4-Attachment B Scope of Work Pioneer Trail Improvement- Scope of Work.docx

DOCX document 26 KB Posted

Attached to
UDOT Region 2 Pioneer Trail Improvements -
Solicitation number
UDOT270027CN -
Issued by
Utah

About this file

This is a Scope of Work document for the Utah Department of Transportation (UDOT) Region 2 Pioneer Trail Improvements project, issued under Solicitation #UDOT270027CN as an Invitation for Bid (IFB). The project involves the removal of existing concrete curb and gutter, pedestrian ramps, and sidewalk, followed by installation of new concrete curb and gutter and pedestrian ramps along Pioneer Trail. A mandatory virtual prebid meeting is scheduled for Wednesday, August 4, 2026, at 10:00 AM Mountain Time via Google Meet, with attendance required for bid eligibility and site visit participation. The meeting will begin promptly, and late arrivals may be prohibited from participating in the site visit and submitting a bid. The project completion deadline is November 20, 2026, and this contract may result in a one-time purchase order award to the lowest responsive and responsible bidder.

The awarded contractor must submit a performance and payment bond upon contract award. This solicitation is issued in accordance with the State of Utah Procurement Code and Utah Administrative Code, with the UDOT Procurement Services Division serving as the issuing unit and Region 2 as the conducting procurement unit. Bidders must reference Solicitation #UDOT270027CN on all bids, correspondence, and documentation submitted to the State. Specific pricing terms, funding sources, and additional project details are contained within the complete solicitation documents provided to interested bidders.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pioneer Trail Improvement Curb Extensions Scope of Work

INSTALLATION, UPGRADE, OR REPAIR OF CONCRETE

The Utah Department of Transportation (UDOT) is requesting your company to submit a detailed estimate for the Pioneer Trail Improvements project as described below.

PROJECT

Concrete Location (Route & Mile Posts)
SR-186 - M.P. 1.64 to M.P 1.96
UDOT Maintenance Station & Contact
Station 2425 (Salt Lake East (Metro))

Robert Giolas (Supervisor) 801.910.2250 rgiolas@utah.gov

INSTRUCTIONS

Date of Request
July 28, 2026
Quote Submission Deadline
2:00 PM on August 12,2026,
Date of Mandatory Site Visit with UDOT Maintenance Representative before Estimate Submission
10:00 AM on August 4, 2026 - Virtual Only

Video call link: https://meet.google.com/tee-dkwh-xto

Anticipated Completion Date for Scope of Work (weather dependent)
November 20, 2026

PROPOSAL

UDOT is seeking a quote to perform concrete, curb and gutter, sidewalk, driveways, & pedestrian ramps, in Salt Lake County. Quote must be submitted as a price per unit of measure. Quantities listed are for estimate purposes only, actual may be more or less and will be determined in the field. Contractor will be paid based on actual quantities placed/performed. Contractor will provide documentation for all items of work prior to receiving payment, including but not limited to: batch tickets, as-builts, and invoices. For project limitations, refer to the Traffic Control and Limitations of Operations section listed below.

SCOPE OF WORK

Contractor will remove existing concrete curb and gutter, pedestrian ramps, and sidewalk at the intersections of Hillside Avenue/State Street, 200 North/State Street, and North Temple/State Street; install concrete curb and gutter, pedestrian ramps (9), and concrete sidewalk; and remove the central island concrete at 300 North/State Street and install concrete curb along the back of the apron. See Table 1 for site locations and general scope. Removed asphalt and concrete will be the property of the contractor and hauled away by the contractor. The contractor is responsible for any damage to items that are to be protected in-place. Contractor must meet all UDOT 2026 Standards, Specifications, and Drawings.

File details come from the government source that posted it. Updated .