SF30 Amendment 3 Solicitation Toledo 47PC0620R0001.pdf

PDF 483 KB Posted

Attached to
General Construction Services for the Hurricane Repair Project at the Jose V. Toledo U. S. Courthouse, San Juan, Puerto Rico
Solicitation number
47PC0620R0001
Issued by

About this file

This solicitation requests proposals for general construction services for hurricane repair projects at the Jose V. Toledo U.S. Courthouse in San Juan, Puerto Rico. The solicitation is a total small business set aside under NAICS code 236220 for commercial and institutional building construction. Interested parties must register for the pre-proposal conference and site visit scheduled for November 18, 2019. Questions regarding the solicitation are due by November 25, 2019, and proposals must be submitted electronically by the date and time specified in the solicitation. The scope of work includes roof repairs, electrical work, and other general construction. Past performance submissions should relate to similar scopes of work. The General Services Administration is the contracting agency, and the solicitation documents contain both public and sensitive information requiring access through beta.sam.gov.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

2. AMENDMENT/MODIFICATION NUMBER

2PQAC

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Contracting Officer

Please see attached.

2PQAC

CARIBBEAN ACQUISITION UNIT

GSA, PUBLIC BUILDINGS SERVICE

150 CARLOS E. CHARDON AVENUE, ROOM 359

HATO REY, PR 00918

CARIBBEAN ACQUISITION UNIT

GSA, PUBLIC BUILDINGS SERVICE

150 CARLOS E. CHARDON AVENUE, ROOM 359

HATO REY, PR 00918

47PC0620R0001

/2019

11/13/2019

1 15

NATALIA LUGO-

VINA CRUZ

Digitally signed by NATALIA

LUGO-VINA CRUZ

Date: 2019.12.11 12:40:20 -04'00'

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

General Construction Services for the Hurricane Repair Project at the Jose V. Toledo U.S.

Courthouse, San Juan, Puerto Rico

Solicitation No. 47PC0620R0001

Amendment No.

GSA-PBS, Region 2

Amendment No. is hereby issued as follows:

END OF AMENDMENT NO.

Section 108113

BIRD CONTROL DEVICES

PART 1 – GENERAL

1.1 SUMMARY

A. This Section includes:

1. PE-Plus Premium Grade Bird Net to prevent birds from entering, roosting and nesting in areas where they are unwanted, and prevent damage from droppings and nesting materials.

1.2 CONFORMANCE SUBMITTALS

A. Substitute Products: No substitute products will be accepted.

B. Product Data: Submit manufacturer’s samples, catalog cuts, shop sketches and other descriptive materials.

1.3 CLOSEOUT SUBMITTALS

A. Maintenance Data

1.4 QUALITY ASSURANCE

A. Single Source Responsibility: Netting and all parts specified in this section will be supplied by a single manufacturer.

B. Obtain technical literature from the specified manufacturer, telephone consultation and plan/photograph evaluation.

C. Utilize labor or Bird-X authorized installers who are certified in Bird-X Product installations. Proof of certification required.

1.5 PRODUCT HANDLING

A. Protect PE-Plus Premium Grade Bird Net and hardware system from damage before, during and after installation.

B. If damage occurs to PE-Plus Premium Grade Bird Net, make all replacements immediately.

1.6 WARRANTY

A. 10-year minimum warranty against material defects and workmanship for black netting, 3-year minimum warranty for white and stone netting.

PART 2 – PRODUCTS

2.1 ACCEPTABLE MANUFACTURER

A. Bird-X, Inc. (Basis of Design)

300 N. Oakley Blvd., Chicago, IL. 60612

Phone: 800.662.5021, Fax: 312.226.2480;

Email: solutions@bird-X.com www.bird-x.com

2.2 PRODUCT DESCRIPTION

A. Model Designation:

1. ¾” PE-Plus Premium Grade Bird Net (NET-PE)

B. Color: Black, White, Stone

2.3 MATERIAL

A. Material: U.V. Stabilized knotted HDPE net. Non-conductive, flame resistant, rot resistant, waterproof, and stable in subzero temperatures.

B. Construction: 12/6 construction – 6 strands of UV protected HDPE yarn, each 0.012 inch in diameter.

C. Sizes: As required

D. Break strength: 52 lbs. per strand

E. ISO 1806 Mesh Strength Test: Peak Load 575 lbs force

F. 24” Wide Span Orthogonal Strength Test: Peak load 575 lbs force

G. Electrical Properties: Non-conductive

H. UV Stability: UV protection system of Hindered Amine Light Stabilizers (HALS), Anti-oxidants and weather resistant pigments formulated exclusively for Bird-X.

I. Thermal Properties: Melting point in excess of 250 degrees F. Flame resistant. Can be heated for short periods of time in excess of 500 degrees F.

J. Flammability: Burns slowly in air. Fine filaments tend to melt and drop away before propagating flame.

2.4 MOUNTING SYSTEMS

A. Hardware: stainless steel recommended for all exterior applications

1. Corner/Primary Attachments

2. Intermediate Attachments

3. Stringing Wire/Cable

4. Ferrules (Copper or Aluminum)

5. Turnbuckles

6. Net Rings

PART 3 – EXECUTION

3.1 EXAMINATION

A. Examine installation area. Notify Owner’s Agent of detrimental work conditions.

B. Do not proceed until conditions are corrected.

3.2 AREA AND SURFACE PREPERATION

A. Remove existing bird droppings in a safe manner. Large quantities shall be removed and disposed. Work areas shall be cleaned, and repair work shall be done in areas which will be excluded by the PE-plus premium grade Bird Net.

B. Remove or repair articles that may damage the PE-plus premium grade Bird Net after installation.

3.3 INSTALLATION

A. Install as recommended by the manufacturer.

B. Correct mesh sizes shall be specified to ensure exclusion of the correct pest bird.

C. Shall be installed tightly and securely to ensure a long-lasting installation that is visually hard to see.

3.4 INSPECTION

A. Visually inspect PE-plus premium grade Bird Net for poor adherence to mounting surfaces, or other problems related to poor installation or surface preparation.

B. Repair as necessary immediately.

RFIs 11-54 Responses

11. Drawing sheets E-101.1 & E-601.1 - No information has been found in relation to the new panel, EPPG1. Can you please provide capacity (Amps) and quantity of breakers for this panel?

Panel EPPG1 is an existing panel by GE, A-series. Key notes 2 and 3 call for 20A/1P breakers for the new circuits.

12. Drawing sheets E-101.1 & E-601.1 - No information has been found in relation to the new panel, EPPG1. Can you please indicate if it should be surface mounted, painted, and if it is lug feed or main breaker feed?

Panel EPPG1 is an existing panel by GE, A-series. Key notes 2 and 3 call for 20A/1P breakers for the new circuits.

13. Drawing sheet E-601.1 - No Panel Schedule has been found for the new panel identified as EPPG1. Can you please provide?

Panel EPPG1 is an existing panel by GE, A-series. Key notes 2 and 3 call for 20A/1P breakers for the new circuits.

14. No information has been found regarding the cable size and conduit diameter for the feeder toward new panel EPPG1. (Sheet E-101.1) Can you please provide?

Panel EPPG1 is an existing panel by GE, A-series. Key notes 2 and 3 call for 20A/1P breakers for the new circuits.

15. Can you please provide information and model in relation to the Electronic Power Demand Meter?

Refer to specification section 260913.

16. Does the teaming partners experience count as Past Experience for this solicitation/evaluation?

Yes.

17. Does the Key Personnel Experience count as experience for this solicitation/evaluation?

Yes.

18. In the document “Specifications NOTES Toledo” Item 14 (13100 – Project Management and Coordination) Mention three positions to be full time in the project:

Quality Control Manager, Safety Officer and Project Coordinator/ Project Manager.

Due to efficiency reasons, The Project Manager can have more than 1 role? E.g. Project Manager/Quality Manager?

Separate from the Project Coordinator shall be a Safety & Health Officer, Waste Management Coordinator, Mechanical & Electrical Coordinator, Commissioning Coordinator, Historic Preservation Coordinator and Quality Control Manager.

19. In Document, “The DRAFT Agreement” Part I. Project Information, Section III.B.

Contractor Responsibilities indicates, “GSAR 552.236-71, Contractor Responsibilities is located in Section IV.A. of this Agreement and is supplemented as follows:

(1) The Contractor shall secure and pay for all necessary permits and governmental fees, licenses, and inspections that are customarily secured after award of the Contract and that are legally required at the time of award. The Contractor shall provide a copy of the permits required for execution”

What kind of permits are required? E.g. Historical, Environmental, Municipality?

All applicable permits to the Project.

20. In Document, “The DRAFT Agreement” Part IV. Contract Clauses Section IV.A.

Clauses Incorporated in Full Text 14- (c) The Contractor shall immediately bring to the Contracting Officer's attention any hazardous materials or conditions not disclosed in the contract documents discovered by or made known to the Contractor during the performance of the contract.

In case of Asbestos and Lead assessment is required in all the areas to be worked?

Asbestos and Lead assessments are required to obtain a construction permit.

21. In Specification Document, Section 073215 - Clay Roof Tile Restoration

For the roof tile manufacturer, Variant equal or similar will be allowed?

No. No similar variants will be allowed. Use only Ludowici Tiles to match the existing tiles.

22. Regarding the handling of the administrative process of the different types of warranties of the variety of products required in project specifications, Is it required that warranty certificates be requested & provided by the contractor as the intermediary between the manufacturer & GSA? In addition, in whose name the manufacturer's warranty certificates be directed? Variants in warranty terms will be allowed?

Refer to the Federal Acquisition Regulation (FAR) - FAR 52.246-21 Warranty of Construction

The Contractor shall require any subcontractors, manufacturers, or suppliers thereof to execute their warranties, in writing, directly to the government.

The manufacturer's warranty certificates shall be directed to GSA.

The Government established required warranties as a minimum to be complied with.

23. In Specifications Document, Section 075216 – SBS Membrane Roofing, 2.2 Manufacturer

A variant (equal or similar) in material/manufacturer will be allowed?

A variant alternate manufacturer of equal or better SBS roofing will be allowed.

24. In drawing A-103 - Tower Level Roof Plan

Substitution in the type of membrane to be applied at tower level (Ex. to cool roof silicone elastomeric membrane or any equal or similar that complying the project requirement in terms of quality, warranty, wind pressure and uplift) can be allowed?

No silicone or rubber single sheet membrane roofing is allowed.

In Drawing A-525 Detail 5 identifies an existing roof membrane under clay tile, but it does not describe the type of membrane.

The existing membrane is a single ply roll of asphalt sheet. Place new roofing membrane on top of existing membrane. Contractor to provide a separate cost for removal of existing membrane if required.

In that case, can use a synthetic rubber, intercoat sealing membrane before installing de clays in all roofs?

The Contractor may propose a membrane that can be applied over the existing asphalt membrane, However, the membrane must be acceptable by the FOAM adhesive manufacturer that the TILE manufacturer will accept. FOAM be able to adhere to both the membrane and the tile.

25. In case of concrete repairs due to clay removal on all roofs. Because the amount of surface to be repaired is unknown, The possible concrete repair on the clay roofs surface must be estimated and considered as part of the cost presented on the proposal or through an allowance?

Assume 15% of surface to be patched. Note that it appears that the only tiles secured to concrete at Main and Lower Spanish tile is at the ridge, hip lines & Eave perimeters. with mortar. This also occurs at the top of the Lantern at the Curbs around the flat copper roof.

Most Spanish tiles are set with Foam Adhesive and removal of this tile does not envision damage to the surface concrete. GC will use methods suitable for the careful removal of tiles. Note that the longer tapered barrel type Cubana tiles at the Shed and Lantern roofs are also set in mortar on top of a sloped concrete roof slab. Here these tiles are being replaced 100% with new. The contractor can assume 40% patching of this surface if needed.

26. In order to comply with Drawing AD-101 Demolition Note #1 indicates: “Assume a minimum of 50% of existing tiles to be salvaged.” and the new attachment format for Spanish Tiles described in Drawing A-525

Are the existing tiles suitable to receive the new attachment format? In case of not, is allowed to consider replacing 100% of tiles to comply with the new attachment format?

This project does not look to provide 100% all new tiles for Spanish “S” type. Existing tiles on the roof have been observed with a corner hole for attachment, it may be possible not every tile has this hole which shall be covered under the Contractors cost. Contractor shall consider the cost to drill holes into existing tiles that may be missing an attachment hole. Assume 30% of the 50% to be reused are missing holes and may require drilling.

27. In Drawing A-202 Keynote #9 indicates: Remove plant growth from exterior finish

Where is it? The drawing does not have specified the location of mentioned keynote.

See elevation A-201, Entry in the middle of the building. On North façade around Stone eagle.

28. In Drawing A-203 Keynote #12 indicates: Replace Anti-Bird netting from eave above to roof below.

Do you have any specification/ requirement of the material mentioned?

Yes. Refer to the attached specification, Section 108113, Bird Control Devices.

29. In Drawing A-201 Keynote #11 indicates Patch Damaged Concrete/Plaster Finish

The mentioned repairs must be estimated and considered as part of the cost presented on the proposal or through an allowance?

The repair of the portion/s indicated on the plans and elevations should be shown on the proposal since they are visible and exposed to view. Patching of unforeseen or unknown should be considered by the Contractors in their proposal.

30. In Drawing A-525 identify a nailable concrete slab under existing roof membrane

How we will proceed is there no nailable concrete slab under the existing roofing membrane?

The existing drawings indicate a nailable concrete, there is no reason to believe that it is not as shown on Drawing A-525. Note that the term nailable does not mean that only nails can be used. Note that concrete screws or specific shanked nails may be required by Tile manufacturer. Refer to clay tile specifications.

31. Due pull test would be required to roof tiles install? If so, How many?

One Pull test per 1,000 SF of roofing. The general contractor will consider this cost in the proposal.

32. Membrane installation will only be torched, or other methods will be allowed?

Refer to Specification 075216 for installation of roofing instructions

33. Will there be a staging area provided?

Due to space limitations a small space to storage material will be provided in the basement to the General Contractor. If desired, the space could be used as a fabrication shop (hot work not allowed) or staging area. No additional space will be provided.

34. For safety, it will be required to provide tunnels in Sidewalks next to the project?

Drw G-002. General Notes #16 Contractor to provide sidewalk bridging at all exterior paved areas where work is to be performed on building or roof, Contractor to maintain lighting at sidewalk bridging for duration of construction.

35. Could you please clarify on Page 11 of the Solicitation No.47PC0620R0001 if new PPQs on the GSA form must be submitted or if existing PPQs are acceptable? If existing PPQs are acceptable, does it have to be on a GSA form? The specific confusion is around the two sentences below.

Offerors may resubmit questionnaires previously submitted with other proposals or may obtain an updated/new PPQ from a client for any submission. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs.

Existing PPQs, not on the GSA form, are acceptable as long as all the evaluation factors on the GSA template are included in the questionnaire. Offerors shall include the complete PPQ, not just citation or reference the rating/evaluation received on that particular experience.

36. Will the contractor have the opportunity to visit the building next week after coordinating with the facilities manager or owner? If so, please send contact information.

No. A pre proposal conference including a site visit was scheduled. No additional site visits will be coordinated.

37. Does the building management has any current maintenance contract for the HVAC system? This is with the purpose of requesting price to the maintenance contractor.

Yes. O&M Contractor is DL Facilities Support Services.

38. Please provide the brand and model of the existing generator.

The building has two generators:

1) Kohler 1250REOZM, 1,676 hp

2) Katolight D350FRZ4, 535 hp

39. Please indicate if the project includes construction permits, municipal taxes and patents.

The Contractor shall consider all cost for permits, state taxes, municipal taxes and patents.

40. Is it necessary to provide temporary facilities for the inspector or government representatives?

No.

41. Reuse of 50% of the existing tiles would mean that there will be a color difference with the new ones. Please, kindly explain how this was considered.

All Clay tiles have subtle variations from palette to palette and mixing/blending within new tiles is required as well as mixing old and new tiles is required to provide a uniform look.

42. Please provide details and Specs of the new expansion joint for the generator room.

Expansion joint at Generator Roof is shown on 5/A531. This is a custom item. Similar to Roof to Wall expansion joint SPF 4 in NRCA roofing manual . Fasteners 12” on center.

43. Which is the existing roof sealing system to be removed?

The tower roof level and the Generator roof needs to be removed.

44. Is there any access from inside the building to transport materials to the work area?

No.

45. The painting is for the entire building exterior? Is part of the project to paint the building exterior?

The exterior painting is not for the entire building. Paint areas where work is performed to match adjacent color. Match in field.

46. We don't have make or model of the expansion joint illustrated in the drawing (for example the one as detail 2/A531).

This is the Loading Dock Canopy. Replace existing with Expando Flash by JohnsManville.

4” 16 OZ copper. Cant to Wall type.

https://www.jm.com/content/dam/jm/global/en/commercial-roofing/Data%20sheets/Special ty%20Roofing%20Products/RS-6016_ExpandOFlashExpansionJointCover.pdf

47. There are no details of the chiller removal works.

This is means and methods of the Contractor

48. Please provide an AS Built for the chillers.

Not available at the moment.

49. Is it up to the Contractor to remove the Chillers or GSA requires that they shall be moved to install the roof sealing? We understand it can be performed without moving the chillers.

This is means and methods of the Contractor.

50. Who pays the municipalities (arbitrios)?

The General Contractor is responsible to pay municipalities taxes and patents.

https://www.jm.com/content/dam/jm/global/en/commercial-roofing/Data%20sheets/Specialty%20Roofing%20Products/RS-6016_ExpandOFlashExpansionJointCover.pdf https://www.jm.com/content/dam/jm/global/en/commercial-roofing/Data%20sheets/Specialty%20Roofing%20Products/RS-6016_ExpandOFlashExpansionJointCover.pdf

51. The contractor would have access to the maintenance/service elevator?

There is an upcoming elevators project, so access will be subject to availability.

52. Which floors reaches the maintenance/service elevator?

Freight elevators are not available. Only passenger elevators and they reach the fifth floor.

53. We have very experienced and skilled tile installers but not currently certified by Ludowici. Would a person like this skilled and experienced tile installer be accepted for the tiles installation in compliance with the Specs requirements?

The installers would need to be certified by the manufacturer.

54. If the project is mostly roof repairs related, why it was classified with a NAICS Code for General Construction? When looking at a past performance of a Contractor how this will be considered if a contractor's expertise and main past performance is in Roofing not in Commercial and Institutional Building Construction.

The scope of the project is a combination of roofing, electrical and other general construction work. In regards to past performance, the Contractor shall present experiences and past performance based on similar scopes of work and in accordance with the evaluation factors stated in the Solicitation.