This is a demolition plan for the Bert Goens Learning Center Pool Improvements project, a capital improvement initiative by the Van Buren Intermediate School District located in Lawrence, Michigan. The plan, designated as Unit 'B' Demolition Plan (A2.1.1B), outlines comprehensive demolition work required prior to construction activities. The scope includes removal of existing walls, doors, windows, and borrowed lites; demolition of suspended and plaster ceilings with replacement per reflected ceiling plans; removal of existing floor coverings, casework, and millwork; extraction of plumbing and mechanical fixtures; elimination of window walls with aluminum framing; removal of lift equipment, basketball backboards, and toilet partitions; demolition of existing lockers and locker bench bases; removal of mezzanine structures; and extraction of terrazzo flooring and concrete slabs. The plan specifies floor surface patching, wall surface preparation for new finishes, and protection of items designated for reuse or relocation. Issuances for the project include the base bid dated May 21, 2026, Addendum 001 dated June 2, 2026, and Addendum 002 dated June 9, 2026. The drawing scale is 1/8" = 1'-0" and covers Unit B of a three-unit project (Units A, B, and C).

The demolition contractor is required to immediately cease work and notify the construction manager if asbestos is encountered, with abatement to be performed under a separate contract negotiated by the owner. All masonry block and brick walls scheduled for removal must be toothed to receive new masonry unless otherwise noted. The contractor must provide temporary shoring and bracing for existing roof and floor structures until permanent walls and lintels are installed, with bearing conditions specified in structural and architectural drawings. Coordination across all trades is mandatory for demolition, capping, and abandonment of mechanical, electrical, plumbing, and architectural items. All items designated for saving or relocation must be stored properly to prevent damage, and all demolition-related damage to adjacent surfaces must be repaired to match existing materials and finishes. Wall and floor surfaces receiving new finish materials require patching to match existing conditions, and new openings in existing walls require coordination of new lintels with the masonry contractor.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BF

BF

DEMOLITION NOTES

01 REMOVE EXISTING WALL INCLUDING DOORS, WINDOWS, BORROWED LITES, AND ANY EQUIPMENT OR FURNISHINGS ATTACHED TO WALL OR PORTION OF EXISTING WALL AS SHOWN ON FLOOR PLAN (MIN. 4" BELOW FLOOR SLAB) AND AS REQUIRED FOR NEW CONSTRUCTION. FLOOR SURFACE TO BE PATCHED AS REQUIRED TO RECEIVE NEW FLOOR MATERIAL. WALL SURFACE TO BE PATCHED AS REQUIRED TO RECEIVE NEW WALL FINISH. SEE MECHANICAL & ELECTRICAL DEMOLITION NOTES FOR RELATED ITEMS. SUPPORT

UNBRACED SECTIONS OF WALL OR ROOF AS REQUIRED.

02 REMOVE EXISTING BORROWED LITE OR DOOR & DOOR FRAME. (DOOR LINTEL TO REMAIN UNLESS OTHERWISE NOTED ON PLAN - SEE STRUCTURAL FOR ADDITIONAL INFORMATION). WHERE DOOR FRAMES ARE TO REMAIN, PROTECT FRAMES FROM DAMAGE. SAND AND PREP FOR NEW PAINT FINISH UNDER SECTION 09 90 00 SEE DOOR SCHEDULE FOR REQUIRED NEW DOORS AND FRAMES OR ONLY NEW DOORS.

03 SAW CUT AND REMOVE FLOOR OR PORTION OF EXISTING FLOOR SLAB AS SHOWN OR DIMENSIONED ON FLOOR PLAN. FLOOR CUTS SHOWN REPRESENT APPROXIMATE SIZE, LOCATION AND INTENT OF FLOOR

CUTTING, FLOOR CUTTING MAY VARY FROM SHOWN, COORDINATE WITH ARCHITECT/ENGINEER.

EXCAVATE, FILL & COMPACT SOIL AS REQUIRED FOR NEW SLAB- COORDINATE WITH MECHANICAL/ ELECTRICAL DEMOLITION NOTES FOR RELATED ITEMS & LOCATIONS. INSTALL NEW SLAB TO MATCH EXISTING

ELEVATION. SEE STRUCTURAL FOR ADDITIONAL INFORMATION REGARDING SLAB REMOVAL.

04 REMOVE EXISTING CASEWORK/MILLWORK, COUNTER TOPS & BACK SPLASH. SAVE ITEMS AT OWNER'S

REQUEST.

05 REMOVE EXISTING SUSPENDED/PLASTER CEILING - INCLUDING ALL FRAMING, TILES, TEES, HANGERS &

WIRES USED TO SUPPORT THAT CEILING. REPLACE PER REFL. CEILING PLANS.

06 SEE MECHANICAL DEMOLITION NOTES FOR REMOVAL OF EXIST. PLUMBING/MECHANICAL (i.e. LAVATORIES, SINKS, WATER CLOSETS, URINALS, SHOWER HEADS, FLOOR DRAINS, FIN TUBE, MECH. DUCTWORK, UNIT

VENTS, ETC.)

07 REMOVE EXISTING WINDOW, WINDOW WALL WITH ALUMINUM FRAMING WITH METAL PANELS BELOW WINDOW, FRAME, SILL & GLAZING INCLUDING ALL EXISTING WOOD BLOCKING AND FRAMING ABOVE

WINDOWS TO ROOF AND/OR MASONRY TIES AT BRICK PIERS AND SIDE WALLS.

08 REMOVE EXISTING LIFT EQUIPMENT AND ANY ITEMS ASSOCIATED SECURED TO THE FLOOR, WALLS, OR CEILING. REPAIR ANY DAMAGE TO ADJACENT SURFACES TO MATCH EXISTING MATERIALS AND FINISHES.

COORDINATE ALL REPAIR WORK WITH NEW CONSTRUCTION.

09 REMOVE EXISTING CHALK, TACK OR WHITE BOARD. REMOVE ALL GLUE RESIDUE, ETC. FROM BLOCK BEHIND

BOARD AND PREPARE SURFACE FOR NEW FINISH MATERIALS WHERE REQUIRED.

16 REMOVE EXISTING BASKETBALL BACKBOARD AND ALL RELATED HANGERS, FASTENERS AND FRAMING TO

STRUCTURE ABOVE.

11 REMOVE PORTION OF EXISTING ROOF & STRUCTURE (AS SHOWN ON DEMOLITION PLAN). PROVIDE TEMPORARY WEATHER PROTECTION AS NEEDED AROUND PERIMETER OF ROOF REMOVAL AS REQUIRED.

PROVIDE TEMPORARY SHORING & BRACING AS REQUIRED.

12 REMOVE EXISTING TOILET PARTITION, DISPENSERS AND/OR TOILET ACCESSORIES AND REPAIR ADJACENT

SURFACES TO RECEIVE NEW FINISHES.

13 REMOVE EXISTING LOCKERS AND LOCKER BENCH BASE. CUT SLOPED LOCKER TOP & BASE AS NECESSARY.

RE-USE/RELOCATE EXISTING END PANEL(S) AS REQUIRED. REVISE & PREPARE FOR NEW FINISHES.

10 REMOVE EXISTING FLOOR COVERING AND BASE, INCLUDING ALL GLUE RESIDUE, MUDBEDS, ETC. FROM FLOORS & WALLS AND PREPARE SURFACE FOR NEW FINISH MATERIALS, INCLUDING GRINDING, PATCHING AND/OR SELF-LEVELING COMPOUND AS REQUIRED. WALL & FLOOR SURFACE TO RECEIVE NEW FINISH

MATERIAL & PATCH TO MATCH EXISTING.

14 REMOVE EXISTING MEZZANINE INCLUDING ALL SUPPORT FRAMING, FLOOR DECK, HANGERS AND ALL ADDITIONAL RELATED MATERIALS. REPAIR WALL TO MATCH ADJACENT WALL MATERIALS AND FINISH.

15 REMOVE EXISTING TERRAZZO FLOORING, CONCRETE SLAB AND COVED BASE. REFER TO ROOM FINISH

SCHEDULE FOR NEW FLOORING.

DEMOLITION CONTRACTOR IS TO STOP WORK IMMEDIATELY IN AREA IF ASBESTOS IS ENCOUNTERED.

NOTIFY CONSTRUCTION MANAGER OF SUSPECTED AREA SO PROPER ABATEMENT CAN BE DONE.

(UNDER A SEPARATE ASBESTOS ABATEMENT CONTRACT AS NEGOTIATED BY OWNER.)

ALL MASONRY BLOCK AND BRICK WALLS TO BE REMOVED MUST BE TOOTHED TO RECEIVE NEW

MASONRY, UNLESS NOTED OTHERWISE ON DRAWINGS.

DEMOLITION CONTRACTOR IS TO PROVIDE TEMPORARY SHORING AND BRACING FOR EXISTING

ROOF/FLOOR STRUCTURE AS REQUIRED UNTIL PERMANENT WALLS & LINTELS ARE INSTALLED.

REFER TO STRUCTURAL & ARCHITECTURAL DRAWINGS FOR BEARING CONDITIONS.

ALL TRADES ARE TO COORDINATE ANY DEMOLITION, CAPPING OR ABANDONMENT OF EXISTING

MECHANICAL, ELECTRICAL, PLUMBING OR ARCHITECTURAL ITEMS.

ALL ITEMS TO BE SAVED AND/OR RELOCATED ARE TO BE STORED IN A PROPER MANNER SO NO

DAMAGE WILL OCCUR TO THESE ITEMS DURING THEIR STORAGE PERIOD.

ALL DEMOLITION WHICH DAMAGES ADJACENT SURFACES IS TO BE REPAIRED TO MATCH THE

EXISTING SURFACE DAMAGED (MATERIALS & FINISHES) AND ALL REPAIR WORK IS TO BE

COORDINATED WITH NEW CONSTRUCTION. FOR NEW OPENINGS IN EXISTING WALLS, COORDINATE

NEW LINTELS W/ MASONRY CONTRACTOR.

PATCH WALLS & ROOF TO MATCH EXISTING CONSTRUCTION BEHIND REMOVAL OF WALL LOUVERS, EXHAUST FANS, INTAKE HOODS & CABINET HEATERS. VERIFY SEQUENCE OF REMOVAL W/

CONSTRUCTION MANAGER. SEE MECHANICAL AND ELECTRICAL DEMOLITION SHEETS FOR WALL,

ROOF & FLOOR OPENINGS TO BE PATCHED.

ALL TRADES ARE TO COORDINATE THE REMOVAL OF EXISTING LOOSE EQUIPMENT WITH ARCHITECT AND/OR OWNER. ADDITIONAL EQUIPMENT FOUND THAT IS NOT NOTED ON DEMOLITION PLAN SHALL BE REMOVED AS PART OF GENERAL DEMOLITION AFTER VERIFICATION WITH ARCHITECT/OWNER.

17 REMOVE EXISTING DOOR LEAF/PANEL AND DOOR HARDWARE. EXISTING FRAME TO REMAIN; PROTECT FRAME FROM DAMAGE, SAND, AND PREP FOR NEW PAINT FINISH UNDER SECTION 09 90 00. REFER TO DOOR

SCHEDULE FOR DEMOLITION SCOPE OF EXISTING DOORS.

17 REMOVE EXISTING DOOR LEAF/PANEL AND DOOR HARDWARE. EXISTING FRAME TO REMAIN; PROTECT FRAME FROM DAMAGE, SAND, AND PREP FOR NEW PAINT FINISH UNDER SECTION 09 90 00. REFER TO DOOR

SCHEDULE FOR DEMOLITION SCOPE OF EXISTING DOORS.

18 REMOVE ANY PARTIAL CERAMIC TILE AT MASONRY WALLS TO REMAIN AND PREPARE SURFACE FOR NEW

FINISHES. SEE MECHANICAL & ELECTRICAL DEMOLITION NOTES FOR RELATED ITEMS.

19 REMOVE ALL EXISTING POOL DECK TILE, BASE, ADHESIVES, AND RELATED MATERIALS WITHIN THE AREA OF WORK. TILE TO BE REPLACED IN ITS ENTIRETY. REFER TO FINISH PLANS FOR NEW TILE LAYOUT.

DEMOLITION LEGEND

EXISTING WALL TO BE DEMOLISHED

PORTION OF EXISTING WALL TO BE DEMOLISHED

EXISTING OBJECT TO BE DEMOLISHED

EXISTING WALLS TO REMAIN

EXISTING OBJECTS TO REMAIN

XX DEMOLITION TAG: SEE DEMOLITION NOTES

AREA OF FLOOR CUTTING

ROOM NAME

CEILING FINISH

FLOOR FINISH

EXISTING ROOM FINISH INFORMATION:

ROOM NAME, FLOORING TYPE, CEILING TYPE

AREA OF CEILING REMOVAL AND REINSTALL

REMOVE AND REINSTALL

EXISTING ACT CEILING AS

REQUIRED FOR WORK

REMOVE AND REINSTALL

EXISTING ACT CEILING AS

REQUIRED FOR WORK

REMOVE CMU TO

RECESS PHONE

BOX, COORDINATE

WITH NEW WORK

MECHANICALOCCUPATIONAL THERAPYEARLY ELEMENTARY

TOILETTIME OUT

OBSERVATION

TIME OUTTOILET

PRE-PRIMARY

SEVERLY MENTALLY IMPAIRED

TOILET

TIME OUT

OBSERVATION

TIME OUT

TOILET

TOILET

CLINICOFFICETEACHER LOUNGE

OFFICE

OFFICE

OFFICE

STORAGE

CONF. ROOM

HALL

RECEPTION

VESTIBULE

LOBBY

CORRIDOR

CORRIDOR

CORRIDOR

CORRIDOR

JANITOR

STORAGE

KITCHEN

MULTI PURPOSE ROOM

GIRLS LOCKER ROOM

BOYS LOCKER ROOM

THERAPY POOL

SHOWER / TOILET RM

SHOWER / TOILET RM

LATER ELEMENTARY

TIME OUT

OBSERVATION

TIME OUT

JUNIOR HIGH

TOILET TOILET

HIGH SCHOOL

TIME OUT

OBSERVATION

TIME OUT

HOME ECONOMICS

TOILET

VESTIBULE

WORKSHOP

PHYSICAL THERAPY

STORAGE AND RECEIVING

VESTIBULE

PROJECT NO.

DRAWN

REVIEWED

NO PART OF THIS DRAWING MAY BE

USED OR REPRODUCED IN ANY FORM

OR BY ANY MEANS, OR STORED IN A

DATA BASE OR RETRIEVAL SYSTEM,

WITHOUT PRIOR WRITTEN

PERMISSION OF

ALL RIGHTS RESERVED

c

KEYPLAN

ISSUANCES

GMB COPYRIGHT

Au to de sk

D oc s:

//5

-6

VB

IS

D

B er t G oe ns L ea rn in g

C en te r P oo l I m pr ov em en ts

/5 -6

2A

5.

rv t

6/ 9/

:2

9:

A M

A2.1.1B

5-6732

UNIT 'B' DEMOLITION PLAN

LFR

SDC

B E

R T

G O

E N

S L

E A

R N

IN

G

C E

N T

E R

P O

O L

IM

P

R O

V E

M E

N T

S

V A

N B

U R

E N

IN

TE

R M

E D

IA

TE

S C

H O

O L

D

IS

TR

IC

T

LA

W R

E N

C E

M

IC

H

IG

A

N

1/8" = 1'-0"

UNIT 'B' DEMOLITION PLAN

UNIT A

UNIT B

UNIT C

05.21.2026 BIDS &

CONSTRUCTION

06.02.2026 ADDENDUM 001

06.09.2026 ADDENDUM 002

A2.1.1B - UNIT 'B' DEMOLITION PLAN