM OF FOUR (4)
CYLINDER CONCRETE BREAK SAMPLES SHALL BE
TAKEN AND THE AVERAGE OF THE TWO SEVEN (7) DAY
AND TWO TWENTY-EIGHT (28) DAY RESULTS REPORTED.
E) ALL TESTS PERFORMED SHALL BE IN ACCORDANCE WITH
ASTM C172 EXCEPT FOR ROUTINE SLUMP AND AIR-CONTENT TESTS
F) THE ENGINEER SHALL BE SPECIFICALLY NAMED ON THE
DISTRIBUTION LIST TO RECEIVE ORIGINAL CONCRETE
TESTING REPORTS FROM THE RESPECTIVE FIRM OR COMPANY
PROVIDING TESTING AND CERTIFIED RESULTS.
GENERAL CONCRETE NOTES CONTINUED
50. BEFORE ANY CONCRETE IS PLACED, ALL ICE, SNOW AND FROST
SHALL BE COMPLETELY REMOVED FROM ALL SURFACES TO BE IN
CONTACT WITH THE NEW CONCRETE AND THE TEMPERATURE OF
THESE SURFACES SHALL BE RAISED TO AS CLOSE AS MAY BE
PRACTICAL TO THE TEMPERATURE OF THE NEW CONCRETE THAT IS
TO BE PLACED THEREON. NO CONCRETE SHALL BE PLACED ON A
FROZEN SUB GRADE OR ON ONE THAT CONTAINS FROZEN
MATERIALS. CONCRETE SHALL NOT BE MIXED OR PLACED WHEN
DAILY MINIMUM ATMOSPHERIC TEMPERATURE IS LESS THAN FORTY
(40) DEGREES F., UNLESS FACILITIES ARE PROVIDED TO ENSURE THE
ADEQUATE PROTECTION OF THE CONCRETE.
TEMPERATURE OF THE CONCRETE AT THE TIME OF PLACEMENT
SHALL NOT BE LESS THAN FIFTY (50) DEGREES F. NOR MORE THAN
NINETY (90) DEGREES F. THE USE OF ACCELERATORS OR ANTIFREEZE
COMPOUNDS WILL NOT BE ALLOWED.
51. NO REPAIRS SHALL BE MADE UNTIL THE CONCRETE HAS BEEN
REVIEWED BY THE ENGINEER OR AUTHORIZED REPRESENTATIVE.
52. REPAIRS SHALL BE CATEGORIZED AND REPAIRED AS FOLLOWS:
A) SURFACE DEFECTS
REPAIR SURFACE DEFECTS THAT ARE SMALLER THAN ONE (1)
FOOT ACROSS IN ANY DIRECTION AND ARE LESS THAN ONE (1) INCH
IN DEPTH. REPAIR BY REMOVING THE HONEYCOMBED AND OTHER
DEFECTIVE CONCRETE DOWN TO SOUND CONCRETE, MAKE THE
EDGES PERPENDICULAR TO THE SURFACE AND AT LEAST
THREE-EIGHTHS (3/8) INCH DEEP, THOROUGHLY DAMPEN THE
SURFACE, WORK INTO THE SURFACE A BONDING GROUT (ONE PART
CEMENT TO ONE PART FINE SAND), FILL THE HOLE WITH
MORTAR, MATCH THE FINISH ON THE ADJACENT CONCRETE AND
CURE AS SPECIFIED.
B) SEVERE DEFECTS
REPAIR SEVERE DEFECTS THAT ARE LARGER THAN SURFACE
DEFECTS BUT DO NOT APPEAR TO AFFECT THE STRUCTURAL
INTEGRITY. REPAIR BY REMOVING THE HONEYCOMBED AND OTHER
DEFECTIVE CONCRETE DOWN TO SOUND CONCRETE, MAKE THE
EDGES OF THE HOLE PERPENDICULAR TO THE SURFACE, SANDBLAST
THE SURFACE, COAT THE SANDBLASTED SURFACE WITH EPOXY
BONDING COMPOUND, PLACE NON-SHRINK GROUT, MATCH THE FINISH
ON ADJACENT CONCRETE, AND CURE AS SPECIFIED.
C) MAJOR DEFECTS
IF THE DEFECTS ARE SERIOUS OR AFFECT THE STRUCTURAL
INTEGRITY OR IF PATCHING DOES NOT SATISFACTORILY RESTORE
THE QUALITY AND APPEARANCE TO THE SURFACE, THE ENGINEER
MAY REQUIRE THE CONCRETE TO BE REMOVED AND REPLACED,
COMPLETE, IN ACCORDANCE WITH THE PROVISIONS OF THIS
SECTION.
D) CRACKS
REPAIR CRACKS IN CONCRETE STRUCTURES THAT ARE WIDER THAN
ONE TENTH (1/10) OF AN INCH IN WIDTH BY CUTTING OUT A SQUARE
EDGED AND UNIFORMLY ALIGNED JOINT THREE EIGHTHS (3/8) INCH
WIDE BY THREE QUARTERS (¾) INCH DEEP, PREPARING EXPOSED
SURFACES OF THE JOINT, PRIMING THE JOINT, AND APPLYING
POLYURETHANE JOINT SEALANT. IF THE CRACKS ARE SERIOUS OR
AFFECT THE STRUCTURAL INTEGRITY OR FUNCTION OF THE ELEMENT,
THE ENGINEER MAY REQUIRE THE CONCRETE TO BE REMOVED AND
REPLACED, COMPLETE, IN ACCORDANCE WITH THE PROVISIONS OF
THIS SECTION.
GENERAL CONCRETE NOTES
15. CHAMFER EDGES OF PERMANENTLY EXPOSED CONCRETE SURFACES
WITH A 45° BEVEL (
" X
16. DRAWINGS ARE NOT TO BE SCALED FOR ESTIMATING OR ANY OTHER
PURPOSE.
17. ALL REINFORCEMENT BENDS AND LAPS, UNLESS OTHERWISE NOTED
SHALL PROVIDE A MINIMUM SPLICE OR LAP LENGTH OF 30 BAR
DIAMETERS. WHEN TWO DIFFERENT SIZED BARS ARE LAPPED THE
LARGER BAR DIAMETER SHALL GOVERN THE SPLICE OR LAP LENGTH.
18. SPLICES SHALL BE INSTALLED AS NEEDED TO ALLOW FOR MINIMUM
COVER REQUIREMENTS BETWEEN BARS AND ANY ADJACENT
CONCRETE FACE.
19. DIMENSIONS ARE TO THE CENTERLINE OF THE BAR UNLESS
OTHERWISE NOTED.
20. REINFORCEMENT PARALLELING ANY CONSTRUCTION JOINT SHALL
PROVIDE A MINIMUM OF 2" CLEAR COVER.
21. REINFORCEMENT AT SMALL OPENINGS (MAX 18" OPENING) IN WALLS
AND SLABS MAYBE SPREAD APART NOT MORE THAN 1.5 TIMES THE
BAR SPACING. ALL OPENINGS 12" OR LARGER SHALL INCORPORATE
AN ANNULAR RING OF REINFORCEMENT AROUND THE OPENING WITH
A MINIMUM OF 2" CLEARANCE FROM THE PENETRATION OPENING.
22. THE FIRST AND LAST BARS IN WALLS AND SLABS, STIRRUPS IN
BEAMS, AND TIES IN COLUMNS ARE TO START AND END AT A MINIMUM
OF ONE HALF OF THE ADJACENT BAR SPACING.
23. UNLESS OTHERWISE NOTED DOWELS INDICATED ON THE DRAWINGS
SUCH AS #5 (DWL) SHALL HAVE AN EMBEDMENT EQUAL TO THE
DEVELOPMENT LENGTH FOR TENSION REQUIRED BY ACI 318 AND A
PROJECTION EQUAL TO THAT REQUIRED FOR LAP SPLICING A BAR OF
THE SAME DIAMETER.
24. TWO PART EPOXY DOWELS SHALL BE HILTI HIT-RE 500 V3 OR
APPROVED EQUAL.
25. AT LOCATIONS WHERE NEW CONCRETE IS PLACED AGAINST EXISTING
CONCRETE, EXISTING SURFACES SHALL BE CLEAN, FREE OF LOOSE
CONCRETE AND ROUGHENED TO A
" AMPLITUDE UNLESS OTHERWISE
NOTED.
26. DOWELS SHALL BE WIRED OR OTHERWISE HELD IN POSITION.
DOWELS SHALL NOT BE SHOVED INTO FRESH CONCRETE.
27. THE CONTRACTOR SHALL PROVIDE NOTICE TO THE ENGINEER A
MINIMUM OF 48 HOURS IN ADVANCE OF ANY CONCRETE PLACEMENT.
28. CONCRETE TESTING FOR ANY CONCRETE DELIVERED TO THE SITE
SHALL BE PROVIDED TO THE ENGINEER BY THE CONTRACTOR.
29. ALL FOUNDATION SURFACES SHALL BE INSPECTED BY A THE DESIGN
ENGINEER OR AN INDEPENDENT SOILS ENGINEER PRIOR TO
PLACEMENT OF ANY REINFORCEMENT STEEL OR FORM WORKS.
CONTRACTOR SHALL PROVIDE A MINIMUM OF 48 HOURS NOTICE TO
THE ENGINEER.
30. CONSTRUCTION SHORING AND BRACING OF FORM WORK SHALL BE IN
ACCORDANCE WITH ACI 301 "SPECIFICATIONS FOR STRUCTURAL
CONCRETE" AND ACI 347R "GUIDE TO FORM WORK FOR CONCRETE".
31. THE STRUCTURES SHOWN ON THE DRAWINGS HAVE BEEN
DESIGNED FOR STABILITY UNDER FINAL CONDITIONS
ONLY. THESE PLANS DO NOT INCLUDE THE NECESSARY
COMPONENTS FOR EQUIPMENT OR EQUIPMENT FOR THE
STRUCTURES DURING CONSTRUCTION. THE CONTRACTOR IS
RESPONSIBLE FOR ALL WORK RELATING TO CONSTRUCTION
ERECTION METHODS. BRACING, SHORING, RIGGING, GUYS,
SCAFFOLDING, FORM WORK, AND OTHER WORK AIDS
REQUIRED TO SAFELY PERFORM THE WORK SHOWN.
32. EXCAVATIONS SHALL BE SHORED AS REQUIRED TO PREVENT
SUBSIDENCE OR DAMAGE TO ADJACENT EXISTING
STRUCTURES, UTILITIES ORE OTHER EXISTING
INFRASTRUCTURE.
33. THE CONTRACTOR SHALL SUBMIT SHOP DRAWINGS FOR
CONCRETE REINFORCEMENT, GATE STEEL AND/OR
MISCELLANEOUS STEEL PRIOR TO FABRICATION.
34. CONCRETE SHALL BE AT LEAST FOUR-THOUSAND (4000) PSI
COMPRESSIVE STRENGTH AT TWENTY-EIGHT (28) DAYS, WHEN
TESTED IN ACCORDANCE WITH ASTM C39 AND MIX DESIGN
SHALL BE IN ACCORDANCE WITH ASTM C94 AND/OR THIS
SPECIFICATION WHICHEVER IS MORE STRINGENT.
35. READY-MIX CONCRETE SUPPLIERS CAN PRE-CERTIFY THEIR
CONCRETE MIX. WHEN A PRE-CERTIFIED MIX IS USED THE MIX
NUMBER WILL BE SHOWN ON THE CONCRETE DELIVERY
TICKET. NON-CERTIFIED READY-MIX SUPPLIERS SHALL
FURNISH DESIGN AND CONCRETE CYLINDER TEST BREAK DATA
FOR APPROVAL BY THE ENGINEER PRIOR TO PLACEMENT.
36. CONCRETE MIX DESIGN SHALL INCLUDE NOT LESS THAN SIX (6)
SACKS CEMENT PER CUBIC YARD OF CONCRETE, EXCEPT FLY
ASH MAY BE USED AS SUBSTITUTION FOR UP TO TWENTY (20)
PERCENT OF THE PORTLAND CEMENT. FLY ASH SHALL
CONFORM TO REQUIREMENTS OF ASTM C618 AS APPLICABLE.
37. CEMENT SHALL BE TYPE II OR IIA LOW ALKALI PORTLAND
CEMENT CLASS C OR F.
38. COARSE AGGREGATE SHALL BE MAXIMUM SIZE OF ONE (1.0)
INCH PER DESIGNATIONS OF ASTM C33
39. AIR ENTRAINMENT SHALL CONFORM TO ASTM C260. THE AIR
ENTRAINMENT SHALL BE FIVE (5) TO SEVEN (7) PERCENT.
40. SLUMP SHALL BE IN THE RANGE OF THREE (3) INCHES PLUS OR
MINUS ONE (1) INCH; UNLESS CYLINDER TEST BREAK DATA IS
SUBMITTED SHOWING THAT COMPRESSIVE STRENGTH IS
ACHIEVED WITH THE HIGHER SLUMP.
GENERAL CONCRETE NOTES CONTINUED
GENERAL NOTES
GENERAL CONCRETE
NOTES
CHECKED BY:
DATE:
EQUINOX PROJECT:
CONTRACT #:
SMC
WEC
07/09/2026
PELICAN HAVEN
WETLANDS
RESTORATION
PROJECT OWNER:
MARK DATE DESCRIPTION
PROJECT IDENTIFICATION:
PROJECT SPONSOR:
BINDING
ORDER
SHEET IDENTIFIER:
PREPARER:
PROFESSIONAL SEAL:
ENGINEERING
EQUINOX
www.equinoxengineering.us
SHEET TITLE:
STATE OF UTAH
DIVISION OF
NATURAL
RESOURCES
STATE OF UTAH
DEPARTMENT OF
NATURAL
RESOURCES
515 EAST
5300 SOUTH
OGDEN, UTAH
84405
UT-139-01
266113
S-100
THE ENGINEER PREPARING THESE PLANS WILL NOT BE RESPONSIBLE AND/OR LIABLE
FOR UNAUTHORIZED CHANGES TO OR USES OF THESE PLANS. ALL CHANGES MUST
BE IN WRITING AND MUST BE APPROVED BY THE PREPARER OF THESE PLANS.
THE ENGINEER PREPARING THESE PLANS WILL NOT BE RESPONSIBLE AND/OR LIABLE
FOR UNAUTHORIZED CHANGES TO OR USES OF THESE PLANS. ALL CHANGES MUST
BE IN WRITING AND MUST BE APPROVED BY THE PREPARER OF THESE PLANS.
ABBREVIATIONS / LEGEND
NOT ALL ABBREVIATIONS WILL APPLY TO THIS
PROJECT
AB ANCHOR BOLT
ADDL ADDITIONAL
AL ALUMINUM
APPROX APPROXIMATE
B BOTTOM
BTWN BETWEEN
CL CENTERLINE
CJ CONSTRUCTION JOINT
CLR CLEAR
CONC CONCRETE
CONT CONTINUED / CONTINUOUS
CMP CORRUGATED METAL PIPE
CNTR CENTER
CP CONTROL POINT
DEMO DEMOLITION
DET DETAIL
DIA DIAMETER
DWG DRAWING
DWLS DOWELS
EA EACH
EF EACH FACE
EW EACH WAY
EL ELEVATION
EQ SP EQUAL SPACE / EQUALLY SPACED
EXIST EXISTING
EXP JNT EXPANSION JOINT
FL FLOWLINE
GAVL GALVANIZED
GR GRADE
HDPE HIGH DENSITY POLYETHYLENE PIPE
ID INSIDE DIAMETER
IE INVERT ELEVATION
JTS JOINTS
MAX MAXIMUM
MIN MINIMUM
NO. NUMBER
NTS NOT TO SCALE
OC ON CENTER
OD OUTSIDE DIAMETER
OPNG OPENING
PL PLATE
PROJ PROJECTION
PLCS PLACES
PS PIPE STEEL
PSI POUNDS PER SQUARE INCH
RAD RADIUS
RCP REINFORCED CONCRETE PIPE
REINF REINFORCEMENT
REQD REQUIRED
SB STEEL BENT
SCH SCHEDULE
SECT SECTION
SIM SIMILAR
SQ SQUARE
SR SUPPORT RING
SS STAINLESS STEEL
STA STATION
STD STANDARD
STL STEEL
SYM SYMMETRICAL
T TOP
T&B TOP AND BOTTOM
TH THICKNESS
THRD THREADED
TYP TYPICAL
VERT VERTICAL
WS WATERSTOP
WCS WATER CONTROL STRUCTURE
W/ WITH
GENERAL NOTES
1. CONTRACTOR SHALL BE RESPONSIBLE TO CONTACT BLUE STAKES
PRIOR TO ANY EXCAVATION WITH SUFFICIENT LEAD TIME AS REQUIRED
BY BLUE STAKES. BLUE STAKES UTAH 800.662.4111
2. UNLESS SPECIFICALLY STATED OTHERWISE IN THE PLANS,
SPECIFICATIONS AND/OR CONTRACT DOCUMENTS, THE CONTRACTOR
SHALL BE RESPONSIBLE TO OBTAIN ALL NECESSARY PERMITS FROM
ANY REGULATORY AGENCY THAT HAS JURISDICTION OVER THE
PROJECT SITE AS NEEDED TO COMMENCE CONSTRUCTION ACTIVITY.
ALL PERMITS SHALL BE APPROVED, ISSUED AND IN HAND A MINIMUM
OF 48 HOURS PRIOR TO THE START OF ANY CONSTRUCTION WORK.
3. THE CONTRACTOR SHALL NOT SCALE DRAWINGS FOR CONSTRUCTION
PURPOSES. ANY MISSING DIMENSIONS OR DISCREPANCIES IN THE
DRAWINGS OR PHYSICAL FEATURES SHALL BE BROUGHT TO THE
ATTENTION OF THE ENGINEER FOR RESOLUTION. IF THE CONTRACTOR
PROCEEDS PRIOR TO OBTAINING THE ENGINEERS RESOLUTION THE
CONTRACTOR DOES SO AT THEIR OWN RISK
4. OBSERVATIONS OF THE WORK IN PROGRESS AND ON-SITE VISITS BY
THE ENGINEER OR OWNER ARE NOT TO BE CONSTRUED AS
ACCEPTANCE OR WARRANTIES OF THE CONTRACTOR'S CONTRACTUAL
OBLIGATION.
5. CONSTRUCTION SAFETY IS THE SOLE RESPONSIBILITY OF THE
CONTRACTOR. THE ENGINEER IS NOT RESPONSIBLE FOR SAFETY IN
OR OR ABOUT HE PROJECT SITE, NOR FOR THE COMPLIANCE BY THE
APPROPRIATE PARTY WITH ANY REGULATIONS RELATING THERETO.
6. THE CONTRACTOR SHALL MAINTAIN A SET OF THE CONSTRUCTION
DRAWINGS AND SPECIFICATIONS ON SITE AT ALL TIMES. ONE SET OF
THE CONSTRUCTION DRAWINGS SHALL BE MAINTAINED SOLELY TO
DOCUMENT ANY CHANGES IN THE WORK AS A RESULT OF CHANGE
ORDERS OR FIELD CONDITIONS THAT MAY REQUIRE ALTERNATIVE
CONSTRUCTION DETAILS. ALL SUCH CHANGES SHALL BE MARKED ON
THE RECORD SET OF DRAWINGS IN PERMANENT INK.
7. THE ENGINEER MAY PROVIDE QUANTITIES AND/OR SURVEY DATA FOR
USE BY THE CONTRACTOR. INFORMATION PROVIDED BY THE
ENGINEER IN GOOD FAITH IS ASSUMED TO BE ACCURATE, HOWEVER
THE CONTRACTOR IS RESPONSIBLE FOR VERIFICATION OF QUANTITIES
AS REPORTED ON THE UNIT PRICE BID TABULATION AND SHALL BE
RESPONSIBLE TO LAYOUT AND CONSTRUCT THE WORK TO MEET THE
INTENT OF THE DESIGN.
8. ALL MATERIALS AND WORKMANSHIP SHALL CONFORM TO THE MOST
CURRENT INTERNATIONAL BUILDING CODE (I.B.C.) AS AMENDED BY
THE STATE IN WHICH THE PROJECT IS LOCATED AND LOCAL AGENCIES
AS NEEDED AND AS APPROPRIATE FOR THE PROJECT WORKS.
9. THE STRUCTURES SHOWN ON THE DRAWINGS HAVE BEEN DESIGNED
FOR STABILITY UNDER FINAL CONDITIONS ONLY. THESE PLANS DO
NOT INCLUDE THE NECESSARY COMPONENTS FOR EQUIPMENT OR
EQUIPMENT FOR THE STRUCTURES DURING CONSTRUCTION. THE
CONTRACTOR IS RESPONSIBLE FOR ALL WORK RELATING TO
CONSTRUCTION ERECTION METHODS. BRACING, SHORING, RIGGING,
GUYS, SCAFFOLDING, FORM WORK, AND OTHER WORK AIDS REQUIRED
TO SAFELY PERFORM THE WORK SHOWN.
10. EXCAVATIONS SHALL BE SHORED AS REQUIRED TO PREVENT
SUBSIDENCE OR DAMAGE TO ADJACENT EXISTING STRUCTURES,
UTILITIES OR OTHER EXISTING INFRASTRUCTURE.
GENERAL EARTHWORK/GRADING NOTES CONTINUED
10. CONTINUED - EQUIPMENT SHALL BE CUT OR REDUCED IN SIZE SUCH
THAT THEY MAY BE CHIPPED ON SITE. INVASIVE TREES AND INVASIVE
WOODY MATERIAL THAT CONTAINS SEEDS SHALL BE REMOVED FROM
THE SITE UNLESS SPECIFICALLY DIRECTED BY THE OWNER,
ENGINEER, OR THE OWNERS DESIGNATED REPRESENTATIVE.
11. AS AN ALTERNATIVE TO CHIPPING AND ONLY AS DIRECTED BY THE
OWNER, THE ENGINEER OR THE OWNERS REPRESENTATIVE, NATIVE
TREE SPECIES AND NATIVE WOODY SPECIES MATERIAL MAY ALSO BE
PLACED INTO SMALL PILES NOT TO EXCEED 15 FEET IN DIAMETER AT
THE BASE AND 6 FEET IN HEIGHT TO SERVE AS HABITAT STRUCTURES
AT SELECT LOCATIONS TO BE DETERMINED ON SITE AS
APPROPRIATE. THIS ALTERNATIVE DOES NOT APPLY TO INVASIVE
SPECIES.
12. THE CONTRACTOR SHALL STOP WORK AND CALL FOR INSPECTION AT
THE FOLLOWING POINTS OF CONSTRUCTION:
A) UPON DISCOVERY OF MAJOR CHANGES IN SOIL COMPOSITION DURING
BORROW AND EXCAVATION OPERATIONS
B) AFTER REACHING FINAL GRADE ON ALL EXCAVATION LOCATIONS
INCLUDING BUT NOT LIMITED TO SOIL LIFTS, DIKES, LEVEES, AND
EMBANKMENT GRADING.
C) BEFORE FILL IS PLACED OVER NEWLY INSTALLED PIPE OR
ANTI-SEEPAGE COLLARS (IF REQUIRED).
D) AS NEEDED TO PROVIDE DOCUMENTATION FOR COMPACTION.
13. COMPACTED FILL SHALL BE MINED FROM BORROW AREAS ON SITE
WITHIN AN APPROVED BORROW AREA. COMPACTED FILL SHALL BE
FREE OF ORGANIC MATERIAL (> 95% ORGANICS) AND LARGE ROCKS
OVER FOUR (4) INCH IN DIAMETER AND SHALL CONSIST OF NATIVE
SOILS. BORROW MATERIAL TO BE USED AS COMPACTED FILL SHALL
BE SUITABLE FOR USE AS COMPACTED FILL AND SHALL NOT BE
SAND, FLOUR LIKE MATERIAL, OVERLY SATURATED OR MATERIAL
THAT EXHIBITS A SOUPY LIKE CONSISTENCY. ANY BORROW
MATERIAL MINED ON SITE IS SUBJECT TO REJECTION BY THE
ENGINEER UPON INSPECTION WHEN MATERIAL IS EXPOSED AND/OR
UNCOVERED IF THE MATERIAL DOES NOT MEET THE MINIMUM
CRITERIA TO BE SUITABLE FOR USE AS COMPACTED FILL.
14. NON COMPACTED FILL SHALL BE MINED FROM BORROW AREAS ON
SITE WITHIN AN APPROVED BORROW AREA. NON COMPACTED FILL
SHALL BE ANY MATERIAL THAT IS NOT SUITABLE FOR USE AS
COMPACTED FILL (SAND, FLOUR LIKE MATERIAL, OVERLY SATURATED
OR MATERIAL THAT EXHIBITS A SOUPY LIKE CONSISTENCY). NON
COMPACTED FILL MATERIAL MAY CONTAIN A HIGH OR SIGNIFICANT
AMOUNT OF ORGANICS WITH THE INTENT TO PROVIDE A ROBUST
SEED BANK TO PROMOTE VEGETATION GROWTH. GRUBBINGS
REMOVED BORROW AREAS OR ANY AREA REQUIRED TO BE CLEARED,
GRUBBED OR STRIPPED MAY BE USED AS NON-COMPACTED FILL
MATERIAL.
15. BORROW AREAS SHALL BE MAINTAINED DURING CONSTRUCTION IN A
GRADED CONDITION SUCH THAT DRAINAGE IS ASSURED AND THAT
OPERATIONS CAN RESUME QUICKLY AFTER PRECIPITATION PERIODS.
FOLLOWING COMPLETION OF THE WORK, BORROW AREAS ARE TO BE
LEFT IN A GRADED CONDITION ACCEPTABLE TO THE ENGINEER AND
ALL HAUL ROADS, ACCESS ROADS, AND TEMPORARY CROSSINGS
ARE TO BE REMOVED. MATERIAL MAY DIFFER FROM LOCATION TO
LOCATION WITH RESPECT TO SUITABILITY OF USE. THE
CONTRACTOR SHOULD BE READY TO BORROW AND TRANSPORT
MATERIAL FROM ANY LOCATION WITHIN THE PROJECT SITE THAT
WILL BE USED AS A BORROW AREA.
UNLESS APPROVED BY THE ENGINEER OR OTHERWISE SPECIFIED,
BORROW OF LEVEE, DIKE OR BERM MATERIAL MUST BE MORE THAN
ONE HUNDRED (100) LINEAR FEET FROM THE FILL LOCATION IN ANY
DIRECTION. THE INTENT OF THIS DIRECTION IS TO ALLEVIATE THE
“MOAT” CONFIGURATION NEXT TO A LEVEE, DIKE OR BERM.
UNLESS SPECIFICALLY DESIGNATED ON THE PLANS OR APPROVED
BY THE ENGINEER, NO BORROW MATERIAL MAY BE TAKEN FROM ANY
AREA THAT WILL BE HIGHER IN ELEVATION THAN ONE (1) FOOT
BELOW THAT OF THE TOP OF THE LEVEE, DIKE OR BERM OR SOIL LIFT.
THE INTENT OF THIS DIRECTION IS TO ALLEVIATE ANY DISTURBED OR
SCARED AREAS THAT ARE ABOVE THE FULL POOL FLOOD ELEVATION.
16. ALL LEVEE, DIKE AND EMBANKMENT FILLS SHALL BE FREE OF
ORGANIC MATERIAL AND LARGE ROCKS OVER FOUR (4) INCH IN
DIAMETER AND SHALL CONSIST OF NATIVE SOILS. UNLESS
OTHERWISE SPECIFIED, ALL MATERIAL SHALL BE PLACED IN LOOSE
LIFTS NOT TO EXCEED EIGHT (8) INCHES IN THICKNESS AND SHALL BE
COMPACTED BY SUITABLE COMPACTION EQUIPMENT TO COMPLY
WITH THE SPECIFIED COMPACTION REQUIREMENTS AS OUTLINED
FOR THE RESPECTIVE AREAS OR LOCATION OF FILL. MAXIMUM
DENSITY SHALL BE AS DETERMINED BY THE STANDARD PROCTOR
METHOD ASTM D698.
17. THE CONTRACTOR SHALL PROVIDE LABOR AND EQUIPMENT. TO
ENSURE THAT SOIL MOISTURE IS WITHIN TWO (2) PERCENT OPTIMUM
MOISTURE. SHAPING OF THE LEVEE, DIKE OR EMBANKMENT SHALL
BREAK UP LUMPS AND CLODS AND YIELD A SMOOTH SURFACE AND
OBTAIN A FINISH TO THE LINES AND GRADES SHOWN ON THE
DRAWING. LEVEE TOPS SHALL BE DRIVABLE BY MAINTENANCE
VEHICLES.
18. LEVEE, DIKE, BERM OR EMBANKMENT MATERIAL EXCAVATED FROM
DITCHES/BORROWS WITH TRACTOR-SCRAPER UNITS SHALL BE
PLACED IN SUCCESSIVE LAYERS ACROSS THE ENTIRE WIDTH OF THE
LEVEE, DIKE OR EMBANKMENT. EACH LAYER MUST BE SPREAD AS
DEPOSITED LONGITUDINALLY ALONG THE LEVEE, DIKE OR
EMBANKMENT WITH EACH LAYER NOT EXCEEDING EIGHT (8) INCHES
IN THICKNESS. THE INITIAL LIFT SHALL BE PLACED ON UNDISTURBED
SOIL AFTER STRIPPING IS COMPLETED. WITH THE ENGINEERS
APPROVAL THE INITIAL LAYER MAY BE INCREASED IN THICKNESS IN
WET AREAS TO PROVIDE A WORKING PAD CAPABLE OF SUPPORTING
THE HAULING EQUIPMENT. THE LEVEE, DIKE OR EMBANKMENT AT
ALL TIMES MUST BE MAINTAINED IN A REASONABLE LEVEL
18. - CONTINUED - CONDITION AND HAULING EQUIPMENT SHALL BE
DIRECTED OVER THE FULL WIDTH OF EACH LAYER TO FACILITATE
UNIFORM COMPACTION.
19. LEVEE, DIKE OR EMBANKMENT MATERIAL EXCAVATED WITH BUCKET
EQUIPMENT SHALL BE DEPOSITED INTO THE LEVEE, DIKE OR
EMBANKMENT WITHIN REACH OF THE EQUIPMENT OR HAULED
DIRECTLY TO THE LEVEE, DIKE OR EMBANKMENT SITE. TO PREVENT
LEVEE, DIKE OR EMBANKMENT FAILURE, STOCK PILING ON LEVEES,
DIKES, EMBANKMENT OR BERMS WILL NOT BE PERMITTED.
MATERIALS SHALL BE PLACED AND SPREAD IN LAYERS WITH EACH
LAYER AFTER SPREADING NOT TO EXCEED EIGHT (8) INCHES IN
THICKNESS.
20. ALL LEVEE, DIKE OR EMBANKMENT CONSTRUCTION MUST BE AS
CONTINUOUS AS POSSIBLE AND THE FILL MAINTAINED SUCH THAT
DRAINAGE IS ASSURED AT ALL TIMES.
21. HAND COMPACTORS SHALL BE USED WHEN COMPACTING ANY FILL
MATERIAL WITHIN TWO (2) FEET OF ANY WATER CONTROL
STRUCTURE OR PIPE.
22. THE INTERSECTION BETWEEN EMBANKMENTS SHALL BE
CONSTRUCTED WITH A MINIMUM RADIUS OF SIXTEEN (16) FEET.
23. WHEN TRENCHING THE CONTRACTOR WILL BE REQUIRED TO
EXCAVATE TO THE LINES AND GRADES SHOWN ON THE PLANS. ALL
PIPE SHALL BE INSTALLED WITH A MINIMUM COVER AS SHOWN ON
THE PLANS. THE LENGTH OF TRENCH EXCAVATION IN ADVANCE OF
THE PIPE LAYING SHALL BE KEPT TO A MINIMUM AND SHALL NOT
EXCEED ONE-HUNDRED FIFTY (150) FEET, UNLESS AUTHORIZED BY
THE ENGINEER. TRENCHES SHALL BE OF SUFFICIENT WIDTH IN THE
PIPE ZONE TO PERMIT THE PROPER INSTALLATION AND BEDDING,
AND TO PROVIDE PROPER COMPACTION OF BACKFILL OF MATERIALS.
THE CONTRACTOR SHALL NOT OVER EXCAVATE BY DIGGING BELOW
SPECIFIED LINES AND GRADES. IF, IN THE OPINION OF THE ENGINEER,
THE CONTRACTOR OVER EXCAVATES MATERIAL IN AN AREA, HE
SHALL REPLACE AT HIS EXPENSE THE OVER EXCAVATED MATERIAL
WITH SUITABLE SITE MATERIAL AND COMPACT THAT MATERIAL TO A
DENSITY EQUAL TO THE SURROUNDING IN-SITU MATERIAL.
24. PLACEMENT OF BEDDING SHALL PRECEDE THE INSTALLATION OF
PIPE. BEDDING SHALL PROVIDE UNIFORM SUPPORT ALONG THE
ENTIRE LENGTH OF THE PIPE BARREL, WITHOUT LOAD
CONCENTRATION AT JOINTS, FITTINGS, ETC. ALL ADJUSTMENTS TO
THE LINE AND GRADE SHALL BE MADE BY SCRAPING OR FILLING WITH
BEDDING MATERIAL UNDER THE PIPE, AND NOT BY BLOCKING OR
WEDGING. BEDDING SHALL BE PLACED IN UNIFORM LOOSE LAYERS
OF NOT MORE THAN EIGHT (8) INCHES IN DEPTH, AND COMPACTED TO
NINETY (90) PERCENT MAXIMUM DENSITY AS DETERMINED BY THE
STANDARD PROCTOR METHOD ASTM D698. MATERIAL SHALL BE
COMPACTED ALONG THE SIDES OF PIPE TO THE DEPTH SHOWN ON
THE PLAN, AND WORKED CAREFULLY UNDER THE PIPE HAUNCHES.
25. THE CONTRACTOR SHALL FURNISH, INSTALL AND OPERATE ALL
NECESSARY EQUIPMENT TO KEEP THE EXCAVATIONS ABOVE THE
FOUNDATION (SUB GRADE) LEVEL FREE FROM WATER DURING
CONSTRUCTION, AND SHALL DEWATER AND DISPOSE OF THE WATER
SO AS NOT TO CAUSE INJURY TO PUBLIC OR PRIVATE PROPERTY OR
NUISANCE TO PUBLIC. DEWATERING EQUIPMENT SHALL BE IN GOOD
WORKING CONDITION AND SHALL BE AVAILABLE THROUGHOUT THE
CONSTRUCTION. THE CONTRACTOR SHALL ALSO PROVIDE
COMPETENT WORKERS FOR THE OPERATION AND MAINTENANCE OF
THE PUMPING EQUIPMENT.
26. COMPACTION WILL BE EVALUATED USING VISUAL INSPECTION AND
TESTING WILL BE PERFORMED BY THE ENGINEER OR AN AUTHORIZED
REPRESENTATIVE, ON THE WORK AT THE ENGINEERS DISCRETION.
SOIL AND FILL COMPACTION TESTING WILL BE CONDUCTED IN
ACCORDANCE WITH ASTM D2922/D3017, AND MAXIMUM DENSITY WILL
BE DETERMINED BY THE STANDARD PROCTOR METHOD ASTM D698,
FOR ALL COMPACTED FILL MATERIAL IN ANY NON-LINEAR
VOLUMETRIC PLACEMENT, DIKES OR LEVEES, SELECT FILL MATERIAL
UNDER ANY STRUCTURE, SELECT FILL MATERIAL BEDDING FOR ANY
PIPE OR ANY OTHER AREA REQUIRING COMPACTION.
27. COMPACTION TESTING SHALL BE ASCERTAINED AND CERTIFIED,
UNLESS SPECIFICALLY NOTED AS DIFFERENT ON RESPECTIVE DETAIL,
TO A MINIMUM LEVEL OF NINETY (90) PERCENT MAXIMUM DENSITY AS
DETERMINED BY THE STANDARD PROCTOR METHOD ASTM D698.
28. THE CONTRACTOR SHALL DEMONSTRATE TO THE ENGINEERS
SATISFACTION THAT THE COMPACTION DENSITY HAS BEEN
ACHIEVED. IF THE COMPACTION IS NOT ACHIEVED OR THE
CONTRACTOR CANNOT DEMONSTRATE THAT THE MEANS AND
METHODS BEING UTILIZED ARE SUFFICIENT TO MEET THE
SPECIFICATION THEN THE ENGINEER MAY REQUIRE ADDITIONAL
TESTING AT AN INTERVAL TO BE DETERMINED AS SITE CONDITIONS
WARRANT OR AS REQUIRED BY THE ENGINEER, AT THE
CONTRACTORS' EXPENSE. THE ENGINEER MAY EMPLOY OR REQUIRE
THE CONTRACTOR TO UTILIZE THE SERVICES OF AN INDEPENDENT
THIRD-PARTY FIRM OR INDIVIDUAL TO PROVIDE CERTIFIED
VERIFICATION OF SOIL COMPACTION. THE INDIVIDUAL OR FIRM
SHALL BE LICENSED AND APPROPRIATELY REGISTERED WITH THE
STATE IN WHICH THE PROJECT IS LOCATED.
29. WHEN THE CONTRACTOR HAS REACHED A POINT IN CONSTRUCTION
WHERE INSPECTION IS REQUIRED TO PROCEED (BASED ON THESE
SPECIFICATIONS OR VERBAL INSTRUCTIONS FROM THE ENGINEER),
CONTRACTOR SHALL PROVIDE A MINIMUM OF FORTY-EIGHT (48)
HOURS NOTICE TO THE ENGINEER BEFORE DEMOBILIZING EQUIPMENT
THAT MAY BE NECESSARY TO ADJUST OR MODIFY THE WORK IN
QUESTION. THE ENGINEER WILL MAKE EVERY EFFORT TO PROVIDE
INSPECTION ON SHORTER NOTICES.
30. NO COMPACTION TESTING SHALL TAKE PLACE WITHOUT APPROVAL
OR THE PRESENCE OF THE ENGINEER OR HIS REPRESENTATIVE. THE
ENGINEER OR HIS REPRESENTATIVE RESERVES THE RIGHT TO
CHOOSE THE LOCATIONS OR SITE OF INDIVIDUAL TESTS.
4. CONTINUED - MATERIALS FROM ANY BORROW SITE OR EXCAVATION
REGARDLESS OF THE DEPTH OF MATERIAL ENCOUNTERED TO THE
SATISFACTION OF THE ENGINEER BEFORE USING THAT MATERIAL FOR
COMPACTED FILL. ADDITIONALLY, STRIPPING SHALL BE DONE TO
REMOVE SOIL UNSUITABLE FOR LEVEE, DIKE OR EMBANKMENT
CONSTRUCTION. UNSUITABLE MATERIAL MAY CONSIST OF
FLOUR-LIKE SAND OR OTHER HIGHLY ERODIBLE SOILS. STRIPPING
SHALL BE DONE BELOW EACH LEVEE, DIKE OR EMBANKMENT
FOOTPRINT AS NECESSARY, AND AS REQUIRED IN ALL BORROW
AREAS THAT WILL SUBSEQUENTLY BE USED FOR MATERIAL
EXCAVATION. THE INTENT OF STRIPPING IS TO ELIMINATE ORGANIC
MATERIALS AND UNSUITABLE SOILS FROM BORROW MATERIALS FOR
SUBSEQUENT LEVEE, DIKE OR EMBANKMENT FILL.
ALL STRIPPED OR GRUBBED MATERIALS SUITABLE AS TOPSOIL OR
USE AS NON-COMPACTED FILL SHALL BE FIRST STOCKPILED AND
RESERVED FOR PLACEMENT OVER DISTURBED AREAS WITH THE
INTENT TO PROMOTE NATIVE PLANT REGENERATION FROM THE SEED
BANK. STRIPPED AND STOCKPILED MATERIAL SHALL BE USED FOR
SLOPE TOE PROTECTION MATERIAL, FETCH INTERCEPT BERMS OR
GRUBBING ISLANDS IN THAT ORDER. IF EXCESS Stripped OR
GRUBBED MATERIAL REMAINS UNUSED AFTER ALL NON-COMPACTED
FILL COMPONENTS OF THE PROJECT HAVE BEEN COMPLETED THEN
THE REMAINING STRIPPED MATERIAL MAY BE RE-SPREAD IN FOUR TO
SIX (4-6) INCH LIFTS AS DIRECTED BY THE ENGINEER.
STRIPPING MATERIALS FROM LEVEE, DIKE OR EMBANKMENT
FOOTPRINTS MAY BE STOCKPILED ALONG SIDE THE LEVEE, DIKE OR
EMBANKMENT PROVIDED THAT SUFFICIENT SPACE IS AVAILABLE TO
PREVENT ACCIDENTAL INCORPORATION OF THE MATERIALS INTO
COMPACTED FILL DURING TRIM WORK ON THE LEVEE, DIKE OR
EMBANKMENT SIDE SLOPES. PLACEMENT OF STRIPPED MATERIAL
SHALL BE AS DIRECTED BY THE ENGINEER. THE CONTRACTOR SHALL
COORDINATE STOCKPILES AND RE-SPREADING ACTIVITIES ON THE
PROJECT SITE AS DIRECTED BY THE ENGINEER.
5. STRIPPING TO A DEPTH OF SIX (6) INCHES IS ASSUMED FOR
ESTIMATES AND AS THE PAY QUANTITY REGARDLESS OF THE DEPTH
OF MATERIAL ACTUALLY STRIPPED
6. THE CONTRACTOR SHALL COMPLY WITH ALL REGULATORY
REQUIREMENTS FOR DUST CONTROL ON THE PROJECT SITE.
7. THE CONTRACTOR SHALL STOP WORK AND CALL FOR INSPECTION AT
THE FOLLOWING POINTS OF CONSTRUCTION:
A) UPON DISCOVERY OF MAJOR CHANGES IN SOIL COMPOSITION DURING
BORROW AND EXCAVATION OPERATIONS
B) AFTER REACHING FINAL GRADE ON ALL EXCAVATION LOCATIONS
INCLUDING BUT NOT LIMITED TO SOIL LIFTS, DIKES, LEVEES AND
EMBANKMENT GRADING.
C) BEFORE FILL IS PLACED OVER NEWLY INSTALLED PIPE OR
ANTI-SEEPAGE COLLARS (IF REQUIRED).
D) AS NEEDED TO PROVIDE DOCUMENTATION FOR COMPACTION.
8. DEMOLITION CONSISTS OF REMOVAL OR NON-NATIVE MATERIALS
SUCH AS EXISTING CULVERTS AND ANY OTHER STRUCTURES FOUND
ON THE JOBSITE AS SHOWN ON THE PLANS OR AS DIRECTED IN THE
FIELD. DEMOLITION MAY INCLUDE THE REMOVAL OF CULVERT PIPE,
STEEL PIPE, CONCRETE ITEMS, WATER CONTROL GATES, OLD
AUTOMOBILES, DISCARDED APPLIANCES, TRASH OR OTHER MAN
MADE MATERIALS FOUND DURING CONSTRUCTION AND NOT
NECESSARILY SHOWN ON THE PLANS. THE CONTRACTOR MAY BE
ELIGIBLE FOR ADDITIONAL COMPENSATION FOR DEMOLITION ONLY IF
THE MATERIALS DISCOVERED ARE LARGER THAN FORTY-EIGHT (48)
INCHES IN DIAMETER AND/OR ARE LARGER THAN SIXTY (60) FEET IN
LENGTH AND CANNOT BE BROKEN INTO SMALLER PIECES WITH
EQUIPMENT EQUIVALENT TO A BACKHOE. ALL MATERIALS REMOVED
SHALL BECOME THE PROPERTY OF THE CONTRACTOR AND BE
REMOVED FROM THE SITE UNLESS OTHERWISE SPECIFIED BY THE
ENGINEER. CONCRETE AND BRICK STRUCTURES MAY BE BROKEN UP
AND USED FOR RIP RAP, UPON APPROVAL BY THE ENGINEER.
9. DEMOLITION OF NATIVE SPECIES WOODY MATERIALS INCLUDING
REMOVAL OF TREES AND STUMPS AND ANY WOODY VEGETATION
ASSOCIATED WITH CLEARING THE SITE TO RECEIVE SOIL LIFTS. THE
TREES AND WOODY MATERIAL SHALL BE MECHANICALLY CHIPPED OR
GROUND ON SITE AND THE REMAINS SPREAD EVENLY OVER THE
AREA. IF THE WORK REQUIRES SEEDING, THEN THE CHIPPINGS SHALL
BE SPREAD LOOSELY OVER THE SEEDED AREA AS MULCH TO A DEPTH
OF NO MORE THAN 1 INCH, OR SPREAD EVENLY IN OPEN AREAS TO
FACILITATE THE RETENTION OF CARBON IN THE PROJECT SITE.
TREES AND WOODY MATERIAL THAT ARE TOO LARGE TO BE CHIPPED
BY MECHANICAL EQUIPMENT SHALL BE CUT OR REDUCED IN SIZE
SUCH THAT THEY MAY BE CHIPPED ON SITE. NATIVE TREE SPECIES
AND NATIVE SPECIES WOODY MATERIAL ARE NOT TO BE
REMOVED FROM THE SIT UNLESS SPECIFICALLY DIRECTED BY THE
OWNER, ENGINEER, OR THE OWNERS DESIGNATED REPRESENTATIVE.
THE INTENT OF THIS SPECIFICATION IS TO ALLOW FOR ORGANIC
MATERIAL TO REMAIN ON SITE.
10. DEMOLITION OF TREES IDENTIFIED BY THE OWNER, ENGINEER OR THE
OWNERS REPRESENTATIVE AS INVASIVE SPECIES, INCLUDING BUT
NOT LIMITED TO RUSSIAN OLIVE OR SIBERIAN ELM SHALL BE
REMOVED IN WHOLE OR IN PART AS PART OF THE DEMOLITION
PROCESS. TREES WILL BE COMPLETELY REMOVED FROM THE
GROUND INCLUDING THE STUMP. WOODY MATERIAL NOT CONTAINING
SEEDS MAY BE REQUIRED TO BE MECHANICALLY CHIPPED ON SITE,
AND THE REMAINS SPREAD EVENLY OVER THE AREA TO RECEIVE
SEEDING AS MULCH TO A DEPTH OF NO MORE THAN 1 INCH, OR
SPREAD EVENLY IN OPEN AREAS TO FACILITATE THE RETENTION OF
CARBON IN THE PROJECT SITE. INVASIVE TREES AND WOODY
MATERIAL THAT ARE TOO LARGE TO BE CHIPPED BY MECHANICAL
GENERAL EARTHWORK/GRADING NOTES CONTINUED
1. THE CONTRACTOR SHALL MINIMIZE DISTURBANCE OUTSIDE THE
CONSTRUCTION LIMITS, AND NOT UNNECESSARILY DISTURB LANDS ON
OR ADJACENT TO THE SITE. DAMAGE TO ANY EXISTING EQUIPMENT OR
STRUCTURES DUE TO THE CONTRACTORS WORK OR ACTIVITIES SHALL
BE REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR
TO THE OWNERS SATISFACTION. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR IDENTIFICATION AND PROTECTION OF ALL UTILITIES
THAT MAY BE AFFECTED BY THE WORK. THE CONTRACTOR SHALL NOT
BE ENTITLED TO ADDITIONAL COMPENSATION FOR PROTECTION OR
AVOIDANCE OF UTILITIES DISCOVERED IN THE COURSE OF THE WORK
UNLESS THE UTILITIES REQUIRE A SUBSTANTIAL REDESIGN OF
IMPROVEMENTS.
2. A PORTION OR ALL OF THE WORK DESCRIBED WITHIN OR OTHERWISE
ASSOCIATED WITH THIS PROJECT MAY BE CONSTRUCTED UNDER
SATURATED CONDITIONS AND THE CONTRACTOR WILL BE
RESPONSIBLE TO DEWATER AS NEEDED TO FACILITATE THE REQUIRED
CONSTRUCTION COMPONENTS. BY SUBMISSION OF A BID THE
CONTRACTOR ACKNOWLEDGES THAT THEY ARE AWARE THAT THE
SITE CONTAINS WETLANDS AND ARE PREPARED TO WORK UNDER
THESE CONDITIONS.
3. CLEARING SHALL CONSIST OF THE CUTTING, REMOVING, AND
DISPOSAL OF ALL NATIVE BRUSH, TREES, LOGS, STUMPS, ROOTS,
HEAVY SOD, VEGETATION, ROCKS, AND STONES LARGER THAN FOUR
(4) INCHES IN ANY DIMENSION, AND RUBBISH WITHIN DESIGNATED
WORK AREAS. ITEMS OR MATERIAL SMALLER THAN FOUR (4) INCHES
IN ANY DIRECTION CLEARED FROM THE SITE AND SUITABLE AS FILL
MATERIAL SHALL BE FIRST, UTILIZED IN ANY AREAS AS IDENTIFIED AS
REQUIRING FILL. MATERIAL SUITABLE FOR TOPSOIL SHALL BE
RESERVED FOR PLACEMENT WITHIN, OVER OR ON TOP OF THE NEWLY
CONSTRUCTED LEVEE TO PROMOTE RE-VEGETATION. EXCESS FILL
MATERIAL SHALL BE MOVED AND/OR TRANSPORTED TO A DESIGNATED
LOCATION ON SITE. EXCESS FILL MATERIAL SHALL BE DEPOSITED AS
SPREAD IN ACCORDANCE WITH TECHNICAL SPECIFICATIONS OR AS
DIRECTED IN THE FIELD BY THE OWNER OR ENGINEER WITH THE
INTENT TO CREATE AN ENVIRONMENT CONDUCIVE FOR PLANT
GROWTH OR RE-VEGETATION OF DISTURBED AREAS. PLACEMENT OF
CLEARED MATERIAL SHALL BE AS DIRECTED BY THE ENGINEER OR IN
ACCORDANCE WITH THE PROVIDED DETAILS LOCATED IN THE PLANS.
4. STRIPPING (OR GRUBBING) SHALL CONSIST OF THE COMPLETE
REMOVAL OF ALL EARTH MATERIALS CONTAMINATED BY ORGANICS
TO PREVENT THOSE ORGANICS FROM BEING INCORPORATED INTO
COMPACTED FILLS. THE CONTRACTOR SHALL STRIP ALL ORGANIC
GENERAL EARTHWORK/GRADING NOTES
GENERAL EARTHWORK/GRADING NOTES CONTINUED
GN02
GENERAL NOTES
GENERAL
EARTHWORK/GRADING
NOTES
CHECKED BY:
DATE:
EQUINOX PROJECT:
CONTRACT #:
SMC
WEC
07/09/2026
PELICAN HAVEN
WETLANDS
RESTORATION
PROJECT OWNER:
MARK DATE DESCRIPTION
PROJECT IDENTIFICATION:
PROJECT SPONSOR:
BINDING
ORDER
SHEET IDENTIFIER:
PREPARER:
PROFESSIONAL SEAL:
ENGINEERING
EQUINOX
www.equinoxengineering.us
SHEET TITLE:
STATE OF UTAH
DIVISION OF
NATURAL
RESOURCES
STATE OF UTAH
DEPARTMENT OF
NATURAL
RESOURCES
515 EAST
5300 SOUTH
OGDEN, UTAH
84405
UT-139-01
266113
S-100
GN03
THE ENGINEER PREPARING THESE PLANS WILL NOT BE RESPONSIBLE AND/OR LIABLE
FOR UNAUTHORIZED CHANGES TO OR USES OF THESE PLANS. ALL CHANGES MUST
BE IN WRITING AND MUST BE APPROVED BY THE PREPARER OF THESE PLANS.
NOTES / SHEET CALLOUTS
GENERAL NOTES
PROJECT SPECIFIC
NOTES
DAY DAYLIGHT LINE
DAYLIGHT LINE SHOW FOR REFERENCE PURPOSES
ONLY. APPROXIMATE DAYLIGHT LINE CALCULATED
AND DRAWN BY CIVIL 3D MODELING SOFTWARE AS
BASED ON PROJECT TOPOGRAPHICAL SURFACE
DATA. ACTUAL DAYLIGHT LINE LOCATION WILL BE
ESTABLISHED IN THE FIELD BY THE CONSTRUCTION
OF THE SIDE SLOPE OF THE LEVEE AS PER THE
SPECIFIED TOP WIDTH AND SLOPE. EXISTING
NATURAL GROUND ELEVATION WILL GOVERN AND
DICTATE THE ACTUAL DAYLIGHT LINE. TYPICAL
COMPACTED FILL
COMPACTED FILL SHALL BE PLACED IN LIFTS NOT TO
EXCEED 12 INCHES. MATERIAL SHALL BE
COMPACTED TO MEET OR EXCEED THE PROJECT
COMPACTION STANDARDS. SEE NOTE CS.
95% MAXIMUM STANDARD PROCTOR AS PER ASTM
698. CONTRACTOR SHALL PROVIDE WATER AS
NEEDED TO ALLOW MATERIAL TO BE WITHIN 2% OF
OPTIMUM MOISTURE CONTENT TO ALLOW FOR
EFFECTIVE COMPACTIVE EFFORT.
DEMOLITION
CONTRACTOR TO DEMOLITION ALL ABANDONED MAN MADE
NON-NATIVE MATERIALS FOUND ON THE PROJECT SITE AS
SHOWN ON THE PLANS OR AS DIRECTED IN THE FIELD. IF
ANY MAN MADE ITEM IS DISCOVERED THAT IS NOT SHOWN
ON THE PLANS THE CONTRACTOR SHALL CONTACT THE
ENGINEER PRIOR TO DISTURBANCE FOR DIRECTIONS
REGARDING THE DEMOLITION OF SAID DISCOVERED ITEM.
DO NOT DEMOLITION ANY UN-MARKED ITEM WITHOUT
PRIOR PERMISSION. DEMOLITION MAY INCLUDE BUT NOT
BE LIMITED TO THE REMOVAL OF CULVERT PIPES, STEEL
PIPE, CONCRETE ITEMS, WATER CONTROL GATES, WOOD,
OLD AUTOMOBILES, DISCARDED APPLIANCES, TRASH OR
OTHER MAN MADE MATERIALS. DEMOLITIONED
MATERIALS BECOME THE PROPERTY OF THE CONTRACTOR
AND MAY BE SOLD FOR SCRAP VALUE OR LEGALLY AND
PROPERLY DISPOSED OF AT THE CONTRACTORS
DISCRETION. CONCRETE TO BE DEMOLITIONED MAY BE
REPURPOSED AND USED AS RIP RAP WITH THE WRITTEN
APPROVAL OF THE ENGINEER. CONCRETE SHALL BE
BROKEN UP INTO SMALLER PIECES THAT MEET THE
GRADATION REQUIREMENTS FOR RIP RAP. UNDER NO
CIRCUMSTANCES SHALL ASPHALT, REBAR AND/OR STEEL
REINFORCEMENT BE ALLOWED TO REMAIN AND BE
INCORPORATED INTO ANY RIP RAP.
DEMO
DIAMETER OF PIPE
DISTANCE VARIES WITH SIZE OF PIPE.
EROSION CONTROL ROCK - RIP RAP
TYPICAL RIP RAP FOR ALL LOCATIONS TO RECEIVE
EROSION CONTROL ROCK SHALL BE WELL GRADED AND
RANGE IN SIZE FROM 3" TO 12" DIAMETER WITH NOT MORE
THAN 15% GREATER THAN 9" DIAMETER AND NOT LESS
THAN 15% SMALLER THAN 4" DIAMETER. ALL ROCK SHALL
BE HARD DURABLE SOUND PIECES HAVING A SPECIFIC
GRAVITY OF NOT LESS THAN 2.5. ROCK SHALL HAVE
ANGULAR FACES - RIVER ROCK WITH SMOOTH OR
ROUNDED SURFACES IS NOT SPECIFIED. ANY MATERIAL
CONTAINING ASPHALT IS PROHIBITED. DEPTH OF ROCK
APRON SHALL BE 12" MINIMUM. FILTER FABRIC SHALL BE
INSTALLED UNDER ALL EROSION CONTROL ROCK.
FILTER FABRIC SHALL BE INSTALLED UNDER ALL SELECT
FILL, AND UNDER ANY INLET/OUTLET EROSION CONTROL
ROCK AND ALONG THE BACK VERTICAL WALL FACES OF
ANY ROCK WALLS THE ARE NOT SCOUR CURTAINS -TYPICAL
OVERLAP CLOSURE SEAM SHALL BE 24" MINIMUM LENGTH.
FABRIC SHALL BE A NON-WOVEN POLYESTER OR
POLYPROPYLENE GEOTEXTILE. THE GEOTEXTILE FABRIC
SHALL HAVE A MINIMUM GRAB TENSILE STRENGTH OF ONE
HUNDRED FIFTY (150) POUNDS AS DETERMINED BY ASTM
D-1682. THE GEOTEXTILE FABRIC SHALL HAVE A
MAXIMUM EQUIVALENT OPENING SIZE (E.O.S.) OF A
NUMBER SEVENTY (70) U.S. STANDARD SIEVE. FABRIC
SHALL BE TENCATE MIRAFI N-SERIES 160N OR APPROVED
EQUAL.
ADJACENT CONCRETE WALL/FLOOR SUPERIMPOSED
FOR VISUAL CLARITY
EXISTING FENCE - PRESERVE AND PROTECT UNLESS THE
FENCE IS SPECIFICALLY NOTED TO BE DEMOLITIONED.
CONTRACTOR MAY TEMPORARILY REMOVE FENCE TO
FACILITATE CONSTRUCTION WITH APPROVAL FROM
ENGINEER OR OWNER. CONTRACTOR SHALL BE
RESPONSIBLE TO REPAIR ANY DAMAGE AND/OR REINSTALL
ANY REMOVED FENCE SECTIONS TO PRE-PROJECT
CONDITIONS.
AW
12CFC 12 INCHES COMPACTED FILL COVER MINIMUM - TYPICAL
NEWLY INSTALLED PIPE SHALL BE COVERED WITH A
MINIMUM OF 12" COMPACTED FILL IN ANY AREA WHERE
TRAFFIC IS EXPECTED (EXISTING DIRT ROAD AND ACCESS
LEVEE INCLUDING ANY SIDE SLOPES FROM THE BROW TO
THE DAYLIGHT TOE). CONTRACTOR MAY MOUND FILL
MATERIAL AS NEEDED TO ACHIEVE MINIMUM COVER. IF
THE COVER MATERIAL IS PLACED ON A ROADWAY, TOP OF
LEVEE OR WHERE VEHICLE TRAFFIC IS EXPECTED THEN
THE CONTRACTOR SHALL PROVIDE A 10H:1V OR
SHALLOWER APPROACH RAMP ON BOTH SIDES OF THE
PIPE TO ALLOW FOR A DRIVABLE SURFACE OVER THE PIPE.
COMPACTION STANDARD FOR PROJECT
ALL COMPACTED FILL FOR AREAS SPECIFIED TO BE
COMPACTED SHALL BE COMPACTED TO 90% MODIFIED
PROCTOR AS DETERMINED BY ASTM D698.
CONTRACTOR SHALL PROVIDE WATER AS NEEDED TO
ALLOW MATERIAL TO BE WITHIN 2% OF OPTIMUM
MOISTURE CONTENT TO ALLOW FOR EFFECTIVE
COMPACTIVE EFFORT.
FLOOR ELEVATION - TOP OF CONCRETE
CF
Dp
ECR
CS
FLOWLINE OF PIPE OR WATER WAYFL
CONTROL POINT
SITE SPECIFIC SPATIAL AND ELEVATION CONTROL POINT
PROJECT VERTICAL AND HORIZONTAL CONTROL.
REBAR WITH CAP - TOP OF REBAR IS REFERENCE
ELEVATION. PRESERVE AND PROTECT - CONTRACTOR
SHALL BE RESPONSIBLE TO REPLACE AT THEIR EXPENSE
ANY DISTURBED OR DESTROYED CONTROL POINTS.
CP
EXISTING WATER CONTROL INFRASTRUCTURE
PRESERVE AND PROTECT.
EXISTING WATER CONTROL INFRASTRUCTURE MAY
INCLUDE BUT NOT BE LIMITED TO PIPE, CONTROL
STRUCTURE, GATES, GRADING, EROSION CONTROL AND/OR
ANY MANMADE OR NATURAL OBJECTS THAT PROVIDE
WATER CONTROL. CONTRACTOR SHALL AVOID DAMAGING
EXISTING WATER CONTROL INFRASTRUCTURE. ANY
DAMAGE CAUSED BY THE CONTRACTOR TO ANY EXISTING
WATER CONTROL INFRASTRUCTURE SHALL BE REPLACED
OR REPAIRED TO PRE-PROJECT CONDITIONS.
EXWCIP
EXISTING WATER CONTROL INFRASTRUCTURE
TO BE DEMOLISHED.
EXISTING WATER CONTROL INFRASTRUCTURE MAY
INCLUDE BUT NOT BE LIMITED TO PIPE, CONTROL
STRUCTURE, GATES, GRADING, EROSION CONTROL AND/OR
ANY MANMADE OR NATURAL OBJECTS THAT PROVIDE
WATER CONTROL. CONTRACTOR SHALL DEMO EXISTING
WATER CONTROL INFRASTRUCTURE AS PART OF THE
SCOPE OF WORK. SEE NOTE DEMO FOR ADDITIONAL
INSTRUCTIONS.
EXWCID
NEW PIPE 24" DIAMETER OUTLET PIPE - LENGTH AND
DIAMETER OF PIPE VARIES BY LOCATION - SEE NOTES AND
WATER CONTROL STRUCTURE CALLOUT. PIPE SHALL BE
ADS N-12 DUAL WALL CORRUGATED HDPE PLASTIC PIPE
OR APPROVED EQUAL. PIPE SHALL BE CONNECTED TO
WCS PIPE STUB BY CONTRACTOR. ALL CONNECTIONS
SHALL BE INSTALLED PER THE MANUFACTURERS
SPECIFICATIONS AND SHALL BE WATER TIGHT. BELL AND
SPIGOT CONNECTIONS ARE SPECIFIED WHERE PIPE
GEOMETRY ALLOWS. FOR NON BELL AND SPIGOT
GEOMETRY, SNAP COUPLERS OR CLAMSHELL TYPE
FITTINGS ARE SPECIFIED - MAR MAC COUPLERS ARE NOT
APPROVED FOR USE. PIPE SHALL BE COVERED WITH A
MINIMUM OF 6" INCHES OF SOIL. IN LOCATIONS WHERE
TOP OF PIPE IS LESS THAN 6 INCHES BELOW THE EXISTING
OR FINISHED GRADE, EARTH MATERIAL SHALL BE
MOUNDED OVER THE PIPE. PROVIDE A MINIMUM OF 6
INCH DEPTH TO A DISTANCE OF 1 PIPE DIAMETER AWAY
FROM THE EDGE OF THE PIPE AND THEN TAPER THE
MOUNDED EARTHEN MATERIAL TO DAYLIGHT AT A 4H:1V
SLOPE OR SHALLOWER. TYPICAL. TRENCH SPOILS MAY BE
USED FOR COVER MATERIAL. IF INSUFFICIENT TRENCH
SPOILS MATERIAL IS GENERATED THEN GRUBBED
MATERIAL OR EARTHEN MATERIAL NOT SUITABLE FOR
COMPACTED FILL MAY BE USED AS COVER MATERIAL -
EXCAVATION OUTSIDE OF THE WORK AREAS IS NOT
PERMITTED. COVER MATERIAL DOES NOT NEED TO BE
COMPACTED. CONTRACTOR SHALL BE REQUIRED TO HAUL
COVER MATERIAL FROM ANY GRUBBED OR BORROW
LOCATION AS NEEDED TO SATISFY THE MINIMUM COVER
REQUIREMENT. TYPICAL.
18P NEW PIPE 18"…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .