Amendment 1 - RFI Answers.pdf
PDF 266 KB Posted
- Attached to
- Jacob Javits Federal Building Service Elevators Modernization Services Federal contract opportunity
- Solicitation number
- 47PC0220R0010
About this file
This document provides answers to questions received in response to a solicitation for the modernization of two service elevators in a federal building located at 26 Federal Plaza in New York, New York. The General Services Administration is seeking a contractor to provide design-build services, which will include developing elevator modernization concepts and preliminary drawings at the 30% design stage for agency feedback. The selected contractor will be responsible for upgrading and refurbishing elevator components as needed, including thoroughly cleaning and repainting reused parts to provide a new finish. There are no specific cab design requirements provided, though the new appearance should be similar to existing and meet functionality objectives outlined in attachments. The contractor must also acknowledge receipt of this amendment answering questions when submitting its proposal in response to solicitation number 47PC0220R0010.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSA Northeast and Caribbean Region
U.S. General Service Administration 1 World Trade Center 55th Floor, Room 5509 New York, NY 10007 www.gsa.gov
June 9, 2020
RFP: 47PC0220R0010
Amendment 1 – RFI Answers
Jacob Javits Federal Building Service Elevators Modernization Service 26 Federal Plaza, New York, NY 10278
To All Prospective Offerors:
This document provides the answers to the requested information. Please review and view the one additional attachment (Model Subcontracting Plan).
The RFI Questions and Answers are as follows:
1. Is there an actual cab design or are we to estimate to match the existing freight type design?
ANSWER: There is no actual cab design. As part of design development (30% submission), the contractor will be responsible to provide elevator modernization approach and features, upgrade concepts, design renderings, material samples, and preliminary drawings such that the GSA can provide feedback and concurrence with the contractor’s approach prior to subsequent design submissions (75%, 90% & Final Construction Set) and construction. Also, refer to Attachment 3 and P100 for general requirements which may affect cab functionality and design to include but not limited to wall protection pads, lighting and signage. At a minimum, new cab appearance shall be similar to existing cab, and cab functionality shall meet the objectives of the SOW.
2. Are we required to paint all existing hatch door entrances and hatch doors (Painting and finishing of the hoistway entrances and doors mentioned in the Painting and Finishing section of Attachment #3)?
ANSWER: In accordance with the SOW "Equipment identified by the GSA to be reused shall be refurbished, patched, repaired, modified and/or adjusted to meet the intent of the modernization.
Reused components shall be thoroughly cleaned and repainted as needed to provide a new finish."
Please acknowledge this amendment when submitting your proposal.
Sincerely, Sung Yoo
Sung Yoo Acquisition Management Division (2PQA) Public Buildings Service