This file is a Table of Contents document for the SR-36 Sound Wall Trail project issued by the Stansbury Park Service Agency in Utah. The project encompasses construction and site improvement work including concrete forming and placement, electrical raceway installation, earthwork operations, exterior improvements such as pavement and landscaping, and utility installations. The solicitation follows a formal sealed bid process with bids due on Wednesday, July 29th, 2026 at 4:00 pm at the Service Agency's office located at 1 Country Club Drive, Suite 1, Stansbury Park, Utah. A non-mandatory pre-bid meeting is scheduled for Wednesday, July 15th, 2026 at 3:00 pm at the same location. Prospective bidders may submit questions until July 23rd, 2026 at 4:00 pm to Shawn Chidester at s.chidester@stansburypark.gov.
The contract documents reference both APWA and UDOT technical specifications covering divisions including general requirements, concrete work, electrical systems, earthwork, exterior improvements, and utilities. Specific technical sections address mobilization, site clearing, excavation, riprap installation, shoring, sign placement, base courses, bituminous concrete, curbing, pavement markings, irrigation systems, landscaping, PVC piping, water distribution, and seeding operations. The document structure indicates a comprehensive construction project with detailed specifications and standard contract conditions, change order provisions, bid bonds, and measurement and payment terms.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6-4. Bid Form.docx | DOCX document | |
| 16-14. APWA Inclusion Document.docx | DOCX document | |
| 11-9. Measurement Payment.docx | DOCX document | |
| 7-5. Bid Form (Supplemental).docx | DOCX document | |
| 8-6. Bid Bond .docx | DOCX document | |
| 3-1. Invitation to Bid.docx | DOCX document | |
| 1-SR-36 Sound Wall Trail Full Plans 6.26.26.pdf | ||
| 12-10. Non-Collusion.docx | DOCX document | |
| 2-SR-36 Sound Wall Trail Alternative 250 Trail Section.pdf | ||
| 10-8. Notice to Proceed.docx | DOCX document | |
| 9-7. Form of Agreement .docx | DOCX document | |
| 14-12. General Conditions.docx | DOCX document | |
| 13-11. Change Order .docx | DOCX document | |
| 5-3. Instructions to Bidder.docx | DOCX document | |
| 15-13. Supplementary Conditions.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STANSBURY PARK SERVICE AGENCY
SR-36 Sound Wall Trail
Table of Contents
Section Number Title
BID
| C-100 | Invitation for Bids |
| C-200 | Instructions to Bidders |
| C-410 | Bid Form |
| C-410M | Bid Form Supplemental |
| C-430 | Bid Bond |
| C-450S | Measurement and Payment |
| C-420S | Affidavit of Non-Collusion |
AGREEMENT
| C-520 | Form of Agreement |
| C-550 | Notice to Proceed |
CONDITIONS OF THE CONTRACT
| C-700 | General Conditions |
| C-800S | Supplementary Conditions |
| C-941 | Change Order |
APWA TECHNICAL SPECIFICATIONS
01 10 01 APWA Inclusion Document
DIVISION 01 – GENERAL REQUIREMENTS (INCLUDED BY REFERENCE)
| 01 11 00 | Summary of Work | |
| 01 32 16 | Progress Schedule | |
| 01 43 40 | Resident Superintendent | |
| 01 57 00 | Temporary Controls | |
| 01 71 13 | Mobilization and Demobilization | |
| 01 74 13 | Progress Cleaning | |
| 01 78 50 | Closeout Procedures |
DIVISION 03 – CONCRETE (INCLUDED BY REFERENCE)
| 03 11 00 | Concrete Forming |
| 03 30 04 | Concrete |
| 03 30 10 | Concrete Placement |
DIVISION 26 – ELECTRICAL (INCLUDED BY REFERENCE)
26 05 33 Raceway
DIVISION 31 – EARTH WORK (INCLUDED BY REFERENCE)
| 31 05 13 | Common Fill | |
| 31 05 19 | Geotextiles | |
| 31 11 00 | Site Clearing | |
| 31 23 16 | Excavation | |
| 31 37 00` | Riprap or Rock Lining | |
| 31 41 00 | Shoring |
DIVISION 32 – EXTERIOR IMPROVEMENTS (INCLUDED BY REFERENCE)
| 32 01 05 | Information, Regulatory, and Warning Signs |
| 32 11 23 | Aggregate Base Course |
| 32 12 05 | Bituminous Concrete |
| 32 16 13 | Curb And Gutter |
| 32 17 23 | Pavement Markings |
| 32 84 23 | Underground Irrigation Systems |
| 32 91 19 | Landscape Grading |
| 32 92 00 | Turf and Grass |
DIVISION 33 – UTILITIES (INCLUDED BY REFERENCE)
| 33 05 07 | Polyvinyl Chloride Pipe |
| 33 05 20 | Backfilling Trenches |
| 33 08 00 | Commissioning of Water Utilities |
| 33 11 00 | Water Distribution and Transmission |
| 33 12 16 | Water Valves |
UDOT TECHNICAL SPECIFICATIONS
| 01501 | Mobilization |
| 01571 | Temporary Environmental Controls |
| 01572 | Dust Control and Watering |
| 01741 | Final Cleanup |
| 02056 | Embankment, Borrow, and Backfill |
| 02075 | Geotextiles |
| 02221 | Remove Structure and Obstruction |
| 02231 | Site Clearing and Grubbing |
| 02721 | Untreated Base Course |
| 02741 | Asphalt Mix |
| 02743 | Asphalt Mix for Bike and Pedestrian Paths |
| 02752 | Portland Cement Concrete Pavement |
| 02924 | Seed, Turf Seed, and Turf Sod |
END OF TABLE OF CONTENTS