Hartford First Proprietary Meeting GSA Slides.pdf

PDF 2 MB Posted

Attached to
Request for Qualifications (RFQ) for Design-Build Services for a New United States Courthouse in Hartford, CT
Solicitation number
47PC0325R0013
Issued by

About this file

This is a Phase I Proprietary Meeting presentation for the New U.S. Courthouse Design-Build Services project in Hartford, Connecticut. The General Services Administration (GSA) is seeking a design-build contractor to develop a new federal courthouse with a maximum total area of 281,000 gross square feet on a 2.19-acre parcel. The project will accommodate up to eleven courtrooms, eighteen chambers, and multiple federal agencies including the U.S. District Court, U.S. Bankruptcy Court, U.S. Probation and Pretrial Services, and others.

The project has a design-build to budget value of $292 million, with a 48-month performance period spanning from September 2025 to August 2030. Key procurement milestones include Phase 1 Proposals due November 5, 2025, a short list issued December 12, 2025, and notification of award in August 2026. The solicitation (No. 47PC0325R0013) will follow a two-phase selection process, with the government seeking contractor input on scope, schedule, budget, and potential betterments and reductions. The project also must adhere to Executive Order 14344 on federal architectural design and will utilize Project Labor Agreements.

View the file

Other files

File Type Posted
Environmental Review and Status Report prepared by GeoQuest Inc dated June 2019.pdf PDF
Phase 2 Site Investigation Draft prepared by BL dated January 2018.pdf PDF
GSA Hartford New Federal Courthouse Solicitation Amendment 2.pdf PDF
Preliminary Geotechnical Considerations prepared by GEI Consultants dated June 2024.pdf PDF
Utility Assessment Report prepared by Fuss ONeill August 2024.pdf PDF
Pre-Site Analysis Report II_Michael Maltzan Architecture.pdf PDF
Results of Environmental Soil Pre Characterization Sampling.pdf PDF
Phase 1 Environmental Site Assessment prepared by BL Companies December 2018.pdf PDF
Allyn Street Data Gap Review prepared by Solve March 2024.pdf PDF
Allyn St. Site Plan, prepared by Close Jensen & Miller, April 1991.pdf PDF
Phase II III Site Investigation prepared by BL April 2019.pdf PDF
Results of Environmental Soil Pre-Characterization Sampling.pdf PDF
Phase I ESA Hartford New Courthouse - Allyn Site.pdf PDF
Draft Phase 2 Submission Requirements.pdf PDF
GSA New Federal Courthouse RFI Log Template.xlsx XLSX spreadsheet
GSA Hartford New Federal Courthouse Solicitation Amendment 1.pdf PDF
Draft Final Site Civil Report.pdf PDF
Hartford_Courthouse Tours Report - Edition II.pdf PDF
GSA Hartford Courthouse Project - RFI Template for Offerors .xlsx XLSX spreadsheet
Hartford USCH DRAFT DB SOW .pdf PDF
Hartford Site Feasibility Report_DRAFT.pdf PDF
Hartford Federal Courthouse Prelim Geo Rpt (GEI 09 15 25).pdf PDF
Hartford DB Agreement DRAFT document.pdf PDF
Proprietary Information Agreement - Sample Template .docx DOCX document
Hartford Small Business Participation Commitment Document (SBPCD) Template.docx DOCX document
DRAFT Hartford SF 1442.pdf PDF
Hartford Reps and Certs GC MAY 2025.docx DOCX document
Hartford POR Parts 1 2 DRAFT.pdf PDF
Solicitation Phase 1 RFQ Design Build New US Courthouse Hartford CT.pdf PDF
Past Performance Questionnaire Hartford.docx DOCX document
GSA Hartford Courthouse Project - Pricing Template - 2025-08-29.xlsx XLSX spreadsheet
Hartford_POR - Appendix A _DRAFT.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Welcome PageNew U.S. Courthouse - Hartford, CT Design-Build Services

Phase I Proprietary Meeting

Project Team

Agenda

● Government Introductions & Opening Remarks

● DBC Team Introductions & Opening Remarks

● Project Overview

● Q&A and Open Discussion

● Next Steps & Follow-up Actions

GSA Solicitation No. 47PC0325R0013 U.S. General Services Administration

Agenda

GSA Solicitation No. 47PC0325R0013 U.S. General Services Administration

What this Proprietary Meeting IS:

● Opportunity to meet the Government team

● Discuss the draft Scope of Work (SOW) and draft Program of

Requirements (POR) for the project; and gather contractor feedback on its clarity, completeness, and feasibility.

● Solicit contractor input and suggestions for improving the SOW, POR or the overall project approach.

● Establish a shared understanding of the complexities of design-build to budget projects and gather insights on potential challenges and solutions.

● Seek preliminary feedback to confirm the schedule and budget are achievable

Agenda

GSA Solicitation No. 47PC0325R0013 U.S. General Services Administration

What this Proprietary Meeting ISN’T:

● Not part of the official evaluation

● Does not count for or against Offerors

● Is not official response to questions, Offerors should still submit formal

Request for Information (RFIs) to the Source Selection Authority (SSA) and Contracting Officer (CO)

Douglas Tumbrello douglas.tumbrello@gsa.gov

Project Team & Introductions

GSA Solicitation No. 47PC0325R0013 U.S. General Services Administration

Project Overview

The U.S. General Services Administration (GSA), Public Buildings Service (PBS) is seeking a highly qualified Design-Build Firm to provide comprehensive site development, design and construction services for a new U.S. Courthouse in Hartford, CT:

● maximum total area not to exceed 281,000 GSF

● 2.19 acre parcel located at 180 Allyn Street in Hartford.

● up to eleven (11) total courtrooms,

● up to eighteen (18) separate chambers

● Tenants: U.S. District Court, U.S. Bankruptcy Court, U.S. District Clerk, U.S. Bankruptcy Clerk, U.S. Probation and Pretrial Services Offices, Circuit Library, Federal Public Defender, U.S. Department of Justice - Attorney’s Office, GSA, and the U.S. Marshals Service.

● Executive Order 14344, Making Federal Architecture Beautiful Again.

Schedule Overview

Design Build Solicitation

September

Design Build Award

August

Construction Begins

July

Substantial Completion

August

48 month Period of Performance

Key Budget Considerations

● Design-Build to Budget Value: $292m

○ Contract Option: Site Remediation

● Unit Cost for Additional Soil Removal

● Betterments and Reductions to Optimize Budget

Value. Available in the draft D/B SOW

● Award based on best value

Original POR

279,750 SF

POR Priorities

201,383 SF

1. DELETE all COA Chamber Suites

2. DELETE 1 Magistrate, 1 District , 1 Sr.

District Chamber Suite

3. CONVERT 40 secure structured parking spaces to surface parking

4. DELETE 2 District Courtrooms

5. DELETE 5 Trial Jury Suites (3 District, 1 Sr. District, 1 Magistrate)

6. SHARE District + Magistrate Court Support Spaces (equipment storage, AV)

7. REDUCE Jury Assembly to 150 person capacity

8. DELETE News Media Room (5.103) and Fitness Center (5.107)

9. DELETE NSF for Shared Training Suite from District Clerk, Bankruptcy Clerk and Probation

10. REDUCE Federal Defender Trial Prep Space (8.100) by 50 NSF

11. REDUCE Circuit Library (12.000) space by 940 GSF

12. REDUCE Joint Use (14.100) by 455 GSF, U.S. Attorney Office Trial Prep (14.200) by 720 GSF,

13. DELETE Congress (14.300) and Trustees (14.400)

14. DELETE Robing Rooms

15. REDUCE Mailroom (14.101) by 380 NSF

POR - Max-Min Program of Requirements

POR Priorities (Min Program Area)

Original POR (Max Program Area)

201,383279,749

Betterments: Level 1

Betterments: Level 2

Reductions: Level 1

Reductions: Level 2

Supplemental Resources

Courthouse Tours Report Space Program Validation & Planning Report I

Pre-Site Analysis Report I

Other Key Considerations

Other Key Considerations:

Executive Order 14344

Making Federal Architecture Beautiful Again

Project Labor Agreements

FAR Subpart 522.5 - Use of Project Labor Agreements for Federal Construction Projects

Q&A - Open Discussion

● Scope, Schedule, and Budget

● Statement of Work

● Specifications & Deliverables

● Risk Identification & Mitigation

● Betterments & Reductions/Alterations to Scope

● Unique Challenges & Opportunities

Next Steps & Follow Up Actions

● Check SAM.gov for details and updates

● Submit Formal RFIs

● Phase 1 Proposals Due: Nov 5, 2025 4:00 PM EST

● Short List Issued: Dec 12, 2025

● Phase 2 Proprietary Meetings: February and March

● Notification of Award: August 2026

Source Selection Authority (SSA) and Contracting Officer (CO) Douglas Tumbrello douglas.tumbrello@gsa.gov http://sam.gov

Welcome Page