SF30-Amendment_7.pdf

PDF 123 KB Posted

Attached to
Design Build, Roof Replacement & Repairs, US Post Office/Courthouse, Little Rock, AR
Solicitation number
47PH0518R0051
Issued by

About this file

SF-30 Amendment 7

View the file

Other files

File Type Posted
SF30-Amendment_6.pdf PDF
Sample_Bid_Schedule.xlsx XLSX spreadsheet
SF30-Amendment_5.pdf PDF
SF30-Amendment_4.pdf PDF
SF30-Amendment_3.pdf PDF
SF30-Amendment_2.pdf PDF
SF30-Amendment_1.pdf PDF
Amended_SOW--Little_Rock_Arnold_CH_Roof_Replacement.pdf PDF
Site_Visit_Agenda-Roof_Replacement_LR_5_8_18.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
Solicitation_and_Agreement.pdf PDF
CAD_Drawings--Little_Rock_Arnold_CH_Roof_Replacement.dwg DWG drawing
Drawings--Little_Rock_Arnold_CH_Roof_Replacement.pdf PDF
GSA527-15b.pdf PDF
C301_GC_Reps_&_Certs.docx DOCX document
Product_samples--Little_Rock_Arnold_CH_Roof_Replacement.pdf PDF
PBS_Past_Performance_Questionnaire.pdf PDF
SOW--Little_Rock_Arnold_CH_Roof_Replacement.pdf PDF
vendor_fitness_manual.pdf PDF
PBS_3490.2.pdf PDF
Sample_Bid_Schedule.xlsx XLSX spreadsheet
AR32_5Jan18.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

GENERAL SERVICES ADMINISTRATION

PUBLIC BUILDING SERVICE

819 TAYLOR ST, RM 12B

FORT WORTH, TX 76102

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

47PH0518R0051

9B. DATED (SEE ITEM

11) 04/19/2018

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATD (SEE ITEM 13)

CODE FACILITY CODE

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable) 2. AMENDMENT/MODIFICATION NUMBER

0007 07/19/2018

6. ISSUED BY CODE 7PQC 7. ADMINISTERED BY (If other than Item 6) CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

1. See Attached RFI Questions and Answers.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

RFP47PH0518R0051

Design Build, Roof Replacement & Repairs US Post Office/Courthouse, Little Rock, AR RFI Questions and Answers

1. On the SF-30 it says Option 3 is for Roof C, but then there’s no Scope provided for work on Roof C. Can you clarify the scope of work and/or if this is not an option?

Answer: Roof C initially had no repairs to it so it was not listed on the original scope as needing any design or work done. However, when the scope was amended to provide roof anchors for window washing/maintenance, roof C came into play. Roof

C will only need an anchor system design and the anchors installed on it per the amended scope. No other repairs will be needed on roof C.

2. What type of ceiling is present at Roofs B and C?

Is the thickness of the concrete decks at Roofs B and C known?

Answer: The ceilings under roof section B are open to the concrete roof deck in three areas, and a mixture of a plaster ceiling and a suspended drop ceiling under the roof deck. There is plenty of accessibility.

The ceiling under roof section C is a mixture of a plaster ceiling and a suspended drop ceiling under the roof deck. There is also plenty of accessibility on this one as well.

The roof deck on roof c is approximately 3 inches thick.

The roof deck(s) on roof(s) b are approximately 5 inches thick.