This is an Expedited Settlement Agreement (ESA) cover letter from the U.S. Environmental Protection Agency (EPA) Region 10 to the City of Seaside regarding compliance violations at the City of Seaside Wastewater Treatment Plant in Seaside, Oregon. The EPA conducted a desk audit on March 4, 2024, to review the facility's compliance with its National Pollutant Discharge Elimination System (NPDES) permit number OR002040 (issued December 8, 2018) and the Clean Water Act. The audit identified violations through review of discharge monitoring reports and other required submissions in the EPA's Integrated Compliance Information System. Rather than pursuing traditional enforcement action, the EPA offers the City of Seaside the opportunity to resolve violations through an expedited settlement process. The City must take corrective action within 30 days of receiving the letter and return a signed ESA to Compliance Enforcement Officer Katrina Chambon either digitally or by certified mail to the EPA Region 10 Anchorage Operations Office. The EPA will provide a 30-day public comment period on the ESA, after which the Regional Judicial Officer will issue a Final Order if no changes are warranted.
The expedited settlement requires the City of Seaside to pay an administrative civil penalty of $3,750, representing a reduced quick settlement amount compared to traditional enforcement proceedings. The City must submit penalty payment and proof of payment within 10 days of receiving the Final Order. The letter was issued on June 7, 2024, and establishes a 30-day response deadline for the City to agree to corrections and return the signed agreement. Copies of the correspondence were sent to the Oregon Department of Environmental Quality, including the Water Quality Division Administrator and related staff.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RETURN RECEIPT REQUESTED
Mr. Walter Mills Acting Wastewater Treatment Plant Foreman City of Seaside 989 Broadway Seaside, Oregon 97138
Re: Expedited Settlement Agreement (ESA) for City of Seaside Wastewater Treatment Plant in
Seaside, Oregon
Dear Mr. Mills:
The U.S. Environmental Protection Agency (EPA) conducted a desk audit for the City of Seaside Wastewater Treatment Plant (“Facility” or “Respondent”) located at Seaside, Oregon on March 4, 2024 for compliance with its National Pollutant Discharge Elimination System (NPDES) permit and the Clean Water Act (CWA). The desk audit reviewed the facilities compliance through EPA's national database, the Integrated Compliance Information System, which contains information regarding discharge monitoring reports (DMRs) and other reports required to be submitted by the Permit. The desk audit and subsequent administrative records review indicated that the City of Seaside violated the December 8, 2018, NPDES permit number OR002040 (“Permit”).
EPA has authority under section 309 of the CWA, 33 U.S.C. § 1319, to take enforcement actions, including seeking civil penalties, for the alleged violations specified in the enclosed Expedited Settlement Offer Worksheet Violation Form (“Violations Form”). At this time, rather than undertake a more traditional enforcement action for civil penalties, EPA is offering the Respondent the opportunity to enter into the enclosed Expedited Settlement Agreement (ESA), provided the Respondent (1) has corrected the deficiencies cited in the Violations Form and (2) agrees to pay the administrative civil penalty in the Violations Form.
EPA encourages the expedited settlement of easily verifiable and correctable violations, such as those identified in the Violations Form. You may therefore choose to resolve the violations identified on this Violations Form quickly, without protracted litigation, by correcting the violations and signing and returning the attached ESA, in which you agree to submit payment for the reduced quick settlement penalty of $3,750. The ESA is issued in accordance with the Consolidated Rules of Practice Governing the Administrative Assessment of Civil Penalties, and the Revocation, Termination or Suspension of Permits at 40 C.F.R. Part 22.
In order to avail yourself of the ESA option, you must take the following steps within 30 days of your receipt of this letter:
REGION 10
SEATTLE, WA 98101
1. Agree to correct all the violations identified in the Violations Form within 30 days of your receipt of this letter or an alternative time frame approved by EPA in writing. Please work with the Compliance Officer listed below to provide documentation of these corrections;
2. Return a digital copy of the signed ESA by email to:
Katrina Chambon, Compliance Enforcement Officer Chambon.Katrina@EPA.gov
If you are unable to email these items, then return the signed original ESA by certified mail to:
Katrina Chambon U.S. Environmental Protection Agency, Region 10 Anchorage Operations Office 222 West 7th Avenue, Suite 19 Room 537 Anchorage, Alaska 99513
EPA will provide an opportunity for public comment on the ESA for 30 days. Assuming no public comments warrant a change to the ESA, EPA would then ask the Regional Judicial Officer to issue a Final Order approving the ESA. Within 10 days of your receipt of the Final Order, you must submit penalty payment in accordance with the instructions in the attached ESA and proof of payment to the Compliance Officer identified above.
We look forward to hearing from you.
Sincerely, Edward J. Kowalski Director Enforcement and Compliance Assurance Division
Enclosures
1. Expedited Settlement Order
2. Expedited Settlement Offer Worksheet Violations Form cc: Ms. Jennifer Wigal Water Quality Division Administrator, Oregon Department of Environmental Quality
Ms. Tiffany Yelton-Bram Water Quality Control Section Manager, Oregon Department of Environmental Quality
Mr. Mike Pinney Environmental Engineer 3, Oregon Department of Environmental Quality
| 2024-06-07T13:39:45-0700 | |
| EDWARD KOWALSKI |
File details come from the government source that posted it. Updated .