4-SLCI27028 Attachment 2 Scope of Work.docx

DOCX document 21 KB Posted

Attached to
Salt Lake City Request for Bid SLCI27028 - Fencing Supplies and Installation
Solicitation number
SLCI27028
Issued by
Salt Lake County, Salt Lake City, Utah

About this file

This Scope of Work document outlines the fencing supplies and installation services required by Salt Lake City Corporation in Utah on an as-needed basis. The contractor shall provide fencing materials available for pickup by City personnel at the contractor's place of business or deliver orders to City departments and locations upon request. The contractor may be required to arrange direct shipment from manufacturers or wholesalers to City-designated sites, with actual shipping charges reimbursed as separate line items. The scope includes fabrication of custom fencing components such as gates and frames within mutually agreed timeframes, with no minimum order requirements. Installation services require the contractor to deliver and provide written cost estimates using bid submittal rates, complete work within agreed timeframes, clear minor vegetation and obstructions, mark underground utilities prior to excavation, and restore job sites to clean and safe conditions upon completion. The contractor must provide specification and design assistance and warrant that all products conform to specified requirements and are of merchantable quality. Additionally, the contractor shall provide temporary chain link fencing services for City events, typically set up the night before and removed immediately following events, with at least one week's advance notice whenever possible.

The contractor warrants that all work products shall remain functional and in good order for a minimum of one year from acceptance date, as verified through a joint walkthrough confirming proper post installation, taut and level fencing, properly functioning gates, and fully restored job sites. The contractor must accept returns of unused non-custom materials with full reimbursement and is responsible for obtaining all required permits prior to project commencement. Final acceptance is granted following the joint walkthrough inspection. The contractor shall submit a comprehensive safety program addressing Utah Occupational Safety and Health Administration, Environmental Protection Agency, National Fire Protection Association, and Utah Department of Transportation regulations, including provisions for employee protection, environmental protection, hazardous materials handling, and subcontractor operations, subject to approval by the City Department's Safety Program Manager prior to notice to proceed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SLCI27028

Attachment No. 2

SCOPE OF WORK

FENCING SUPPLIES AND INSTALLATION

The responsibilities of Contractor include, but shall not be limited to, the following.

A. Contractor shall provide Fencing Supplies and Installation City-wide on an “as needed” basis.

1. Generally, City personnel shall pick up orders for fencing materials that are not to be installed by Contractor’s place of business. When picked up by a City employee, Contractor shall request the employee’s City identification and have the employee print his or her name and sign the invoice for the products received.

2. Contractor shall deliver orders for products stocked locally to City departments or locations upon request.

3. At the request of City, Contractor shall make arrangements to ship products directly from the manufacturer or Contractor’s wholesaler (F.O.B. destination) to a site designated by City, and City shall reimburse Contractor for the actual shipping charges as a separate line item on Contractor’s invoice to City for the applicable product that was shipped.

4. There shall be no minimum order limitations.

B. Fabrication – When necessary, City shall have Contractor fabricate certain fencing components, such as custom gates and frames. Items that need to be fabricated shall be fabricated and shipped, or made available for pick-up if applicable, within a time frame mutually agreed upon by both parties at the time of order.

C. Contractor may be required to submit its company safety program to one of the City Department’s Safety Program Managers addressing specific work activities and associated hazards. The safety program shall be in compliance with Utah Occupational Safety and Health Administration (UOSH) regulations, Environmental Protection Agency (EPA) regulations, National Fire Protection Association (NFPA) regulations, Utah Department of Transportation (UDOT) regulations and any other federal, state, or local regulations. The safety program shall include requirements applicable to the scope of its work, the protection of its employees, employees and owners of buildings and property adjacent to the work area. The safety program shall include the operations of Contractor’s sub-contractors, at any tier, and include environmental protection, safety, occupational health, respiratory protection, hearing conservation, fire prevention protection, and hazardous materials handling requirements as applicable. The safety program documents shall be reviewed and approved by the City Department’s Safety Program Manager prior to notice to proceed.

D. Installation Services:

1. Contractor shall deliver and install all required fencing materials upon request to various sites specified by City, on an as needed basis.

2. Contractor shall provide a written cost estimate using the parts and labor rates stated in their bid submittal.

3. Contractor shall begin installation and shall complete installation within a time frame mutually agreed upon by both parties at the time of order.

4. Contractor shall clear minor vegetation, debris, or obstructions along the designated fence line as needed.

5. Contractor shall mark and identify all underground utilities prior to digging or post excavation.

6. Upon completion of the installation the Contractor shall be responsible for removing all excavation spoils, debris, and leaving the site in a clean and safe condition.

E. Contractor shall provide specification and design assistance.

F. Contractor warrants that products furnished conform to the specified requirements And are of good merchantable quality and suitable for the purpose intended.

G. In the event Contractor is unable to supply a requested product from inventory, Contractor shall make every effort possible to secure the required product from another local source. Contractor may be required to order parts that are not stocked locally from a non-local source.

H. The Contractor shall warrant that work product resulting from its services shall remain functional and in good order for a minimum of one year from the date of acceptance as detailed in paragraph “K” below.

I. Contractor shall accept returns of unused materials, other than custom fabricated components, at City’s request, and shall refund any amounts paid for such returned materials. City shall be responsible for returning the products to Contractor’s place of business with copies of the original material list and the invoice.

J. Contractor shall be responsible for obtaining any/all required permits prior to commencing any project.

K. Final acceptance will be granted following a joint walkthrough by assigned City personnel and the Contractor to verify the following:

1. All posts are secure, plumb, and properly set.

2. Fencing is taut, level, and free of defects or damage.

3. All gates latch and lock properly.

4. The job site is fully restored, cleared of debris, and free of any hazardous conditions.

L. Temporary Fencing:

Upon request, contractor shall provide 6-foot high by 12-foot wide chain link or similar type fencing for various events on a temporary basis. Whereas each event’s requirements shall vary and where there may be more than one event occurring at any given time, Contractor shall be required to set up required chain link fencing the night before an event and remove the chain link fencing immediately following the event. (i.e. for a Saturday event, set up could be anytime between 6:00 PM Friday and 6:00 AM Saturday morning with the fencing removed any time after 11:00 PM Saturday, but before 8:00 AM Sunday morning)

1. City shall endeavor to give Contractor at least one-week prior notice of events requiring temporary fencing services of Contractor. However, there may be events of an unforeseen or emergency nature which preclude such advance notice and Contractor shall extend reasonable effort to accommodate such emergency requests.

2. Amount of temporary fencing material and length of the rental shall be agreed upon by both parties, in writing, prior to set up materials.