13-11. Change Order .docx
DOCX document 25 KB Posted
- Solicitation number
- NS26-166
- Issued by
- Tooele County, Utah
About this file
This is a Change Order document related to the Stansbury Park Service Agency's SR-36 Sound Wall Trail project in Utah (Contract NS26-166). The change order modifies the terms and scope of the original contract agreement between the Stansbury Park Service Agency and the contractor. The document outlines specific modifications to the work requirements, deliverables, or project specifications as originally bid. A non-mandatory pre-bid conference was scheduled for Wednesday, July 15th, 2026 at 3:00 pm at the Service Agency's office located at 1 Country Club Drive, Suite 1, Stansbury Park, Utah 84074. Sealed bids for the project were due by Wednesday, July 29th, 2026 at 4:00 pm. Questions regarding the bidding documents could be submitted to Shawn Chidester at s.chidester@stansburypark.gov until the cutoff date of July 23, 2026 at 4:00 pm.
The change order represents a formal modification to the contract terms and likely includes adjustments to project costs, timelines, or scope of work. As a change order document, it would specify the nature of modifications, any associated cost adjustments or credits, revised completion schedules if applicable, and authorization signatures from both the agency and contractor. The specific details of the modifications, pricing impacts, and implementation timeline would be contained within the change order document itself.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6-4. Bid Form.docx | DOCX document | |
| 16-14. APWA Inclusion Document.docx | DOCX document | |
| 11-9. Measurement Payment.docx | DOCX document | |
| 7-5. Bid Form (Supplemental).docx | DOCX document | |
| 8-6. Bid Bond .docx | DOCX document | |
| 3-1. Invitation to Bid.docx | DOCX document | |
| 1-SR-36 Sound Wall Trail Full Plans 6.26.26.pdf | ||
| 12-10. Non-Collusion.docx | DOCX document | |
| 2-SR-36 Sound Wall Trail Alternative 250 Trail Section.pdf | ||
| 10-8. Notice to Proceed.docx | DOCX document | |
| 9-7. Form of Agreement .docx | DOCX document | |
| 14-12. General Conditions.docx | DOCX document | |
| 4-2. Table of Contents.docx | DOCX document | |
| 5-3. Instructions to Bidder.docx | DOCX document | |
| 15-13. Supplementary Conditions.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Change Order No.
Date of Issuance:
Effective Date:
| Project: |
| Owner: |
| Owner’s Contract No.: |
| SR-36 Sound Wall Trail |
| Stansbury Park Service Agency |
| Contract: |
| Date of Contract: |
| Contractor: |
| Engineer’s Project No.: |
The Contract Documents are modified as follows upon execution of this Change Order:
Description:
Attachments (list documents supporting change):
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price:
| Original Contract Times: |
| |_| Working days |
| |_| Calendar days |
Substantial completion (days or date):
Ready for final payment (days or date):
[Increase] [Decrease] from previously approved Change Orders No. to No. :
[Increase] [Decrease] from previously approved Change Orders No. to No. :
Substantial completion (days):
Ready for final payment (days):
Contract Price prior to this Change Order:
Contract Times prior to this Change Order:
Substantial completion (days or date):
Ready for final payment (days or date):
[Increase] [Decrease] of this Change Order:
[Increase] [Decrease] of this Change Order:
Substantial completion (days or date):
Ready for final payment (days or date):
Contract Price incorporating this Change Order:
Contract Times with all approved Change Orders:
Substantial completion (days or date):
Ready for final payment (days or date):
RECOMMENDED:
ACCEPTED:
ACCEPTED:
By:
By:
By:
Engineer (Authorized Signature)
Owner (Authorized Signature)
Contractor (Authorized Signature)
Date:
Date:
Date:
Approved by Funding Agency (if applicable):
Date:
Change Order Instructions
GENERAL INFORMATION
This document was developed to provide a uniform format for handling contract changes that affect Contract Price or Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into a subsequent Change Order if they affect Price or Times.
Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The practice of accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes.
If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be addressed.
For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times, a Field Order should be used.
COMPLETING THE CHANGE ORDER FORM
Project Manager normally initiates the form, including a description of the changes involved and attachments based upon documents and proposals submitted by Contractor, or requests from Owner, or both.
Once Project Manager has completed and signed the form, all copies should be sent to Owner or Contractor for approval, depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated agreement for a previously performed change. After approval by one contracting party, all copies should be sent to the other party for approval. Project Manager should make distribution of executed copies after approval by both parties.
If a change only applies to price or to times, cross out the part of the tabulation that does not apply.
EJCDC No. C-941 (2002 Edition) Page 1 of 2 Prepared by the Engineers’ Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute.
File details come from the government source that posted it. Updated .